PMP Certification Exam Prep Quiz

PMP Certification Exam Prep Quiz

University

23 Qs

quiz-placeholder

Similar activities

การพัฒนาบุคลิกภาพ

การพัฒนาบุคลิกภาพ

University

20 Qs

Job Titles

Job Titles

University

20 Qs

ECCONET RA 9292

ECCONET RA 9292

University

20 Qs

Vocabulary: Housekeeping

Vocabulary: Housekeeping

University - Professional Development

20 Qs

manajemen risiko

manajemen risiko

University

19 Qs

Islamic Digital Economy

Islamic Digital Economy

University

20 Qs

Responsi Peraga Praktikum TPP_Geoslope

Responsi Peraga Praktikum TPP_Geoslope

University

20 Qs

Name The Disney Animation Films

Name The Disney Animation Films

KG - University

20 Qs

PMP Certification Exam Prep Quiz

PMP Certification Exam Prep Quiz

Assessment

Quiz

Professional Development

University

Easy

DOK Level 2: Skill/Concept, DOK Level 1: Recall

Standards-aligned

Created by

Mangaiah Garikapati

Used 4+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

23 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What should a project manager do first when informed that a key stakeholder, James, is dissatisfied with the outcomes of the new software development project?

Meet with the key stakeholder, James, to better understand their concerns

Update the lessons learned documentation with the new information

Present the concerns at the next team meeting to get feedback

Revise the project management plan to address the concerns

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

During project execution, if a key activity will take longer than originally estimated, what should the project manager do first?

Ask the team member to complete the activity as quickly as possible

Determine the impact on project schedule and cost estimates

Report the issue to the project sponsor

Update the risk register with this new risk

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which tool would a project manager use to evaluate the completeness of the project scope statement?

Context diagram

Stakeholder register

Requirements traceability matrix

Risk register

Answer explanation

The requirements traceability matrix tracks requirements through every stage of the project to ensure they are delivered as expected. This helps assess the completeness of the scope statement.

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What should a project manager verify when reviewing the work breakdown structure (WBS) created by the team?

There is at least one work package for each activity

All scheduled work is tied to milestones

Work package estimates are only based on 3-point estimates

No single work package exceeds 80 hours of effort

5.

MULTIPLE SELECT QUESTION

1 min • 1 pt

Before beginning work on a new software feature not included in the original project charter, what all should the project manager do?

Obtain approval for the scope change

Issue a change request

Update the scope management plan

Submit a revised business case

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What technique could help a project manager compress the schedule if the project sponsor requests the project to finish earlier and provides more budget?

Crashing

Resource smoothing

Critical path analysis

Fast tracking

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

As a project manager, you have to balance three elements that compose the project triangle. Suppose your customer requests that you add some new requirements to the project when you are halfway through.


If you agree to this request, how could it affect other aspects of the project?

Project scope will decrease

Cost of the project will increase

Cost of the project will decrease

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?