1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does the term 'Specification' refer to in project management?

C. A standard, rule, or test on which a judgment or decision can be based

A. A detailed description or assessment of requirements, dimensions, materials, etc.

B. The object of one's endeavors; goal; aim.

D. A limitation or restriction

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the main purpose of a Gantt Chart in project management?

A. To create a detailed project budget

B. To identify project risks

D. To define project objectives

C. To visualize project timeline and track progress

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is NOT considered a common project constraint?

C. Quality

B. Scope

D. Resources

A. Time

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary goal of the project execution phase in project management?

C. Executing the baseline project plan

D. Creating a statement of work

B. Identifying project standards and procedures

A. Developing a preliminary schedule

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the purpose of a Work Breakdown Structure (WBS) in project management?

D. To conduct post project reviews

A. To define the scope of the project and break the work down into components

B. To monitor project progress against the baseline project plan

C. To identify potential sources of risk in the project

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What are the characteristics of a project according to the text?

A. Has a beginning and end date, is ongoing, has no specific goal

C. Has a beginning and end date, is temporary, has a specific goal in mind

B. Is temporary, has a specific goal in mind, has no project phases

D. Is ongoing, has no specific goal, has no project phases

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the main focus of the project planning phase in project management?

A. Executing the baseline project plan

B. Determining project standards and procedures

C. Describing project scope, alternatives, and feasibility

D. Closing down the project

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?