Cost Modelling

Cost Modelling

University

12 Qs

quiz-placeholder

Similar activities

Accounting Concept

Accounting Concept

University

10 Qs

IET2213 WME-CLO1_Set1

IET2213 WME-CLO1_Set1

University

10 Qs

cost accounting

cost accounting

University

11 Qs

Accounting 2-Chapter 6 Depreciation of L-T Assets

Accounting 2-Chapter 6 Depreciation of L-T Assets

11th Grade - University

15 Qs

Introduction to IBS

Introduction to IBS

University

16 Qs

TOPIC 1- COST PLANNING

TOPIC 1- COST PLANNING

University

10 Qs

Mixed  Arki SPP No.2

Mixed Arki SPP No.2

University

15 Qs

PRELIMINARY ESTIMATING METHOD

PRELIMINARY ESTIMATING METHOD

University

15 Qs

Cost Modelling

Cost Modelling

Assessment

Quiz

Other

University

Hard

Created by

DR IDA

Used 2+ times

FREE Resource

12 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Which of the below are NOT Single Rate , Traditional Cost Models.

Functional Unit

Storey Enclosure

Elemental Method

Square Metre

2.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

What is the primary purpose of the Functional Unit or unit method in cost estimation?

To provide a detailed breakdown of construction costs

To express costs based on specific functional units relevant to the project type

To estimate costs based on the total floor area of a building

To calculate costs per hour of labor

3.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

What is the method of measurement used in the Functional Unit or unit method?

By dividing the total project cost by the number of units provided

By multiplying the total project cost by the number of units

By subtracting the number of units from the total project cost

By adding the number of units to the total project cost

4.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

What is the primary purpose of the Square Metre Method in construction cost estimation?

To calculate the total volume of a building

To estimate the number of rooms in a building

To determine the height of each floor in a building

To measure the total floor area of a building and compare it with previous rates

5.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

What type of data is required for the Square Metre Method?

Cost per cubic meter of completed buildings

Details about the building's location

Outline or sketch plan of the proposed building

Historical weather data for the construction site

6.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

What is a disadvantage of the Square Metre Method?

It is too complex for quick estimates

It does not consider floor-to-ceiling height variations

It provides precise cost estimates without any approximation

It does not require drawings or specifications for calculations

7.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Cubic Method is primarily used for:

Measuring the length and width of each part of the building

Estimating the floor area of a proposed building

Calculating the volume of the building and applying a cost per cubic meter

Analyzing the structural form of the building

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?