Which of the below are NOT Single Rate , Traditional Cost Models.

Cost Modelling

Quiz
•
Other
•
University
•
Hard
DR IDA
Used 2+ times
FREE Resource
12 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Functional Unit
Storey Enclosure
Elemental Method
Square Metre
2.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
What is the primary purpose of the Functional Unit or unit method in cost estimation?
To provide a detailed breakdown of construction costs
To express costs based on specific functional units relevant to the project type
To estimate costs based on the total floor area of a building
To calculate costs per hour of labor
3.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
What is the method of measurement used in the Functional Unit or unit method?
By dividing the total project cost by the number of units provided
By multiplying the total project cost by the number of units
By subtracting the number of units from the total project cost
By adding the number of units to the total project cost
4.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
What is the primary purpose of the Square Metre Method in construction cost estimation?
To calculate the total volume of a building
To estimate the number of rooms in a building
To determine the height of each floor in a building
To measure the total floor area of a building and compare it with previous rates
5.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
What type of data is required for the Square Metre Method?
Cost per cubic meter of completed buildings
Details about the building's location
Outline or sketch plan of the proposed building
Historical weather data for the construction site
6.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
What is a disadvantage of the Square Metre Method?
It is too complex for quick estimates
It does not consider floor-to-ceiling height variations
It provides precise cost estimates without any approximation
It does not require drawings or specifications for calculations
7.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Cubic Method is primarily used for:
Measuring the length and width of each part of the building
Estimating the floor area of a proposed building
Calculating the volume of the building and applying a cost per cubic meter
Analyzing the structural form of the building
Create a free account and access millions of resources
Similar Resources on Quizizz
10 questions
BASIC OF CASH AND ACCRUAL ACCOUNTING

Quiz
•
University
15 questions
PERFORMANCE APPRAISAL

Quiz
•
University
15 questions
Accounting Basics

Quiz
•
University
10 questions
Environmental Economics Quiz CBA & Valuation

Quiz
•
University
10 questions
Estimating 2

Quiz
•
University
15 questions
PRELIMINARY ESTIMATING METHOD

Quiz
•
University
16 questions
Cost Estimating Theory

Quiz
•
12th Grade - University
15 questions
QUIZ 2 - CHAPTER 8 & 9

Quiz
•
12th Grade - University
Popular Resources on Quizizz
15 questions
Character Analysis

Quiz
•
4th Grade
17 questions
Chapter 12 - Doing the Right Thing

Quiz
•
9th - 12th Grade
10 questions
American Flag

Quiz
•
1st - 2nd Grade
20 questions
Reading Comprehension

Quiz
•
5th Grade
30 questions
Linear Inequalities

Quiz
•
9th - 12th Grade
20 questions
Types of Credit

Quiz
•
9th - 12th Grade
18 questions
Full S.T.E.A.M. Ahead Summer Academy Pre-Test 24-25

Quiz
•
5th Grade
14 questions
Misplaced and Dangling Modifiers

Quiz
•
6th - 8th Grade