Cost Modelling

Quiz
•
Other
•
University
•
Hard
DR IDA
Used 2+ times
FREE Resource
12 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Which of the below are NOT Single Rate , Traditional Cost Models.
Functional Unit
Storey Enclosure
Elemental Method
Square Metre
2.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
What is the primary purpose of the Functional Unit or unit method in cost estimation?
To provide a detailed breakdown of construction costs
To express costs based on specific functional units relevant to the project type
To estimate costs based on the total floor area of a building
To calculate costs per hour of labor
3.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
What is the method of measurement used in the Functional Unit or unit method?
By dividing the total project cost by the number of units provided
By multiplying the total project cost by the number of units
By subtracting the number of units from the total project cost
By adding the number of units to the total project cost
4.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
What is the primary purpose of the Square Metre Method in construction cost estimation?
To calculate the total volume of a building
To estimate the number of rooms in a building
To determine the height of each floor in a building
To measure the total floor area of a building and compare it with previous rates
5.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
What type of data is required for the Square Metre Method?
Cost per cubic meter of completed buildings
Details about the building's location
Outline or sketch plan of the proposed building
Historical weather data for the construction site
6.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
What is a disadvantage of the Square Metre Method?
It is too complex for quick estimates
It does not consider floor-to-ceiling height variations
It provides precise cost estimates without any approximation
It does not require drawings or specifications for calculations
7.
MULTIPLE CHOICE QUESTION
45 sec • 1 pt
Cubic Method is primarily used for:
Measuring the length and width of each part of the building
Estimating the floor area of a proposed building
Calculating the volume of the building and applying a cost per cubic meter
Analyzing the structural form of the building
Create a free account and access millions of resources
Similar Resources on Wayground
13 questions
CMA I - Budgeting

Quiz
•
University
10 questions
OSCM 306 Quiz 3 2nd

Quiz
•
University
10 questions
Weighted Average Cost

Quiz
•
University
12 questions
CMA I - Intro & Cost Classification

Quiz
•
University
10 questions
PAS 2 Inventory - Cost of Inventories and Cost Formulas

Quiz
•
University
15 questions
Marginal Costing

Quiz
•
University
10 questions
Quiz on ch. 1

Quiz
•
University
10 questions
Marketing Management Quiz 2

Quiz
•
University
Popular Resources on Wayground
50 questions
Trivia 7/25

Quiz
•
12th Grade
11 questions
Standard Response Protocol

Quiz
•
6th - 8th Grade
11 questions
Negative Exponents

Quiz
•
7th - 8th Grade
12 questions
Exponent Expressions

Quiz
•
6th Grade
4 questions
Exit Ticket 7/29

Quiz
•
8th Grade
20 questions
Subject-Verb Agreement

Quiz
•
9th Grade
20 questions
One Step Equations All Operations

Quiz
•
6th - 7th Grade
18 questions
"A Quilt of a Country"

Quiz
•
9th Grade