A project manager calls a meeting to identify risks for a complicated project. Several subject matter experts are invited to this meeting along with the project team.
Why has the project manager invited the subject matter experts?
PMI-SH Assess and Manage Risks
Quiz
•
Professional Development
•
1st Grade
•
Hard
sudiyuwono wowo
Used 1+ times
FREE Resource
11 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager calls a meeting to identify risks for a complicated project. Several subject matter experts are invited to this meeting along with the project team.
Why has the project manager invited the subject matter experts?
Subject matter experts have specialized expertise and can help identify and address high-risk issues.
Identifying risks in a meeting with subject matter experts makes getting better project resources easier.
Risks will be easier to accept if the subject matter experts who attended the meeting work together.
The project manager can leverage subject matter experts' resources to follow up on the identified risks.
Answer explanation
A. Subject matter experts have specialized expertise and can help identify and address high-risk issues.
Subject matter experts are invited to the meeting because they provide functional expertise that will help to quickly identify high-risk areas. Expert judgment is the contribution provided to risk identification based on expertise in a subject area, industry segment, organizational processes, etc.
The other answer choices are incorrect because the meeting was called to identify risks, not what may happen after the risk has been identified. When subject matter experts assist in identifying risks, they do not typically provide resources beyond their expertise. The participation of subject matter experts does not necessarily make risks easier to accept nor does it ensure that better resources will be secured.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The opening of a new overseas office faces potential delays as the required permit has not yet been issued by the local government. The project team met to evaluate the appropriate course of action as outlined in the risk register. After a thorough assessment, the team decided to postpone the opening to another date.
Which document should the project manager use to update the project management plan?
Risk management plan
Risk report
Risk register
Lessons learned register
Answer explanation
In this scenario, the team identified a risk related to the delay in obtaining the necessary permit, which was already included in the risk register. The team assessed the response to take, which was to postpone the opening to another date. Therefore, the project manager should update the risk register to reflect the new status of the risk and update the project management plan accordingly.
The other options are incorrect.
The risk management plan describes how risk management activities will be structured and performed.
A risk report summarizes information on individual project risks and the level of overall project risk.
A lessons learned register records knowledge gained during a project but is not intended for documenting real-time risk management decisions.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During an important project, one of the contractors complains that the approval process is difficult to handle and may delay the project schedule.
What should the project manager do first?
Hire additional resources for the team to mitigate this risk.
Discuss with the team to find options to mitigate the risk.
C.Escalate the risk to upper management as critical for timely delivery.
Add the risk to the risk register to be monitored and reviewed.
Answer explanation
The project manager should immediately record the risk in the risk register.
After that, the project manager can discuss with the team to determine solutions to mitigate the risk.
Hiring additional resources for the team could potentially increase the project cost, and escalating the risk to upper management should be done only after the project manager and team fail to find a mitigating solution.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During the development phase of a construction project, key stakeholders approved a project budget. The team identified risks and appropriate risk responses. However, during project execution, an unexpected local health emergency halted and delayed work on the project. This event type was not identified as a risk or listed in the risk register. The team decides that this issue must be mitigated, which would incur additional costs.
How should the project manager address this unforeseen budgetary overrun?
Use the management reserve to cover the cost.
Identify potential ways to exploit the risk.
Use the contingency reserve to cover the cost.
Develop cost and performance baselines.
Answer explanation
The correct answer is to use the management reserve to cover the cost.
Since the health emergency was unforeseen, the management reserve would be the appropriate resource to cover the cost or mitigation. A management reserve is the amount of the project budget or project schedule held outside of the performance measurement baseline for management control purposes that is reserved for unforeseen work that is within the project scope.
Risk exploitation addressed opportunities, not threats. Risk exploitation is a response strategy whereby the project team acts to ensure that an opportunity occurs. Further, the question states that the issue must be mitigated, so the risk response has already been determined.
A contingency reserve is the time or money allocated in the schedule or cost baseline for known risks with active response strategies. This option is incorrect because the risk was not known.
The cost baseline is the approved version of the time-phased project budget, excluding any management reserves, which can be changed only through formal change control procedures and is used as a basis for comparison to actual results.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project is in the execution phase, and product testing is almost complete. A team member proposes that the testing can be fast-tracked by removing some of the tests. The team member believes this will help to finish the job earlier and give the project more float.
What should the project manager do?
Request more information from the team member.
Reject the team member's proposal.
Discuss this proposal with the project team.
D.Ask the quality manager to consider the proposal.
Answer explanation
Removing certain tests is a risky move, and can't be done just to fast-track the project. The Project Manager should have considered all tests while assigning time for the testing phase. If the project is progressing as per the assigned time, no review of tests is needed, and the proposal should be rejected.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager learns that in-house resources are insufficient to produce a critical component of a deliverable. This poses a significant threat. The quality of the component is integral to the project, and the in-house resources cannot guarantee high-quality output. The project manager decides to outsource the production of the component by contracting a third-party vendor.
Which threat response strategy did the project manager use?
Accept
Mitigate
Enhance
Transfer
Answer explanation
A threat is an event or condition that, if it occurs, has a negative impact on one or more objectives. In threat mitigation, action is taken to reduce the probability of occurrence and/ or impact of a threat. Early mitigation action is often more effective than trying to repair the damage after the threat has occurred. The project manager acted to reduce the probability of the threat associated with the development of a project-critical component.
The other answers are incorrect because they do not align with this situation.
Threat acceptance acknowledges the existence of a threat, but no proactive action is planned.
Enhancement refers to opportunities, not threats. In opportunity enhancement, the project team acts to increase the probability of occurrence or impact of an opportunity.
Escalation is appropriate when the project team or the project sponsor agrees that a threat is outside the scope of the project or that the proposed response would exceed the project manager’s authority.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In an agile development environment, when should a risk analysis be performed?
Before the start of each iteration
After every scrum meeting
In the retrospective meeting
During the daily standup meeting
Answer explanation
The initial iteration would occur after an initial risk analysis, and that process should be repeated after every subsequent iteration. It is necessary to analyze new and existing risks to thoroughly understand their potential impact on project outcomes while preparing for each iteration. An iteration planning meeting is used to clarify the details of the backlog items, acceptance criteria, and work effort required to meet an upcoming iteration commitment.
The other options are incorrect because they are not appropriate times to analyze risks. A daily standup meeting (also referred to as a daily scrum) is a brief collaboration meeting during which the project team reviews its progress from the previous day, declares intentions for the current day, and highlights any obstacles encountered or anticipated. A retrospective meeting in a regularly occurring workshop in which participants explore their work and results to improve both the process and product. These meetings provide an opportunity for the project team to review how it works and to suggest changes to improve processes and efficiency. Retrospectives can be useful for identifying risks.
9 questions
Flash Backyard MY Quiz - Network
Quiz
•
1st - 3rd Grade
11 questions
PMI-ACP (10C)
Quiz
•
1st Grade
7 questions
Roles y Responsabilidades-Scrum
Quiz
•
1st - 3rd Grade
10 questions
Chapt 7
Quiz
•
1st Grade
10 questions
PMP 2017 PEOPLE
Quiz
•
1st - 12th Grade
10 questions
Chapt1
Quiz
•
1st Grade
10 questions
CARMA
Quiz
•
1st - 8th Grade
11 questions
O5A Level 2 Day 2
Quiz
•
1st - 3rd Grade
15 questions
Multiplication Facts
Quiz
•
4th Grade
20 questions
Math Review - Grade 6
Quiz
•
6th Grade
20 questions
math review
Quiz
•
4th Grade
5 questions
capitalization in sentences
Quiz
•
5th - 8th Grade
10 questions
Juneteenth History and Significance
Interactive video
•
5th - 8th Grade
15 questions
Adding and Subtracting Fractions
Quiz
•
5th Grade
10 questions
R2H Day One Internship Expectation Review Guidelines
Quiz
•
Professional Development
12 questions
Dividing Fractions
Quiz
•
6th Grade