__________ is not a project communications management process.
PMP Exam Prep 2024 - Bonus Q&A - Chapter 7 - Project Comm Mngmt

Quiz
•
Professional Development
•
Professional Development
•
Medium

Patrick Pepin
Used 3+ times
FREE Resource
50 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Manage stakeholders
Performance reporting
Information distribution
Conflict resolution
Answer explanation
The correct answer is D.
Communicating is a general management skill that includes conflict management.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project status report is an example of which form of communication?
Formal written communication
Formal verbal communication
Informal written communication
Informal verbal communication
Answer explanation
The correct answer is A.
Information Distribution
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
When is formal written correspondence with the customer required?
When defects are detected
When the customer requests additional work not covered under the contract
When the project has a schedule slippage
When the project has cost overruns
Answer explanation
The correct answer is B.
This is an example of a question in which all the answers are correct. The exam taker has to choose the best answer based on experience and common sense.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The 3 major types of communication are:
Written, verbal and nonverbal
Upward, downward and lateral
Written, verbal and graphic
Written, verbal and electronic
Answer explanation
The correct answer is A.
Executing, see Verma, pages 18 to 21
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
All of the following are true about earned value techniques except:
They allow for an assessment of project performance
They can be done at any level, work element, summary or project
They are techniques to measure performance against the project plan
They should only be done on high-value government projects
Answer explanation
The correct answer is D and all the other answers are true.
Earned value techniques are used to integrate the processes of time, cost, and communication and to measure the performance of the project.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Outputs from performance reporting include all of the following except?
Trend analysis
Forecasts
Performance reports
Change requests
Answer explanation
The correct answer is A.
Trend analysis is a tool, not an output.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
You are a new project manager assigned to a troubled project that is 20% into the planning phase.
What is the first thing you should do?
Hold a status meeting to assess project status
Stop all tasks until a new approved project charter is established
Review the project charter and supporting documents, including the current team status reports
Close the project; it has no chance of succeeding
Answer explanation
The correct answer is C.
Although there is nothing in the PMBOK Guide specifically addressing this issue, this is a good example of the situational question that requires that you understand the purpose and value of a project charter and regular performance reporting
Create a free account and access millions of resources
Similar Resources on Quizizz
47 questions
BT (Mock -2 2023)

Quiz
•
Professional Development
46 questions
AZ400 quiz prelim prep 2

Quiz
•
Professional Development
50 questions
Cuestionario Resumen PMI-CP

Quiz
•
Professional Development
50 questions
National Builder Farmwork 4

Quiz
•
Professional Development
50 questions
Self-Leadership and Management Quiz

Quiz
•
Professional Development
45 questions
FRCP Bootcamp Quiz

Quiz
•
Professional Development
50 questions
JOE 13 Scrum Foundation 1

Quiz
•
Professional Development
47 questions
PEOPLE

Quiz
•
Professional Development
Popular Resources on Quizizz
15 questions
Character Analysis

Quiz
•
4th Grade
17 questions
Chapter 12 - Doing the Right Thing

Quiz
•
9th - 12th Grade
10 questions
American Flag

Quiz
•
1st - 2nd Grade
20 questions
Reading Comprehension

Quiz
•
5th Grade
30 questions
Linear Inequalities

Quiz
•
9th - 12th Grade
20 questions
Types of Credit

Quiz
•
9th - 12th Grade
18 questions
Full S.T.E.A.M. Ahead Summer Academy Pre-Test 24-25

Quiz
•
5th Grade
14 questions
Misplaced and Dangling Modifiers

Quiz
•
6th - 8th Grade