During the team meeting, two of the team members who worked on the same tasks are arguing about who is at fault for the task being late. None of them want to be perceived as the one who caused the delay.
What is the most likely cause of this issue?
PMI SH - Build and Lead a Team (0.5)
Quiz
•
Professional Development
•
1st Grade
•
Hard
sudiyuwono wowo
Used 1+ times
FREE Resource
30 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During the team meeting, two of the team members who worked on the same tasks are arguing about who is at fault for the task being late. None of them want to be perceived as the one who caused the delay.
What is the most likely cause of this issue?
Conflicting Priorities
Unclear Responsibilities
Personal Competition
Personnel Selection
Answer explanation
Solution: B. Unclear Responsibilities
Any of the stated answers COULD be correct. The PM may have specific insight, but lacking that, the most likely culprit is a lack of clarity in responsibilities. If those are clarified, not only will conflict be less likely, but it will become more obvious where the issue lies.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
An organization has decided to implement agile and a project manager with Scrum Master has been selected to coach the project team to understand agile delivery. One of the team members asks the project manager what servant leadership hierarchy means.
How should the project manager respond?
Team members are supposed to serve their manager.
Managers are supposed to serve their team members.
Clients are supposed to serve the team members.
Team Members are supposed to serve their clients.
Answer explanation
Solution: B. Managers are supposed to serve their team members.
Servant leadership is the inverted hierarchy. In Agile, the manager is a leader that serves the team by creating the environment for the team to grow, removing impediments, and facilitating rather than commanding.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which leadership behavior is least likely to boost motivation in an Agile project team?
Instruct the team to immediately use a new productivity tool.
Ask the team to vote if a new work method should be adopted.
Assign individual team members to the tasks in the backlog.
Ask for a volunteer to run a customer satisfaction survey.
Answer explanation
Solution: A. Instruct the team to immediately use a new productivity tool
Instructing or dictating the team immediately to do something is least likely to boost motivation. The principles of servant leadership and the Agile Manifesto recognize that empowerment and autonomy promote individual and team motivation.
Agile Manifesto Principle #5 - Build projects around motivated individuals. The remaining options align with this. Give them the environment and support they need, and trust them to get the job done.
Asking the team to vote about a new work method will also boost motivation.
Asking for a volunteer to run a customer satisfaction survey will also boost motivation.
Assigning individual team members to the tasks in the backlog will also boost motivation.
Allowing the team members to decide what to work on based on prioritized objectives or features will motivate them.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A hybrid project has the following characteristics:
It is in the early stages.
It has a brand new team.
The project manager will be very busy executing other projects during the first two weeks of the project.
During this early stage, how should the project manager develop the new project team?
Ensure the team understands self-organizing principles.
Plan and host several team-building events to normalize the team.
Provide daily project status updates to keep the team informed.
Get to know each team member through one-on-one conversations.
Answer explanation
Solution: A. Ensure the team understands self-organizing principles.
The project manager needs to make sure that the team is capable of working on the project during their absence in the first two weeks of the project. To do so, the project manager should ensure that the team understands self-organizing principles. A self-organizing team is a cross-functional team in which people assume leadership as needed to achieve the team’s objectives. Some projects benefit from decentralized coordination in which project team members self-organize and self-manage. In this case, the project manager can not devote their full attention to managing the team, so the team must understand how to self-organize and self-manage.
The other answer choices are incorrect. Team-building events may be productive, but the project manager will be very busy and not consistently available during the first two weeks. Hosting several team-building events will be a drain on the project manager's bandwidth and may not be possible until after the project manager can focus on the team.
Providing project status updates is incorrect because the project manager will not be consistently available. The team will be working on the project in the project manager's absence, it is more likely that they will provide the manager with status updates.
Having one-on-one conversations may result in deeper relationships but would have to wait until the project manager can focus on the team.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
After success in a particulary challenging project phase, a project manager reassigned a high-performing team member to a more strategic task.
This is an example of what?
Recognition
Risk acceptance
Mentorship
Scope change
Answer explanation
Solution: A. Recognition
Recognition - singles out an individual by recognizing them as worthy of more of the work that satisfies them. In this case, the high-performing team member is recognized for their work and is reassigned to a more strategic task.
Risk Acceptance - There is no identified risk here hence the option is incorrect.
Mentorship- the guidance provided by a mentor, especially an experienced person in a company or educational institution hence not the correct answer.
Scope Change - a scope change comes into effect when there is a significant change that impacts project parameters to a defined, accepted work package or project, hence not the correct answer.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
An organization is developing a new product. What should the project manager of this development do first to improve the success of the project?
Work with the project management office (PMO) to develop a detailed project schedule.
Work with the marketing team to conduct an impact analysis to identify the target market.
Work with the project sponsor to define the project vision and overall initiative.
Work with the stakeholders to identify the appropriate project team members.
Answer explanation
Solution: C. Work with the project sponsor to define the project vision and overall initiative
For project success, it is critical to initially define vision and mission of the overall initiative before even focusing on detailed planning. Impact Analysis, detailed project schedule and identification of project team members will follow once the project vision and overall initiative is defined
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A new graduate recently joined a mature agile R&D team. A mentor, assigned to work with the graduate, is overwhelmed by the extra workload. Team performance and motivation are dropping.
How can the project manager help with this situation?
Maintain a laissez-faire leadership style with the team, but use a transactional style to give firm guidance to the graduate.
Ask the mentor to use a collaborative servant leader approach to perform the usual duties along with the mentor role.
Cancel the mentor plan and focus on keeping the graduate motivated by learning through an intensive immersion.
Ask three more team members to share the mentor role in order to reduce the individual mentor workload by 75%.
Answer explanation
Solution: A. Maintain a laissez-faire leadership style with the team, but use a transactional style to give firm guidance to the graduate
The graduate is in need of authoritative and stable guidelines and positive feedback while the team must not lose their autonomy to maintain motivation.
Collaborative servant leadership approach is used for increasing team gel and motivation
Without mentor it is difficult to learn through an insensitive immersion
Asking three team members to share the mentor role is not an effective way
25 questions
ABC's of BES
Quiz
•
1st - 5th Grade
32 questions
Project Management Part 3
Quiz
•
1st Grade
30 questions
open assessment 3
Quiz
•
1st Grade
25 questions
Agile PM#4 Quiz
Quiz
•
1st Grade
25 questions
DINING
Quiz
•
1st Grade
30 questions
RESIDENTNIVERSARY
Quiz
•
1st - 3rd Grade
25 questions
The Financial Free Zone Law Quiz 3
Quiz
•
KG - Professional Dev...
33 questions
iBPLS: BPBC Learning Assessment
Quiz
•
KG - 5th Grade
15 questions
Multiplication Facts
Quiz
•
4th Grade
20 questions
Math Review - Grade 6
Quiz
•
6th Grade
20 questions
math review
Quiz
•
4th Grade
5 questions
capitalization in sentences
Quiz
•
5th - 8th Grade
10 questions
Juneteenth History and Significance
Interactive video
•
5th - 8th Grade
15 questions
Adding and Subtracting Fractions
Quiz
•
5th Grade
10 questions
R2H Day One Internship Expectation Review Guidelines
Quiz
•
Professional Development
12 questions
Dividing Fractions
Quiz
•
6th Grade