PMI SH - Build and Lead a Team (0.5)

PMI SH - Build and Lead a Team (0.5)

1st Grade

30 Qs

quiz-placeholder

Similar activities

Managment

Managment

1st - 12th Grade

30 Qs

Refresher Service Excellence

Refresher Service Excellence

KG - Professional Development

25 Qs

Quiz8

Quiz8

1st Grade

26 Qs

Agile PM#4 Quiz

Agile PM#4 Quiz

1st Grade

25 Qs

DINING

DINING

1st Grade

25 Qs

PMI SH - Address and Remove Impediments, Obstacles, and Blockers

PMI SH - Address and Remove Impediments, Obstacles, and Blockers

1st - 3rd Grade

28 Qs

ILM Diploma level 5

ILM Diploma level 5

1st - 5th Grade

25 Qs

open assessment 3

open assessment 3

1st Grade

30 Qs

PMI SH - Build and Lead a Team (0.5)

PMI SH - Build and Lead a Team (0.5)

Assessment

Quiz

Professional Development

1st Grade

Hard

Created by

sudiyuwono wowo

Used 1+ times

FREE Resource

30 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During the team meeting, two of the team members who worked on the same tasks are arguing about who is at fault for the task being late. None of them want to be perceived as the one who caused the delay.

What is the most likely cause of this issue?

Conflicting Priorities

Unclear Responsibilities

Personal Competition

Personnel Selection

Answer explanation

Solution: B. Unclear Responsibilities

Any of the stated answers COULD be correct. The PM may have specific insight, but lacking that, the most likely culprit is a lack of clarity in responsibilities. If those are clarified, not only will conflict be less likely, but it will become more obvious where the issue lies.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

An organization has decided to implement agile and a project manager with Scrum Master has been selected to coach the project team to understand agile delivery. One of the team members asks the project manager what servant leadership hierarchy means.

How should the project manager respond?

Team members are supposed to serve their manager.

Managers are supposed to serve their team members.

Clients are supposed to serve the team members.

Team Members are supposed to serve their clients.

Answer explanation

Solution: B. Managers are supposed to serve their team members.

Servant leadership is the inverted hierarchy. In Agile, the manager is a leader that serves the team by creating the environment for the team to grow, removing impediments, and facilitating rather than commanding.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which leadership behavior is least likely to boost motivation in an Agile project team?

Instruct the team to immediately use a new productivity tool.

Ask the team to vote if a new work method should be adopted.

Assign individual team members to the tasks in the backlog.

Ask for a volunteer to run a customer satisfaction survey.

Answer explanation

Solution: A. Instruct the team to immediately use a new productivity tool

Instructing or dictating the team immediately to do something is least likely to boost motivation. The principles of servant leadership and the Agile Manifesto recognize that empowerment and autonomy promote individual and team motivation.

Agile Manifesto Principle #5 - Build projects around motivated individuals. The remaining options align with this. Give them the environment and support they need, and trust them to get the job done.

Asking the team to vote about a new work method will also boost motivation.

Asking for a volunteer to run a customer satisfaction survey will also boost motivation.

Assigning individual team members to the tasks in the backlog will also boost motivation.

Allowing the team members to decide what to work on based on prioritized objectives or features will motivate them.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A hybrid project has the following characteristics:

  • It is in the early stages.

  • It has a brand new team.

  • The project manager will be very busy executing other projects during the first two weeks of the project.

During this early stage, how should the project manager develop the new project team?

Ensure the team understands self-organizing principles.

Plan and host several team-building events to normalize the team.

Provide daily project status updates to keep the team informed.

Get to know each team member through one-on-one conversations.

Answer explanation

Solution: A. Ensure the team understands self-organizing principles.

The project manager needs to make sure that the team is capable of working on the project during their absence in the first two weeks of the project. To do so, the project manager should ensure that the team understands self-organizing principles. A self-organizing team is a cross-functional team in which people assume leadership as needed to achieve the team’s objectives. Some projects benefit from decentralized coordination in which project team members self-organize and self-manage. In this case, the project manager can not devote their full attention to managing the team, so the team must understand how to self-organize and self-manage.

The other answer choices are incorrect. Team-building events may be productive, but the project manager will be very busy and not consistently available during the first two weeks. Hosting several team-building events will be a drain on the project manager's bandwidth and may not be possible until after the project manager can focus on the team.

Providing project status updates is incorrect because the project manager will not be consistently available. The team will be working on the project in the project manager's absence, it is more likely that they will provide the manager with status updates.

Having one-on-one conversations may result in deeper relationships but would have to wait until the project manager can focus on the team.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

After success in a particulary challenging project phase, a project manager reassigned a high-performing team member to a more strategic task.

This is an example of what?

Recognition

Risk acceptance

Mentorship

Scope change

Answer explanation

Solution: A. Recognition

Recognition - singles out an individual by recognizing them as worthy of more of the work that satisfies them. In this case, the high-performing team member is recognized for their work and is reassigned to a more strategic task.

Risk Acceptance - There is no identified risk here hence the option is incorrect.

Mentorship- the guidance provided by a mentor, especially an experienced person in a company or educational institution hence not the correct answer.

Scope Change - a scope change comes into effect when there is a significant change that impacts project parameters to a defined, accepted work package or project, hence not the correct answer.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt


An organization is developing a new product. What should the project manager of this development do first to improve the success of the project?

Work with the project management office (PMO) to develop a detailed project schedule.

Work with the marketing team to conduct an impact analysis to identify the target market.

Work with the project sponsor to define the project vision and overall initiative.

Work with the stakeholders to identify the appropriate project team members.

Answer explanation

Solution: C. Work with the project sponsor to define the project vision and overall initiative

For project success, it is critical to initially define vision and mission of the overall initiative before even focusing on detailed planning. Impact Analysis, detailed project schedule and identification of project team members will follow once the project vision and overall initiative is defined

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A new graduate recently joined a mature agile R&D team. A mentor, assigned to work with the graduate, is overwhelmed by the extra workload. Team performance and motivation are dropping.

How can the project manager help with this situation?

Maintain a laissez-faire leadership style with the team, but use a transactional style to give firm guidance to the graduate.

Ask the mentor to use a collaborative servant leader approach to perform the usual duties along with the mentor role.

Cancel the mentor plan and focus on keeping the graduate motivated by learning through an intensive immersion.

Ask three more team members to share the mentor role in order to reduce the individual mentor workload by 75%.

Answer explanation

Solution: A. Maintain a laissez-faire leadership style with the team, but use a transactional style to give firm guidance to the graduate

The graduate is in need of authoritative and stable guidelines and positive feedback while the team must not lose their autonomy to maintain motivation.

Collaborative servant leadership approach is used for increasing team gel and motivation

Without mentor it is difficult to learn through an insensitive immersion

Asking three team members to share the mentor role is not an effective way

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?