PMI SH - Execute Project With the Urgency Required to Deliver Bu

PMI SH - Execute Project With the Urgency Required to Deliver Bu

1st - 3rd Grade

40 Qs

quiz-placeholder

Similar activities

recepcja + poprawa (wyposażenie)

recepcja + poprawa (wyposażenie)

3rd Grade

35 Qs

AKK

AKK

2nd - 3rd Grade

35 Qs

Certiprof ISO27001 Foundation - Exercise

Certiprof ISO27001 Foundation - Exercise

1st Grade

40 Qs

PRE-ASSESSEMENT PPL 1

PRE-ASSESSEMENT PPL 1

1st - 5th Grade

36 Qs

02. Role SCRUM

02. Role SCRUM

1st Grade - University

45 Qs

Project Management Quiz

Project Management Quiz

1st Grade

38 Qs

Are you ready for PMO-CP?

Are you ready for PMO-CP?

1st - 12th Grade

40 Qs

Quiz REV111 _12 November 2024_ 1B&1K

Quiz REV111 _12 November 2024_ 1B&1K

1st Grade - University

36 Qs

PMI SH - Execute Project With the Urgency Required to Deliver Bu

PMI SH - Execute Project With the Urgency Required to Deliver Bu

Assessment

Quiz

Professional Development

1st - 3rd Grade

Hard

Created by

sudiyuwono wowo

FREE Resource

40 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager is on a mega industrial project. The project team is distributed throughout six different countries and time zones.

During a review meeting, it was noticed that important baselined milestone dates were missed.

What is the most likely reason for the missed deadlines?

Lack of buy-in commitment

Poor team communication

Misunderstanding stakeholder expectations

Stakeholders' expectation is set too high

Answer explanation

Solution: B. Poor team communication

Missing milestone dates is not due to stakeholders, but is directly incumbent on the project team. That makes team communication the most likely culprit.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A key stakeholder requests a change that will solve a critical issue that might affect continuity of operations. However, the project is nearing completion and the change would increase the overall project cost and delay the completion date.

What should the project manager do?

Assign the decision regarding the critical nature of the change to a more knowledgeable stakeholder.

Submit a change request to the change control board (CCB).

Revise the work breakdown structure (WBS) and the project scope statement to include the change.

Communicate the impact on the budget and schedule to the project sponsor.

Answer explanation

Solution: B. Submit a change request to the change control board (CCB)

The Project Management Plan defines how to handle changes, including submitting them to a change control board (CCB). The Project Manager must follow the defined procedure.

Assigning the decision to a more knowledgeable stakeholder as this change raised by the key stakeholder needs to be managed correctly via the change request process.

The Project Manager can't revise the WBS before the change request is approved to proceed.

Communicating the impact on the budget and schedule will be discussed after the change request is submitted.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A business manager and product owner are requesting a more flexible way to incorporate changes into the product backlog. They want to reduce go-to-market time in order to react to a competitor's release strategy.

What should the project manager do?

Coach the product owner to prioritize product backlog items in accordance with business goals.

Review the assumption log and the project management plan to identify potential changes.

Establish a comprehensive change control process and select a change control board (CCB).

Authorize all key stakeholders to make modifications in order to deliver the product faster.

Answer explanation

Solution: A. Coach the product owner to prioritize product backlog items in accordance with business goals.

The prioritization of the backlog items is the responsibility of the product owner. In markets where competitors are releasing new products frequently, the features planned for a new release may be updated in response. A competitor's release strategy can trigger a change in direction that requires the product owner to reprioritize the product backlog.

The other options are incorrect.

Reviewing the assumption log and the project management plan does not directly address the request to reduce go-to-market time.

Establishing a comprehensive change control process may not be necessary depending on the opportunity for change and the designated development approach.

Authorizing stakeholders to make modifications can lead to uncontrolled changes that might not align with the project's objectives or the business goals. 

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A senior business stakeholder with many years of experience is pressuring an agile team to deliver most of the promised functionality to the customer 18 months in the future as opposed to multiple, incremental deliveries over the course of the 18 months. What should the project lead do next?

Work with the agile team to schedule the incremental deliveries to enable delivery of business value sooner to the customer.

Schedule meetings with the customer to determine their ability to support multiple incremental deliveries.

Provide details of the concern to the agile team and adjust their goals and release plans to conform to the stakeholder's request.

Work with the stakeholder to understand what the concerns are while, at the same time, conveying the benefits of incremental deliveries.

Answer explanation

Solution: D. Work with the stakeholder to understand what the concerns are while, at the same time, conveying the benefits of incremental deliveries.

The project lead will need to understand the reasons why one of the senior business stakeholder is pressuring for delivery 18 months in the future . At the same time, the Project lead will need to impress upon on the benefits of incremental delivery and also stress that incremental delivery is a fundamental aspect of agile delivery.. Hence this option is correct.

The project lead should not proceed with scheduling incremental deliveries especially when there is resistance from one of the senior stakeholder. Hence this option is incorrect.

Scheduling meetings with customer is also detrimental without having an internal consensus from all stakeholders on the delivery. Hence this option is also incorrect.

The project lead cannot adjust to goals and release plans without consensus from the entire team. Hence this option is incorrect.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A demanding project stakeholder insists that an additional feature be added to a project product without changing the scope, budget, or schedule. The project manager allows this feature to be included since it adds great value to the end product. However, the project manager discovers that adding this feature has lengthened the project schedule and increased project costs.
Which process should the project manager have followed before including the additional product feature?

Change control

Schedule planning

Procurement planning

Quality audit

Answer explanation

Solution: A. Change control

 Any change requests should be accompanied by an evaluation of any new risks that are introduced as well as changes in scope, budget, or schedule. All changes must be evaluated for the potential value they bring to the project and the potential resources, time, and budget needed to realize the potential value. The project manager should work with the change control board and the demanding stakeholder to guide change requests through the change control process. Approved changes are integrated into the applicable project planning documents, product backlog, project scope, etc. 

The other options are incorrect because they do not provide a comprehensive assessment of the full impact of the additional feature. The change control process would encompass all project aspects, allowing the project manager to identify areas that would be impacted. Had the project manager performed a holistic review of the potential impacts of adding the feature, they would have discovered that the scope and budget would be impacted. 

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A customer's requested design change is approved by the change control board (CCB). The project manager then discovers that the change will cause a three-month project delay.

What should the project manager have done to avoid this?

Increased the authorized budget, and requested additional resources

Redefined the project scope to include the new design

Fast tracked and crashed the schedule

Thoroughly assessed the request in accordance with the risk management plan

Answer explanation

Solution: D. Thoroughly assessed the request in accordance with the risk management plan

PMBoK Sixth Edition Chapter 4 and 11 state: "Risk management plan. Described in Section 11.1.3.1. The risk management plan provides information on risk-related roles and responsibilities, indicates how risk management activities are included in the budget and schedule, and describes categories of risk, which may be expressed as a risk breakdown structure,

4.6.2.5 MEETINGS

Change control meetings are held with a change control board (CCB) that is responsible for meeting and reviewing the change requests and approving, rejecting, or deferring change requests. Most changes will have some sort of impact on time, cost, resources, or risks. Assessing the impact of the changes is an essential part of the meeting. Alternatives to the requested changes may also be discussed and proposed. Finally, the decision is communicated to the request owner or group.

The CCB may also review configuration management activities. The roles and responsibilities of these boards are clearly defined and agreed upon by the appropriate stakeholders and are documented in the change management plan. CCB decisions are documented and communicated to the stakeholders for information and follow-up actions.

4.6.3 PERFORM INTEGRATED CHANGE CONTROL: OUTPUTS

4.6.3.1 APPROVED CHANGE REQUESTS

Change requests (described in Section 4.3.3.4) are processed according to the change management plan by the project manager, CCB, or an assigned team member. As a result, changes may be approved, deferred, or rejected. Approved change requests will be implemented through the Direct and Manage Project Work process. Deferred or rejected change requests are communicated to the person or group requesting the change.

The disposition of all change requests are recorded in the change log as a project document update"

The correct answer is: "Thoroughly assessed the request in accordance with the risk management plan"

The distractors are valid

7.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

A project manager is leading a large business transformation project that involves the entire organization. The project manager is working on the communications management plan.

Which two elements should the project manager consider while planning communications?

(Choose 2).

Key messages

Objectives and values

Collecting feedback

Multiple communication channels

Best communication channel

Answer explanation

Solution: A and D. Key messages and Multiple communication channels

The project manager should focus on key messages and the use of multiple communication channels while planning communications for the transformation.

The other answer choices are incorrect. The organization's objectives and values will not be included because they may change after the transformation of the entire organization. Collecting feedback is already a part of the project plan and has been well considered in advance. The project manager should aim to use all communication channels and should avoid narrowing usage down to a single "best" option.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?