1.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
Several components of an expensive manufacturing project have been returned by the customer. The customer is complaining that the quality of the components is poor and is concerned that, as a result, their products will be returned due to quality issues. The project manager is certain that quality has been maintained. How should the project manager communicate with the customer to help assure them that the project has produced quality products?
2.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
A company is working on a project to develop an integration of their existing systems. There are known issues in production. What should the project manager do?
3.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
A company changed the product owner on an existing project. The new product owner has less knowledge of the product than everybody else on the team. Due to the product owner's lack of knowledge, the team does not consider the opinions of the product owner seriously and mostly relies on the project manager's opinion. What should the project manager do?
4.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
A mid-size capital project has shared resources from the company's contract department. During the execution phase, the project team observed a delay in contracting. After communicating with the contract department, the project manager found the contract team is prioritizing other contracting jobs because they are not part of the project team. What should the project manager do first in this situation?
5.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
A team shared a complaint regarding the scrum master during the last sprint review. The team expressed that they were delayed because the scrum master did not remove impediments, such as scheduling some meetings with external teams and obtaining a room to work collaboratively, among other critical blockers. What should the project manager do?
6.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
A project manager is leading a global project with resources spread out in different locations. The stakeholders have different interpretations of the requirements. The project manager is concerned about scope creep. Which action should the project manager take to control the scope?
7.
MULTIPLE CHOICE QUESTION
3 mins • 1 pt
During a kick-off meeting, the project manager notices that one of the stakeholders responsible for providing key information to the team has a low level of participation. This stakeholder believes that there will be no benefit from implementing the project. The project manager realizes that this could be a high risk for the project. Which action should the project manager take?
Create a free account and access millions of resources
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
100 questions
Soal Pedagogik 1
Quiz
•
Professional Development
97 questions
Questionnaire MAF niveau 1
Quiz
•
Professional Development
96 questions
Code95 - chapter 3
Quiz
•
Professional Development
100 questions
PAKET 100 SOAL CPNS
Quiz
•
University - Professi...
100 questions
Coronal Polish 100 Questions
Quiz
•
Professional Development
100 questions
Day 1 - Pre Course Test
Quiz
•
Professional Development
100 questions
POPR písemný test
Quiz
•
Professional Development
100 questions
EIE | INTRODUCCIÓN A LA ECONOMÍA | A2 | OPOSICIONES
Quiz
•
Professional Development
Popular Resources on Wayground
5 questions
This is not a...winter edition (Drawing game)
Quiz
•
1st - 5th Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
10 questions
Identify Iconic Christmas Movie Scenes
Interactive video
•
6th - 10th Grade
20 questions
Christmas Trivia
Quiz
•
6th - 8th Grade
18 questions
Kids Christmas Trivia
Quiz
•
KG - 5th Grade
11 questions
How well do you know your Christmas Characters?
Lesson
•
3rd Grade
14 questions
Christmas Trivia
Quiz
•
5th Grade
20 questions
How the Grinch Stole Christmas
Quiz
•
5th Grade