A project manager begins to notice disengaged members arriving late, not delivering on time, not attending meetings, and producing low-quality deliveries.
What action should the project manager take?
PMI SH - Empower Team Members and Stakeholders
Quiz
•
Professional Development
•
1st - 3rd Grade
•
Hard
sudiyuwono wowo
FREE Resource
29 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager begins to notice disengaged members arriving late, not delivering on time, not attending meetings, and producing low-quality deliveries.
What action should the project manager take?
Investigate the reason for the team members' disengaged behavior and boost morale and participation.
Ask the team members to change the way they are working to match the newest work trends.
Encourage the team to double their efforts to pick up the slack from the disengaged team members.
Request that the team members abandon the process that is slowing their progress.
Answer explanation
Solution: A. Investigate the reason for the team members' disengaged behavior and boost morale and participation.
The project manager should investigate the reason for the team members' disengaged behavior and boost morale and participation. The project manager needs to understand why the team members are disengaged and then take steps to address it. This could involve providing more support, giving the team members more autonomy, or changing the way the project is structured. Boosting morale and participation will help to improve the team's performance. When team members feel engaged and motivated, they are more likely to be productive and deliver high-quality work.
The other answer choices are incorrect. Asking the team members to change the way they are working to match the newest work trends is not a good option because it does not address the root cause of the disengagement. Encouraging the team to double their efforts to pick up the slack from the disengaged team members is not a good option because it is unfair to the other team members. Requesting that the team members abandon the process that is slowing their progress is not a good option because it could lead to more problems down the road.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A delivery milestone for a project is fast approaching, but an item that is planned to be completed is at risk. A team member begins to act defensively and is blaming others for this issue.
How should the project manager have acted to avoid this?
Established ground rules for interaction that the whole team must follow.
Established and maintained meaningful relationships between team members.
Established formal patterns of authority, responsibility, and accountability.
Established clear delegation and accountability-sharing principles.
Answer explanation
Solution: A. Established ground rules for interaction that the whole team must follow.
By establishing clear ground rules, the project manager would be creating a positive and productive team environment, where everyone feels comfortable speaking up and contributing. This would help to prevent finger-pointing and blaming, as everyone would know how to interact with each other in a respectful and productive way.
The other answer choices are incorrect because they are important, but don't necessarily do much to prevent disrespectful behaviors.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project team in the middle of an incremental delivery project decided they need the help of a subject matter expert (SME) who is working in a different department. The project team asked the SME to join their team and assist in a specific task and they informed the project leader about this action.
What should the project manager do?
Check the project budget and assess the impact and feasibility of adding an additional resource
Talk with the project sponsor and get approval, explaining that this resource is important and crucial
Talk to the functional manager of this needed resource and check their availability and bandwidth
Facilitate the coordination of resources with the needed resources based on the teams working agreement
Answer explanation
Solution: D. Facilitate the coordination of resources with the needed resources based on the teams working agreement
Facilitating the coordination of resources with the needed resources based on the team's working agreement is correct as a team often needs to coordinate with other delivery teams across the organization, using effective coordination strategies, based on the working agreement.
The other options are incorrect.
Checking the project budget and assessing the impact and feasibility of adding additional resources is not the best choice, even if there is a budget available, as adding an SME in the middle of an incremental delivery process will impact team fabric and there will be a ramp curve for any new member being added. Similarly, seeking approval from the project sponsor, or talking to the functional manager of the resource, are incorrect because they do not address the full impact of the added resource.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The product owner decides to launch a product after a couple of releases, knowing that the minimum viable product (MVP) lacks some features. One of the key stakeholders, the marketing vice president, is not happy with the results and questioned the release decision.
What should the project manager do?
Coach the team on the decision-making process, assuming a risk-averse strategy towards product releasing.
Support the product owner's decision and seek better alignment with this stakeholder in order to avoid this type of issue in the future.
Assume the responsibility for product releases, making the final call on when something is ready for customer launch.
Escalate the issue to the sponsor, questioning the authority of the key stakeholder regarding the product launch decision.
Answer explanation
Solution: B. Support the product owner's decision and seek better alignment with this stakeholder in order to avoid this type of issue in the future
The agile team owns complete responsibility of the launch of the product and the Product owner being a part of the agile team, understands the product and the releases and is in a better position to decide when to launch the product . However, it also the duty of the Product Owner and the agile team to start involving all stakeholders early in the project, ensure inclusions in Priority decisions and solicit feedback during reviews that will eliminate stakeholder dissatisfaction. Hence this option is the correct answer.
Agile projects are less prone to risks as there are built in quality measures and their quick response to changes. Hence risk averse strategy may not be applicable. Hence this option is incorrect.
Project Manager in agile projects do not take responsibility for product releases nor can the project manager question the authority of the key stakeholders. Hence these options are incorrect.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project team is actively engaged in the preparation of the last delivery before the final product is live in production. What should the project manager do to make sure that the whole team is in full sync?
Ensure the team is attending the daily meetings and participating actively
Ensure that the needed information is available and accessible to each and every member
Ensure to visualize the work to be done on a white board visual and accessible to all
Ensure there is a room for the team to have regular conversation whenever needed
Answer explanation
Solution: A. Ensure the team is attending the daily meetings and participating actively
"Ensure the team is attending the daily meetings and participating actively" as daily meetings keep the team on track so that there are no surprises. and eliminate the waste of waiting dependencies of the work to be done between the team
Although rest of the options seems to be by providing the additional information, but the right choice is participation in daily meetings
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In the middle of a project incremental delivery, due to a change in the technology, a team member informed the project leader that due to a lack of knowledge in the technology the delivery will be delayed and suggests outsourcing services.
What should the project manager do?
Inform the end user of the delay of the specific delivery due to the new technology
Search for an outsourcing service with the experience needed
Inform the sponsor of the delay and ask for their support and approval
Discuss the impact of the new technology with the team and decide action jointly
Answer explanation
Solution: D. Discuss the impact of the new technology with the team and decide action jointly
The project manager is responsible of enabling his team to work as autonomously as possible
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Within the fourth iteration of product development, the project manager realizes that the software used for the project management plan is not permitting planned updates.
Which action should the project manager take?
Select a team resource who can update the project management plan template.
Based on business value for the upcoming iterations, choose a priority for the activities.
Resolve the issue independently so that team members do not become distracted.
Add the problem as a new project risk in the risk register and suggest corrective actions.
Answer explanation
Solution: C. Resolve the issue independently so that team members do not become distracted
A project manager's job is to remove impediments to team performance, therefore software deficiencies must be addressed at an administrative level and not at the team level.
The other answer choices are incorrect. They are not valid because administrative resources, rather than team resources, will be used to address the issue.
30 questions
Quiz 951
Quiz
•
1st Grade
25 questions
Agile PM#3 Quiz
Quiz
•
1st Grade
30 questions
Managment
Quiz
•
1st - 12th Grade
33 questions
Agile Training-Final Assessment
Quiz
•
1st Grade
27 questions
PMI SH - Support Team Performance by Providing Adequate Training
Quiz
•
1st - 3rd Grade
28 questions
PMI SH - Address and Remove Impediments, Obstacles, and Blockers
Quiz
•
1st - 3rd Grade
31 questions
PMI SH - Mentor and Collaborate With Stakeholders
Quiz
•
1st - 3rd Grade
25 questions
Refresher Service Excellence
Quiz
•
KG - Professional Dev...
15 questions
Character Analysis
Quiz
•
4th Grade
17 questions
Chapter 12 - Doing the Right Thing
Quiz
•
9th - 12th Grade
10 questions
American Flag
Quiz
•
1st - 2nd Grade
20 questions
Reading Comprehension
Quiz
•
5th Grade
30 questions
Linear Inequalities
Quiz
•
9th - 12th Grade
20 questions
Types of Credit
Quiz
•
9th - 12th Grade
18 questions
Full S.T.E.A.M. Ahead Summer Academy Pre-Test 24-25
Quiz
•
5th Grade
14 questions
Misplaced and Dangling Modifiers
Quiz
•
6th - 8th Grade