PMI SH - Support Organizational Change

Quiz
•
Professional Development
•
1st - 3rd Grade
•
Hard
sudiyuwono wowo
FREE Resource
15 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager participates in a focus group that implements project management changes across the organization. The goal is to improve project effectiveness and success.
Which process should the project manager suggest for lasting and successful change within projects?
Conduct individualized skills assessments and provide targeted training for each team member.
Monitor external regulations and adapt project management practices accordingly.
Faciliate open communication and build buy-in from all project stakeholders.
Implement a project management change management plan aligned with industry best practices.
Answer explanation
Solution: D. Implement a project management change management plan aligned with industry best practices.
By implementing a project management change management plan aligned with industry best practices, changes, timelines, and implementation processes can be better defined, communication strategies can be developed, and potential issues can be mitigated.
The other answer choices are incorrect. Individualized training is valuable, but training alone doesn't guarantee adoption without broader organizational shifts and support. Regulatory monitoring is important, but it is not the primary focus for internal project management improvement. Open communication is crucial, but it's most effective within a structured change management framework and defined plan.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A company is going through an organizational change. Most of the senior management has changed, including the project manager's direct supervisor. The supervisor has an aggressive working style, and has made critical comments to the project manager regarding the ongoing project, without really understanding the situation. The project manager feels uncomfortable working with the new supervisor.
What should the project manager do next?
Hold a project review meeting to explain the key points of the project to the new supervisor.
Apply the new supervisor's recommendations to the project.
Evaluate the impact of the organizational change to the project.
Communicate to the project team that they need to be ready to embrace change.
Answer explanation
Solution: C. Evaluate the impact of the organizational change to the project.
The project manager needs to deal with the change objectively, and first should understand the impact of organizations changes to the project. With that knowledge, the PM and team can engage the supervisor. The project manager should not blindly execute changes dictated by the supervisor. Changes will always affect the project, so simply communicating to the team that they should be ready for change does not accomplish much.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
An agile team is working on a new product development project. The product owner has requested a new change to accommodate recent technology requirements as a result of changes in the market environment.
Which of the following should the project manager do next?
Go ahead and implement the change immediately
Log a change request document and set up a change control board
Ensure the change request has been added to the product backlog
Reject the change as it may cost more money and delay the project
Answer explanation
Solution: C. Ensure the change request has been added to the product backlog
An agile project will required the product owner or project manager to add the new story or task (change request) to the product backlog so it can be prioritized and then sized without adding the item in to backlog and without prioritization, implementing / rejecting the change request is not possible
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project team member assigned to a new project will be required to report on all project tasks progress to the project manager while his current line manager will be responsible for his career growth and development.
Which of the following describes the project organization structure?
Matrix
Projectised
Functional
Cross-functional
Answer explanation
Solution: A. Matrix
The two bosses or more scenario is a characteristic of matrix organizational structures.
Projectized organization performs based on the assigned projects. one project manager reporting will be there
Functional organization performs based on the function wise.
5.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
A project manager is leading a remote home office implementation. The project manager is surprised with early signs of resistance from key stakeholders in the organization. The key stakeholders strongly disagree with the change and will require more persuasion than the project manager originally expected.
Which two tools and techniques should be used to identify the organizational and project influence of the stakeholders? (Choose two)
Stakeholder matrix
RACI chart
Stakeholder analysis
Stakeholder map
Engagement map
Answer explanation
Solution: A and D. Stakeholder matrix and Stakeholder map.
Stakeholders map involves different techniques to identify stakeholders by power and influence. The stakeholder matrix is one of the techniques that allows you to to identify such power relations in stakeholders.
The other answer choices are incorrect. They are used to create the stakeholder matrix and map, which are the best tools for determining organizational and project influence. The RACI chart includes all project roles, not just the key stakeholders.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
After several interviews with key stakeholders and checking the project charter, a project manager found that the current project organizational structure is no longer appropriate for the project's strategic goals. What should the project manager do next?
Assess the lessons learned documents and validate which organizational structure was used in the past for similar projects.
Ask the team to document the risk in the project risk register and develop a risk response plan accordingly.
Evaluate the gaps between the current organizational structure and the expected project benefits to determine required actions.
Ask the team to review the project charter and evaluate the project objectives for relevance.
Answer explanation
Solution: C. Evaluate the gaps between the current organizational structure and the expected project benefits to determine required actions.
Organizational structure should be flexible to accommodate the project goal, and may evolve in the project life cycle. If the current structure is not appropriate, the project manager should first evaluate the deficiencies against what the project needs to accomplish to determine a more fitting organizational structure. Assessing lessons learned from prior projects may give some direction, but gaps on the current project should be evaluated first. There is nothing in the question that suggests that project objectives are incorrect, so evaluating the objectives for relevance is not warranted.
This question and rationale were developed in reference to:
PMBOK Guide Sixth Edition (2018) PMI/PMI/9. Project Resource Management/ [Item Projects with high variability benefit from team structures that maximize focus and collaboration, such as self-organizing teams with generalizing specialists.Collaboration is intended to boost productivity and facilitate innovative problem solving. Collaborative teams may facilitate accelerated integration of distinct work activities, improve communication, increase knowledge sharing, and provide flexibility of work assignments in addition to other advantages.Although the benefits of collaboration also apply to other project environments, collaborative teams are often critical to the success of projects with a high degree of variability and rapid changes, because there is less time for centralized tasking and decision making.]
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A new customer relations database is being deployed. The schedule calls for migration from the previous system to occur over one weekend. However, some key stakeholders believe it may take more time for the migration.
What should the project manager do?
Assess the concerns and risks of not deploying within the scheduled time frame and react accordingly.
Change the deployment plan such that additional resources are available to perform the weekend deployment.
Review and revise as necessary the risk management plan.
Modify the schedule to increase the time frame of the deployment plan.
Answer explanation
Solution: A. Assess the concerns and risks of not deploying within the scheduled time frame and react accordingly.
The project manager should assess the risk in accordance with the risk management plan and react accordingly.
Changing the deployment plan by adding resources may not address the stakeholder requirements.
Revising the risk management plan will not address stakeholder concerns.
It may not be necessary or possible to modify the deployment plan.
Create a free account and access millions of resources
Similar Resources on Wayground
18 questions
PMI SH - Evaluate and Deliver Project Benefits and Value

Quiz
•
1st Grade
20 questions
Domain#1 Agile Mindset & Principles Mike Griffith

Quiz
•
1st Grade
10 questions
Agile Knowledge Quiz

Quiz
•
KG - 3rd Grade
11 questions
Prep-Cast CAPM Domain#3 : Agile Framework/Methodologies

Quiz
•
1st Grade
16 questions
CAPM Cost & Quality

Quiz
•
1st Grade
10 questions
Agile Roles

Quiz
•
2nd Grade
16 questions
PMI SH - Negotiate Project Agreements

Quiz
•
1st Grade
20 questions
ACP Prep-Cast Random #1

Quiz
•
2nd Grade
Popular Resources on Wayground
18 questions
Writing Launch Day 1

Lesson
•
3rd Grade
11 questions
Hallway & Bathroom Expectations

Quiz
•
6th - 8th Grade
11 questions
Standard Response Protocol

Quiz
•
6th - 8th Grade
40 questions
Algebra Review Topics

Quiz
•
9th - 12th Grade
4 questions
Exit Ticket 7/29

Quiz
•
8th Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
19 questions
Handbook Overview

Lesson
•
9th - 12th Grade
20 questions
Subject-Verb Agreement

Quiz
•
9th Grade
Discover more resources for Professional Development
18 questions
Writing Launch Day 1

Lesson
•
3rd Grade
9 questions
A Fine, Fine School Comprehension

Quiz
•
3rd Grade
12 questions
Passport Quiz 1

Quiz
•
1st - 5th Grade
10 questions
Place Value

Quiz
•
3rd Grade
8 questions
Writing Complete Sentences - Waiting for the Biblioburro

Lesson
•
3rd Grade
10 questions
Third Grade Angels Vocab Week 1

Quiz
•
3rd Grade
12 questions
New Teacher

Quiz
•
3rd Grade