35 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is a project described as in the context of project development?

A) A permanent and repetitive operation

B) A temporary and nonrepetitive operation

C) A long-term and repetitive operation

D) A temporary and repetitive operation

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Projects are often operated in what kind of management style?

A) Structured and formal

B) Ad-hoc and improvised

C) Rigid and controlled

D) Predictable and consistent

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following activities is associated with project development?

A) Mapping activities

B) Routine operations

C) Continuous improvement

D) Standardized procedures

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the definition of "Activity time"?

The time it takes a resource to complete an activity once it has started work on it.

The dependency of activities on each other.

A matrix in which each column represents an activity that provides information to another activity.

The time it takes to plan an activity before starting work on it.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does "Precedence relationship" refer to?

The time it takes a resource to complete an activity once it has started work on it.

The dependency of activities on each other.

A matrix in which each column represents an activity that provides information to another activity.

The order in which activities are planned.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is a "Dependency matrix"?

The time it takes a resource to complete an activity once it has started work on it.

The dependency of activities on each other.

A matrix in which each column represents an activity that provides information to another activity and in which each row indicates an activity that receives information.

A chart that shows the timeline of project activities.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is a predecessor activity?

An activity that starts after another activity.

An activity that is dependent on another activity.

An activity that needs to be completed before starting another activity.

An activity that is independent of other activities.

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?