CHAPTER 3: THE PROJECT MANAGEMENT PROCESS GROUP: A CASE STUDY
Authored by undefined undefined
Science
University
Used 58+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
63 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Choose the incorrect answer
Managing projects often requires making trade-offs among the project’s scope, time,
and cost.
Project managers and team should reexamine the business need for the project
during every phase of the project life cycle to determine if the project is worth
continuing
Project teams should never revise project plans during the project life cycle.
Process groups occur at varying levels of intensity throughout each phase of a
project
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Choose the correct answer
Project management process groups are isolated events
Planning processes are especially important for information technology projects
The executing process group should not overlap the other process groups.
The ideal outcome of the controlling process is to complete a project successfully by delivering the agreed-upon project scope within time, cost, and quality constraints.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Choose the incorrect answer
Key outcomes of the executing process group are formal acceptance of the work and creation of closing document, such as a final project report and lessons-learned report.
Some organizations develop their own internal information technology project
management methodologies.
An organization should put considerable thought into project selection to ensure that it
initiates the right kinds of projects for the right reasons.
JWD’s business case includes a discussion of potential risks.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Choose the incorrect answer
Critical assumptions and constraints are not included in JWD’s business case.
Unfortunately, JWD’s Project Charter did not include a space for comments from the stakeholders
Executing is often the most difficult and unappreciated process in project management.
All other answer
5.
FILL IN THE BLANK QUESTION
1 min • 1 pt
Is the following statement true or false? If false, replace the underlined part with the correct answer
"Planning is one of the five project management process groups."
(Answer: False-> Correct answer/True)
6.
FILL IN THE BLANK QUESTION
1 min • 1 pt
Is the following statement true or false? If false, replace the underlined part with the correct answer
"Project management is an integrative endeavor; decisions and actions taken in one
knowledge area at a certain time usually affect other knowledge areas."
(Answer: False-> Correct answer/True)
7.
FILL IN THE BLANK QUESTION
1 min • 1 pt
Is the following statement true or false? If false, replace the underlined part with the correct answer
"Closing processes take place during each phase of a project."
(Answer: False-> Correct answer/True)
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Popular Resources on Wayground
15 questions
Fractions on a Number Line
Quiz
•
3rd Grade
20 questions
Equivalent Fractions
Quiz
•
3rd Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
54 questions
Analyzing Line Graphs & Tables
Quiz
•
4th Grade
22 questions
fractions
Quiz
•
3rd Grade
20 questions
Main Idea and Details
Quiz
•
5th Grade
20 questions
Context Clues
Quiz
•
6th Grade
15 questions
Equivalent Fractions
Quiz
•
4th Grade