Search Header Logo

PMP Exam Prep 2024 - Practice Test 2 - Project Team (PDF Chapt3)

Authored by Patrick Pepin

Professional Development

Professional Development

Used 3+ times

PMP Exam Prep 2024 - Practice Test 2 - Project Team (PDF Chapt3)
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project experienced a significant team conflict during the final sprint. Nonetheless, the agile team succeeded in delivering a product that was accepted bythe customer.

What should the project manager do at the end of the sprint?

Conduct a retrospective meeting with the team to discuss what happened

Meet individually with the involved team members to express concernsregarding their behavior

Disregard the conflict since the project is coming to an end

Disregard the conflict since the team succeeded to achieve the project goals

Answer explanation

Even though the project is going to be closed soon, the project manager should hold a retrospective meeting to openly discuss what happened during the last sprint.

This allows the agile team to understand what went well and what actions to take in the future to improve work processes and collaboration.

Lessons learned is an important process not only for the ongoing project but also for the organization.

Thus, the project manager should openly discuss the conflict, rather than disregard it

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During a retrospective meeting, some agile team members stated that it sometimes gets confusing to check who is working on each work item and at what stage they are.

What can the project manager do to solve this problem?

Coach the team on how to be more attentive during the daily standup meeting

Guide the team on how to use the kanban board and update it regularly

Send a daily status report to all team members to remove the impediment

The project manager shouldn’t do anything since agile teams are self-organizing

Answer explanation

In the case of unclear work assignments or work progress, the project manager should help their team by using a Kanban board to display the flow of work (Agile Practice Guide, page 58). A kanban board could be already used, but team members might not be updating it properly; they’re not self-assigning tasks or they’re not moving work items to the right column.

The project manager should ensure that all team members know how to properly handle the kanban board.

Even though the problem raised by the team is considered an impediment, it’s not practical for the project manager to solve it by sending a daily status report to everyone.

It’s also not sufficient to coach the team to pay more attention during standups, as it’s difficult to keep in mind the status of all items

throughout the day, thus an up-to-date information radiator is needed.

Self-organizing teams work autonomously by assuming responsibility for achieving the

product increment.

However, they still need the project manager's help to adjust work processes and support them so that they can focus on achieving deliverables without interruptions or hindrance.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The project team is suffering from low morale since the departure of a key project stakeholder, who was a big support and motivation source for them.

What actions should the project manager take to boost morale?

Understand the team’s needs and what motivates them

Perform team building activities to strengthen team bonds

Try to prevent the departure of the key stakeholder

Set objectives and encourage the team to attain them

Answer explanation

The key to maintaining your team’s morale and motivation is the accurate identification of their incentives.

Knowing what each of your team members needs will help you provide them with the necessary conditions to reach their potential, create a productive work environment, and keep them encouraged in the long run.

In most cases, the project manager cannot prevent the departure of a stakeholder if they decide to. Instead, the project manager should set a long-term motivation policy to avoid having their team’s morale depend on the presence of certain members or factors.

Setting objectives or performing team-building activities won’t probably solve this team’s issue since they might be missing other motivational factors that the key stakeholder was providing, such as recognition for instance.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In order to ensure that their agile team is cross-functional, a project manager hires a new team member who is more inclined towards testing tasks. After a few days, the new member informs the project manager that they are unable to do their work properly because they don't have the necessary permission to access a portion of the code.

What should the project manager do next?

Ask the team member to raise the issue during the retrospective meeting

Tell the team member to adjust the acceptance criteria of their pending tasks and then inform the product owner

Explain to the team member that they cannot access the whole code due to security restrictions

Reach out to the appropriate stakeholder to either confirm or update the team member’s privilege

Answer explanation

Being a servant leader, the project manager should reach out to the appropriate stakeholder in order to verify why the new member doesn’t have access to that portion of code.

It could be for security reasons, or because the concerned stakeholder is unaware of the nature of the new member’s duties.

In an Agile work environment, a project manager should listen to the impediments faced

by their team members and act to solve them.

If the new member’s permission can’t be changed, the project manager should explain this to them and to the product owner in order to update the tasks’ acceptance criteria. Retrospective meetings are set up to improve processes rather than remove impediments.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Mid-sprint, an agile team encountered too many impediments to the point it became impossible to produce any working increments by the end of the sprint.

What should the project manager do next?

Cancel the sprint

Proceed with resource leveling or smoothing

Ask the development team to work on the less difficult work items first

Continue supporting the development team even though the sprint goal will not be achieved

Answer explanation

In agile, the project manager should be a servant leader.

Therefore, the right course of action in the described scenario is to support the development team by helping them remove existing and new impediments, regardless of being able to achieve the sprint goal or not.

However, the project manager should not dictate what the agile team should work on during the sprint.

The project manager cannot cancel the sprint either, since it’s up to the product owner to take such a decision.

Resource leveling or smoothing are two schedule compression techniques used in a predictive work environment

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

After introducing a new foreign developer to the team, the project manager noticed that a certain senior team member seems to be avoiding any interaction with them.

What should the project manager do about this issue?

Talk to the senior team member privately to try and find out the reason behind their behavior while making it clear that discrimination is neither tolerated nor accepted

Notify the functional manager of the senior team member’s behavior and ask them to take the appropriate disciplinary action

Look past the senior team member’s behavior since no conflict between the two has occurred and work seems to be going just fine

Address the issue in the next team meeting by scolding the senior team member and lecturing everyone about the importance of an inclusive work environment

Answer explanation

The project manager should talk to the senior project manager privately to get to know the reason behind their behavior.

Besides, the project manager should be clear about not tolerating any kind of discriminating behavior towards the new team member and the potential consequences and disciplinary procedures the senior team member will face in case their behavior persists.

The project manager should talk directly to the concerned party with no need for escalating the issue to the functional manager at this stage.

Such behavior should not be ignored, even when it seems to have no tangible impact on work progress.

On the other hand, it’s not appropriate nor professional to scold a team member in a meeting and in the presence of their colleagues, regardless of their behavior.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

An organization recently transitioned to the agile approach. However, project team members always wait for the project manager to assign them work.

How can the project manager help their team be self-organized?

Take a few weeks off to force the team to act on their own

Mentor the team on how to make their own decisions

Ensure that the team includes different functional expertise

Support the team by removing encountered impediments

Answer explanation

The project manager can help their team get self-organized by mentoring them on how to make their own decisions.

This will empower them to pick their own tasks without waiting for assignments or asking for permission or direction from the project manager every time.

Taking a vacation is a passive approach to dealing with the problem and it won’t solve it since the team will get back to relying on the project manager as soon as they come back.

Ensuring that the team includes different functional expertise will help the team be cross-

functional rather than self-organizing.

Supporting the team by removing encountered impediments is part of the agile project manager’s duties an.d won’t help make the team self-organizing

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?