PMP Exam Prep 2024 - Practice Test 5 - Project Work (PDF Ch.6)

PMP Exam Prep 2024 - Practice Test 5 - Project Work (PDF Ch.6)

Assessment

Quiz

Professional Development

Professional Development

Easy

Created by

Patrick Pepin

Used 3+ times

FREE Resource

Student preview

quiz-placeholder

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A few days after introducing a new release to the market, the Product Owner received a complaint from a user, claiming that the product has an annoying defect.

What should the Product Owner do next?

Create an item to fix the defect, add it to the product backlog, then prioritize it

Ask the development team to fix the defect immediately since the product is already released

Estimate the effort required to fix the defect, then decide what to do accordingly

Ask the development team to roll back the last release in order to work more on exploring undetected defects

Answer explanation

In Scrum, any change request, whether to implement a new requirement or fix a defect, should be inserted in the Product Backlog and then prioritized by the Product Owner.

If the defect is critical, the Product Owner can prioritize it to be tackled in the upcoming sprint.

The fact that the product is already on the market doesn't mean that discovered defects should be immediately fixed.

Additionally, going to an older version (i.e., rollback) is not a wise decision taking into consideration that only one defect was detected.

Finally, the product owner is not the one responsible for estimating efforts; it’s the responsibility of the development team

2.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

During the project execution phase, the Change Control Board (CCB) approved a change request that no one on the project team knew how to implement.

What should the project manager do to deal with this issue? (Select two)

Document the issue in the issue log

Hire a subject matter expert

Formally request the CCB to revoke their decision

Ask the team to do more research on how to implement the approved change request

Answer explanation

Hiring a subject matter expert and conducting more research will help your team implement the change request.

This is considered a problem-solving approach since it entails finding solutions to the encountered issues or challenges.

Uncertainty can be reduced by collecting more information through conducting research, engaging experts, or performing a market analysis (PMBOK 7th edition, page 229).

Neither documenting the issue in the issue log nor asking the CCB to revoke their decision could help resolve the issue.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Halfway through a sprint, the development team realized that they planned for more work than they could possibly complete.

What should the project manager advise the development team to do next?

Ask the product owner to remove some work items from the sprint backlog

Collaborate with the product owner to reprioritize the product backlog items

Continue work and put off discussing this issue to the sprint retrospective

Inform the product owner during the sprint review that some features could not be completed

Answer explanation

First, the development team should collaborate with the product owner in order to remove some work items from the sprint backlog.

The sprint backlog is a living artifact that should be updated whenever something new is learned or discovered.

Afterward, in the sprint retrospective, the team should discuss how they can improve their estimations.

The agile team should be proactive and should not wait for the sprint review in order to inform the product owner that they couldn’t complete the affected work.

Reprioritizing the product backlog items

won’t help solve this problem.

This activity is often undertaken during the refinement sessions with the purpose of making user stories ready for the next iterations.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager is leading a software project. The project team has finished all of the tasks in the iteration backlog early and decided to work on code clean-up for the rest of the iteration. In spite of their intention to decrease technical debt, which will save the customer maintenance fees in the future, neither the customer nor the project manager seems to be happy.

What could be the reason behind the customer’s dissatisfaction?

They wanted to avoid scope creep

They wanted to avoid gold plating

They wanted to prioritize the scope

They wanted to minimize costs by ending the iteration earlier

Answer explanation

The probable reason for customer dissatisfaction is there are more prioritized items in the product backlog that the team could have worked on instead of the code clean-up activity.

Stakeholders are the ones responsible for defining and prioritizing the scope and requirements for the project team (PMBOK 7th edition, page 14).

Since the customer didn’t ask for the code clean-up work, then it could not be considered as scope creep.

What the team did is “gold plating”, which implies doing additional activities that were neither agreed upon nor included in the iteration backlog, with the intention to please the customer.

By definition, gold plating entails providing extra value to the customer.

However, the customer can get more value by prioritizing the product backlog.

In such a scenario, the customer expects to get notified when the project team completes all of the iteration backlog items.

In an adaptive approach, the scope is variable while the project cost and schedule are fixed.

Consequently, the customer would not be interested in ending a pre-approved iteration earlier.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A newly assigned interim project manager got a call from one of the project vendors claiming that they had already completed 50% of the agreed-upon work and asked for payment.

What should the project manager refer to in order to check whether they need to pay the vendor or not and how much should they get paid?

Request for proposal

Contract

Response to bid

Procurement management plan

Answer explanation

The contract is the document the project manager should refer to in order to verify the payment procedure.

A contract is a mutually binding agreement that obligates the seller to provide the required services and the buyer to pay a predetermined amount on an agreed-upon date or schedule (PMBOK 7th edition, page 191).

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project has been hampered by many quality issues, putting the project at risk.

Which meeting should the project manager conduct with the team to figure out how to avoid or deal with such problems in the future?

Kick-off

Lessons learned

Risk review

Team building

Answer explanation

Lessons learned meetings are collaborative retrospective sessions for discussing, documenting, and soliciting feedback about the project's successes and missteps.

These meetings are a must for the project team to learn from previous mistakes and improve future processes and projects.

Lessons learned meetings should be held whenever needed, to review the way a project has been progressing, note important learnings, and set new ways for amelioration.

Team building activities aim to increase collaboration among team members.

Kick-off meetings are meant for communicating the objectives of the project and ensuring the stakeholders’ commitment to the project.

Risk review meetings are used to verify the status of existing risks and identify new ones (PMBOK 7th edition, page 180).

However, capturing lessons learned from current or closed risks commonly happens in the lessons learned meetings.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

At the end of a sprint retrospective, a team member stated that the meeting output is almost the same as the previous ones and suggested canceling it or at least reducing its frequency.

What should the Scrum Master do in this case?

Extend the sprint timebox in order to allow for more improvements to be discussed in the retrospective

Reduce the frequency of retrospectives to once every two sprints

Go with voting, and if all team members agree, then skip retrospectives

Keep the same frequency of retrospectives and reflect on how to make them more relevant and actionable

Answer explanation

The sprint retrospective is one of the main scrum events, which aims to help the team adjust and improve their work processes over time.

The scrum master’s role is to maintain scrum practices, therefore they should neither cancel the retrospective meeting nor reduce its frequency.

On the other hand, extending the sprint timebox denotes smoothing the problem rather than trying to solve it.

Instead, the scrum master should reflect on why the retrospective meeting is not driving the intended value to the team.

The scrum master may need to better facilitate the meeting, engage team members, solicit and collect more feedback, check various metrics, and use different investigation techniques such as the why-why method to help them take future actionable measures accordingly.

The scrum master can also use ESVP, for instance, which is a short activity for assessing

participants’ engagement.

This technique entails asking team members to describe anonymously their attitude toward the retrospective as being an Explorer, Shopper,

Vacationer, or Prisoner.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?