
PMP Exam Prep 2024 - Practice Test 6 - Scope & Meeting (PDF Ch7)
Authored by Patrick Pepin
Professional Development
Professional Development
Used 3+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
15 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A solar-powered car project is almost finished when the project manager receives an approved change request to replace a defective component of the car batteries.
What should the project manager do?
Record the problem in the issue log
Meet with the change control board to discuss the matter
Repair the defective component
Replace the defective component
Answer explanation
Since the project manager has received an approved change request, they should ensure its appropriate implementation.
Since the change request specifically entails the replacement of the defective component, the project manager shouldn’t repair it instead.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager is wrapping up a one-year project.
Which of the following activities should be prioritized?
Updating the change log
Releasing the project resources
Completing the knowledge transfer activities
Celebrating the project completion
Answer explanation
Because projects are temporary endeavors, most of the acquired knowledge is lost once the project is completed.
The project manager should be attentive to knowledge documentation and transfer to allow the organization to gain and retain the knowledge and experience obtained through running projects (PMBOK 7th edition, page 78).
Once this activity is completed, a celebration could take place and resources can be released.
On the other hand, the change log should be updated to monitor the change requests’ status.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager is leading a project using an adaptive approach. During the sprint review, the product owner asks for an acceptance document to sign off in order to demonstrate their approval of the deliverables.
What should the project manager do?
Create an acceptance document and share it with the product owner to sign off
Ask the product owner to create a task in the product backlog and prioritize it, so that the development team can create the acceptance document
Ask the product owner to create the acceptance document and sign it off
Inform the product owner that an acceptance document is unnecessary
Answer explanation
A sprint review is conducted to demonstrate the accomplished work, solicit feedback, and foster collaboration rather than seeking formal approval through an acceptance document sign-off (Essential Scrum by Rubin, Kenneth S, page 372).
Besides, formal approvals are more common in predictive environments.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager closed all contracts related to their construction project, except one that concerns setting up security cameras. The only thing left for this contract is to go through a quick inspection by an expert in order to check out wireless connection, night vision, cloud storage, etc.
Knowing that the security cameras are working fine and that the project needs to be closed as soon as possible, what should the project manager do?
Close the contract and the project with no inspection
Close the contract, but keep the project open
Close the project, but keep the contract open
Keep the contract and the project open
Answer explanation
The project manager should keep both the contract and the project open until the seller performs the inspection.
losing a project entails conducting several processes and steps including closing out all contracts.
Closing a contract in return requires verifying that the seller has delivered their work as predetermined in the contract.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager is leading a team that is not familiar with the adaptive approach. After several weeks, the project has reached a point where there is an accumulation of Work In Progress (WIP).
What should the project manager do to figure out whether the team is properly following procedures?
Perform a process evaluation
Review the notes of the previous retrospective meetings
Check the Kanban board
Check relevant Key Performance Indicators (KPIs)
Answer explanation
Process evaluation involves quality assurance activities and process audits to ensure procedures and processes are being followed and are generating the intended outcomes (PMBOK 7th edition, page 72).
Process evaluation can also include reviewing the notes of the previous retrospective meetings as they can reflect the type of issues that were encountered in the past and how they were handled.
Therefore, process evaluation involves more than just reviewing the previous retrospective meetings notes. KPIs and the Kanban board can only determine whether WIP is beyond the acceptable level, without identifying the causes.
Finally, process evaluation can take place during a retrospective meeting or a lessons learned session, and it can require further investigation that could go beyond those meetings
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
An organization asked the project manager to send a report on the cost of quality.
The report stated that the total cost was $30,000, detailed as follows (see image).
According to the above table, how much is the appraisal cost of the project?
$2,000
$3,000
$5,000
$10,000
Answer explanation
Appraisal costs, also known as inspection costs, are part of the Cost of Conformance as they represent the costs of identifying defective products before they are delivered to clients.
This comprises testing, inspecting, auditing, evaluating, and measuring the deliverables, product, or service the project is producing. Appraisal costs are set up to implement a series of activities to determine work results’ degree of conformance to quality requirements.
Meaning the project appraisal cost involves inspection costs which are $5,000.
Training falls under prevention activities.
Rework and scrap costs, on the other hand, are part of the Internal Failure Costs, whereas Warranty charges fall under External Failure Costs.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Mid project, a project manager is notified by the information security department that they just came to know about the design changes that were made lately.
They also expressed their concern about these changes’ compliance with the organization’s standards since they did not take part when these changes were made.
What should the project manager do to overcome this issue?
Undo all design changes since the information security department wasn’t involved in the process
Allow the information security department team to attend all of the following daily stand-ups to ensure all made changes comply with security
requirements
Ask the security department to raise the issue to the product owner
Conduct a meeting with the information security department to go over all design changes and ensure their compliance with the organization’s
standards
Answer explanation
The project manager should first try to resolve the issue through collaboration by conducting a meeting with the information security department to go over the design changes and implement the appropriate process to ensure their compliance with security requirements.
If certain design changes are found to be critical and unfixable, then those should be reverted.
The product owner could be involved in the problem resolution process, but transferring the issue to them wouldn’t work since compliance with the organization’s standards requires understanding security concerns and setting up the appropriate processes by the project manager and their team.
Standup meetings are used for daily work synching between team members, not for examining changes.
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?