Estimation Techniques

Estimation Techniques

4th Grade

8 Qs

quiz-placeholder

Similar activities

Bi Weekly DMAIC - DEFINE

Bi Weekly DMAIC - DEFINE

1st - 10th Grade

10 Qs

Cost Management Terminology

Cost Management Terminology

4th Grade

8 Qs

Understanding Scope Management

Understanding Scope Management

4th Grade

10 Qs

Schedule Compression & Optimization

Schedule Compression & Optimization

4th Grade

8 Qs

Team Development Stages

Team Development Stages

4th Grade

7 Qs

Maslow's Hierarchy

Maslow's Hierarchy

4th Grade

7 Qs

ASP-SM-Fmk

ASP-SM-Fmk

KG - University

7 Qs

PMP Quiz -01

PMP Quiz -01

1st - 5th Grade

10 Qs

Estimation Techniques

Estimation Techniques

Assessment

Quiz

Professional Development

4th Grade

Medium

Created by

Afghanistan Center

Used 11+ times

FREE Resource

8 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a humanitarian project aimed at constructing temporary shelters after a natural disaster, the project manager decides to estimate the duration for setting up each shelter based on the actual durations from similar past projects in different regions. However, the terrain and weather conditions in this region are significantly different. What estimating technique is being used, and what might be a potential risk?

Parametric Estimating; Overestimating the duration due to conservative figures

Three-Point Estimating; Underestimating due to optimism bias

Analogous Estimating; Inaccurate estimates due to differing conditions

Bottom-Up Estimating; Delays due to underestimation of smaller tasks

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During the planning phase of an IT infrastructure upgrade project, the project manager uses a formula that considers the number of servers, the average setup time per server, and the expected efficiency rate of the team based on historical data. What estimating technique is this, and what is a key advantage of using it?

Single-Point Estimating; Simplicity in estimation process

Parametric Estimating; Increased accuracy due to statistical relationships

Affinity Estimating; Quick categorization of tasks

Analogous Estimating; Leverages past project data directly

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In an agricultural project, the team uses historical data from previous planting seasons to estimate the effort required for various tasks like planting, irrigation, and harvesting. They compare new tasks to previously completed ones and group similar tasks together to provide a high-level estimate. What is this technique called, and what is a potential challenge?

Planning Poker Estimating; Ensuring team alignment on estimates

T-Shirt Sizing Estimating; Difficulty in maintaining consistency across categories

Affinity Estimating; Subjectivity in task categorization

Bottom-Up Estimating; Time-consuming due to detailed task breakdown

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

For a critical task in a healthcare project involving a nationwide vaccination rollout, the project manager asks team members to provide optimistic, pessimistic, and most likely duration estimates. The project manager then calculates a weighted average to estimate the task duration. Which technique is being used, and why might this approach be beneficial?

Parametric Estimating; It provides precise estimates based on statistical data

Single-Point Estimating; Simplifies the estimation process

Three-Point Estimating; Accounts for uncertainty and variability

Planning Poker Estimating; Encourages team consensus

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a banking project to implement a new financial system, the project manager breaks down each deliverable into smaller components such as software modules and interface designs. Estimates are made for each component and then aggregated to develop the overall project estimate. What is this technique known as, and what is a potential drawback?

Analogous Estimating; Might overlook unique aspects of the current project

Bottom-Up Estimating; Can be time-consuming and resource-intensive

Three-Point Estimating; Requires extensive data for accurate results

T-Shirt Sizing Estimating; May lead to oversimplification of tasks

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a construction project, the project manager decides to use a straightforward technique where a single estimate is given for the time required to complete the foundation work without considering variability or uncertainty. Which estimating technique is this, and what is a significant risk associated with it?

Three-Point Estimating; Overly complex for simple tasks

Single-Point Estimating; Increased risk of inaccuracy due to lack of contingency

Parametric Estimating; May require more data than available

Affinity Estimating; Might not be detailed enough for critical tasks

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During a sprint planning meeting in a software development project, team members use a consensus-based technique where they estimate the effort required for user stories by discussing and selecting from predefined values on cards. What is this technique called, and what is its main advantage?

Planning Poker Estimating; Encourages team collaboration and consensus

Affinity Estimating; Quickly categorizes tasks into groups

T-Shirt Sizing Estimating; Provides a simple and fast estimation

Three-Point Estimating; Accounts for uncertainty and variability

8.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a project to develop an educational curriculum, the project team uses a technique where they categorize tasks such as lesson planning and content creation into different sizes (e.g., small, medium, large) based on their relative complexity and effort required. What is this estimating technique known as, and what is a potential limitation?

Planning Poker Estimating; Requires significant team consensus

Affinity Estimating; May introduce bias in task grouping

T-Shirt Sizing Estimating; Can be subjective and inconsistent

Bottom-Up Estimating; Time-consuming for detailed breakdown