Estimation Techniques

Quiz
•
Professional Development
•
4th Grade
•
Medium
Afghanistan Center
Used 11+ times
FREE Resource
8 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In a humanitarian project aimed at constructing temporary shelters after a natural disaster, the project manager decides to estimate the duration for setting up each shelter based on the actual durations from similar past projects in different regions. However, the terrain and weather conditions in this region are significantly different. What estimating technique is being used, and what might be a potential risk?
Parametric Estimating; Overestimating the duration due to conservative figures
Three-Point Estimating; Underestimating due to optimism bias
Analogous Estimating; Inaccurate estimates due to differing conditions
Bottom-Up Estimating; Delays due to underestimation of smaller tasks
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During the planning phase of an IT infrastructure upgrade project, the project manager uses a formula that considers the number of servers, the average setup time per server, and the expected efficiency rate of the team based on historical data. What estimating technique is this, and what is a key advantage of using it?
Single-Point Estimating; Simplicity in estimation process
Parametric Estimating; Increased accuracy due to statistical relationships
Affinity Estimating; Quick categorization of tasks
Analogous Estimating; Leverages past project data directly
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In an agricultural project, the team uses historical data from previous planting seasons to estimate the effort required for various tasks like planting, irrigation, and harvesting. They compare new tasks to previously completed ones and group similar tasks together to provide a high-level estimate. What is this technique called, and what is a potential challenge?
Planning Poker Estimating; Ensuring team alignment on estimates
T-Shirt Sizing Estimating; Difficulty in maintaining consistency across categories
Affinity Estimating; Subjectivity in task categorization
Bottom-Up Estimating; Time-consuming due to detailed task breakdown
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
For a critical task in a healthcare project involving a nationwide vaccination rollout, the project manager asks team members to provide optimistic, pessimistic, and most likely duration estimates. The project manager then calculates a weighted average to estimate the task duration. Which technique is being used, and why might this approach be beneficial?
Parametric Estimating; It provides precise estimates based on statistical data
Single-Point Estimating; Simplifies the estimation process
Three-Point Estimating; Accounts for uncertainty and variability
Planning Poker Estimating; Encourages team consensus
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In a banking project to implement a new financial system, the project manager breaks down each deliverable into smaller components such as software modules and interface designs. Estimates are made for each component and then aggregated to develop the overall project estimate. What is this technique known as, and what is a potential drawback?
Analogous Estimating; Might overlook unique aspects of the current project
Bottom-Up Estimating; Can be time-consuming and resource-intensive
Three-Point Estimating; Requires extensive data for accurate results
T-Shirt Sizing Estimating; May lead to oversimplification of tasks
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In a construction project, the project manager decides to use a straightforward technique where a single estimate is given for the time required to complete the foundation work without considering variability or uncertainty. Which estimating technique is this, and what is a significant risk associated with it?
Three-Point Estimating; Overly complex for simple tasks
Single-Point Estimating; Increased risk of inaccuracy due to lack of contingency
Parametric Estimating; May require more data than available
Affinity Estimating; Might not be detailed enough for critical tasks
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During a sprint planning meeting in a software development project, team members use a consensus-based technique where they estimate the effort required for user stories by discussing and selecting from predefined values on cards. What is this technique called, and what is its main advantage?
Planning Poker Estimating; Encourages team collaboration and consensus
Affinity Estimating; Quickly categorizes tasks into groups
T-Shirt Sizing Estimating; Provides a simple and fast estimation
Three-Point Estimating; Accounts for uncertainty and variability
8.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In a project to develop an educational curriculum, the project team uses a technique where they categorize tasks such as lesson planning and content creation into different sizes (e.g., small, medium, large) based on their relative complexity and effort required. What is this estimating technique known as, and what is a potential limitation?
Planning Poker Estimating; Requires significant team consensus
Affinity Estimating; May introduce bias in task grouping
T-Shirt Sizing Estimating; Can be subjective and inconsistent
Bottom-Up Estimating; Time-consuming for detailed breakdown
Similar Resources on Wayground
10 questions
Agile Mindset - 1-6

Quiz
•
4th Grade
10 questions
Blank Quiz 48

Quiz
•
4th Grade
7 questions
Schedule Management Processes

Quiz
•
4th Grade
11 questions
Schedule Management Terms

Quiz
•
4th Grade
7 questions
Team Development Stages

Quiz
•
4th Grade
7 questions
Responsabilidades de un gerente de proyectos en Scrum

Quiz
•
1st - 12th Grade
7 questions
Leadership and Time Management

Quiz
•
1st - 10th Grade
10 questions
Blank Quiz 52

Quiz
•
4th Grade
Popular Resources on Wayground
18 questions
Writing Launch Day 1

Lesson
•
3rd Grade
11 questions
Hallway & Bathroom Expectations

Quiz
•
6th - 8th Grade
11 questions
Standard Response Protocol

Quiz
•
6th - 8th Grade
40 questions
Algebra Review Topics

Quiz
•
9th - 12th Grade
4 questions
Exit Ticket 7/29

Quiz
•
8th Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
19 questions
Handbook Overview

Lesson
•
9th - 12th Grade
20 questions
Subject-Verb Agreement

Quiz
•
9th Grade
Discover more resources for Professional Development
12 questions
Passport Quiz 1

Quiz
•
1st - 5th Grade
10 questions
Making Predictions

Quiz
•
4th - 5th Grade
6 questions
Spiral Review 8/5

Quiz
•
4th Grade
18 questions
Rotation/Revolution Quiz

Quiz
•
4th Grade
22 questions
Geography Knowledge

Quiz
•
4th Grade
10 questions
Capitalization

Quiz
•
4th Grade
15 questions
Multiplication Facts

Quiz
•
4th Grade
20 questions
Basic multiplication facts

Quiz
•
4th Grade