EVM Basic Terminology

Quiz
•
Professional Development
•
4th Grade
•
Hard
Afghanistan Center
Used 4+ times
FREE Resource
6 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In an IT project to develop a new customer relationship management (CRM) system, the project manager calculates the total budget allocated for the entire project from start to finish, including all planned work and expenses. What is this total budget called?
Planned Value (PV)
Budget at Completion (BAC)
Earned Value (EV)
Actual Cost (AC)
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During a humanitarian project to provide clean water access in a rural area, the project manager tracks the value of work planned to be completed by a specific date according to the project schedule. What metric is the project manager tracking?
Budget at Completion (BAC)
Earned Value (EV)
Planned Value (PV)
Actual Cost (AC)
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In a healthcare project to build a new clinic, the project manager needs to determine the value of the work actually performed by a certain point in the project. This value helps measure project performance and progress. What is this value known as?
Budget at Completion (BAC)
Planned Value (PV)
Earned Value (EV)
Actual Cost (AC)
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During the execution phase of an agricultural project to develop a new irrigation system, the project manager wants to assess the total cost incurred for the work performed up to a specific date. This cost includes all expenses, such as labor, materials, and overheads. What is this cost referred to as?
Budget at Completion (BAC)
Planned Value (PV)
Earned Value (EV)
Actual Cost (AC)
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In a humanitarian project focused on building temporary shelters after a natural disaster, the project manager calculates the total approved budget for completing the project. This budget includes all planned costs and resources. What is this total budget called?
Budget at Completion (BAC)
Earned Value (EV)
Planned Value (PV)
Actual Cost (AC)
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During an agricultural project aimed at developing sustainable farming practices, the project manager needs to determine the monetary value of the work that should have been completed by a certain date according to the project schedule. What metric is the project manager calculating?
Earned Value (EV)
Planned Value (PV)
Actual Cost (AC)
Budget at Completion (BAC)
Similar Resources on Wayground
10 questions
AAC NISSAN BRAND TRAINING MANINDER

Quiz
•
1st - 10th Grade
7 questions
Schedule Management Processes

Quiz
•
4th Grade
6 questions
Risk Response Strategies-Negative Risks

Quiz
•
4th Grade
8 questions
Project Management Challenges & Project Constraints Quiz

Quiz
•
4th Grade
10 questions
IOS - Perfomance - Optimization

Quiz
•
1st - 12th Grade
10 questions
Blank Quiz 51

Quiz
•
4th Grade
7 questions
Types of Contract

Quiz
•
4th Grade
7 questions
Quality Vs. Grade

Quiz
•
4th Grade
Popular Resources on Wayground
18 questions
Writing Launch Day 1

Lesson
•
3rd Grade
11 questions
Hallway & Bathroom Expectations

Quiz
•
6th - 8th Grade
11 questions
Standard Response Protocol

Quiz
•
6th - 8th Grade
40 questions
Algebra Review Topics

Quiz
•
9th - 12th Grade
4 questions
Exit Ticket 7/29

Quiz
•
8th Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
19 questions
Handbook Overview

Lesson
•
9th - 12th Grade
20 questions
Subject-Verb Agreement

Quiz
•
9th Grade
Discover more resources for Professional Development
12 questions
Passport Quiz 1

Quiz
•
1st - 5th Grade
10 questions
Making Predictions

Quiz
•
4th - 5th Grade
6 questions
Spiral Review 8/5

Quiz
•
4th Grade
18 questions
Rotation/Revolution Quiz

Quiz
•
4th Grade
22 questions
Geography Knowledge

Quiz
•
4th Grade
10 questions
Capitalization

Quiz
•
4th Grade
15 questions
Multiplication Facts

Quiz
•
4th Grade
20 questions
Basic multiplication facts

Quiz
•
4th Grade