EVM Basic Terminology

Quiz
•
Professional Development
•
4th Grade
•
Hard
Afghanistan Center
Used 4+ times
FREE Resource
6 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In an IT project to develop a new customer relationship management (CRM) system, the project manager calculates the total budget allocated for the entire project from start to finish, including all planned work and expenses. What is this total budget called?
Planned Value (PV)
Budget at Completion (BAC)
Earned Value (EV)
Actual Cost (AC)
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During a humanitarian project to provide clean water access in a rural area, the project manager tracks the value of work planned to be completed by a specific date according to the project schedule. What metric is the project manager tracking?
Budget at Completion (BAC)
Earned Value (EV)
Planned Value (PV)
Actual Cost (AC)
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In a healthcare project to build a new clinic, the project manager needs to determine the value of the work actually performed by a certain point in the project. This value helps measure project performance and progress. What is this value known as?
Budget at Completion (BAC)
Planned Value (PV)
Earned Value (EV)
Actual Cost (AC)
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During the execution phase of an agricultural project to develop a new irrigation system, the project manager wants to assess the total cost incurred for the work performed up to a specific date. This cost includes all expenses, such as labor, materials, and overheads. What is this cost referred to as?
Budget at Completion (BAC)
Planned Value (PV)
Earned Value (EV)
Actual Cost (AC)
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In a humanitarian project focused on building temporary shelters after a natural disaster, the project manager calculates the total approved budget for completing the project. This budget includes all planned costs and resources. What is this total budget called?
Budget at Completion (BAC)
Earned Value (EV)
Planned Value (PV)
Actual Cost (AC)
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During an agricultural project aimed at developing sustainable farming practices, the project manager needs to determine the monetary value of the work that should have been completed by a certain date according to the project schedule. What metric is the project manager calculating?
Earned Value (EV)
Planned Value (PV)
Actual Cost (AC)
Budget at Completion (BAC)
Similar Resources on Wayground
6 questions
Quiz Manejo de Proyectos

Quiz
•
1st Grade - University
9 questions
The Meaning of Prostration

Quiz
•
1st - 5th Grade
5 questions
EAC, ETC, and VAC

Quiz
•
4th Grade
7 questions
1. PMP Sample Questions

Quiz
•
4th Grade
10 questions
TPM (Total Productive Maintenance)

Quiz
•
1st - 10th Grade
8 questions
Estimation Techniques

Quiz
•
4th Grade
5 questions
Expected Monetary Value (Correct it)

Quiz
•
4th Grade
10 questions
EL Education Overview

Quiz
•
KG - 5th Grade
Popular Resources on Wayground
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
10 questions
Nouns, nouns, nouns

Quiz
•
3rd Grade
10 questions
9/11 Experience and Reflections

Interactive video
•
10th - 12th Grade
25 questions
Multiplication Facts

Quiz
•
5th Grade
11 questions
All about me

Quiz
•
Professional Development
22 questions
Adding Integers

Quiz
•
6th Grade
15 questions
Subtracting Integers

Quiz
•
7th Grade
9 questions
Tips & Tricks

Lesson
•
6th - 8th Grade
Discover more resources for Professional Development
20 questions
Place Value

Quiz
•
4th Grade
18 questions
Subject and Predicate Practice

Quiz
•
4th Grade
5 questions
Remembering 9/11 Patriot Day

Lesson
•
3rd - 5th Grade
20 questions
Run-On Sentences and Sentence Fragments

Quiz
•
3rd - 6th Grade
20 questions
4 Types of Sentences

Quiz
•
3rd - 5th Grade
20 questions
place value

Quiz
•
4th Grade
20 questions
Place Value and Rounding

Quiz
•
4th Grade
15 questions
Place Value

Quiz
•
4th Grade