PMI SP Schedule Planning and Development

Quiz
•
Professional Development
•
Professional Development
•
Medium
PMI Trainer
Used 7+ times
FREE Resource
13 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Which of the following is NOT a key component of project scheduling?
WBS (Work Breakdown Structure)
Risk register
Gantt chart
Network diagram
Dependencies and logic
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
What is the critical path in project scheduling?
The longest path in the project network diagram with shortest time to complete the project
The path with the highest resource utilization and all complex activities
The path with the most dependencies
The path that requires the most complex activities to complete the project
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
What is the purpose of a schedule model in the schedule approach?
To establish the project timeline and milestones with a methodology choosen
To identify and analyze project risks
To define the project's work breakdown structure (WBS)
To allocate resources to project activities
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Which scheduling technique is commonly used to allocate resources to project activities?
Critical Path Method (CPM)
Precedence Diagramming Method (PDM)
Resource levelling
Monte Carlo simulation
All of the above
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
What is the significance of identifying near-critical paths in project scheduling?
Near-critical paths have the highest resource utilisation
Near-critical paths have the least number of dependencies
Near-critical paths have the potential to become critical paths
Near-critical paths are not important for project scheduling
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
What is the role of resource calendars in defining the resource-constrained schedule?
To allocate resources to project activities
To track changes and variances in resource utilization
To establish a reference point for project control
To define resource availability and working hours
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
What does the Performance Measurement Baseline (PMB) typically include?
Project scope statement and objectives
Project resource allocation plan
Approved project schedule, SOW, WBS and milestones
Risk register and mitigation strategies
All of these
Create a free account and access millions of resources
Similar Resources on Wayground
14 questions
Agile Fundamentals Q2

Quiz
•
Professional Development
10 questions
SESSION 5

Quiz
•
Professional Development
12 questions
Project management principles

Quiz
•
Professional Development
10 questions
New Methods and Resources to Enhance Project Management

Quiz
•
Professional Development
10 questions
Project Management Master Class 3

Quiz
•
Professional Development
15 questions
IT Modernisation Quizz 3

Quiz
•
Professional Development
10 questions
Quiz Lesson 3 - Topic C (Schedule)

Quiz
•
Professional Development
10 questions
CGEIT Domain 2 MCQ (Additional)

Quiz
•
Professional Development
Popular Resources on Wayground
10 questions
Video Games

Quiz
•
6th - 12th Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
25 questions
Multiplication Facts

Quiz
•
5th Grade
10 questions
UPDATED FOREST Kindness 9-22

Lesson
•
9th - 12th Grade
22 questions
Adding Integers

Quiz
•
6th Grade
15 questions
Subtracting Integers

Quiz
•
7th Grade
20 questions
US Constitution Quiz

Quiz
•
11th Grade
10 questions
Exploring Digital Citizenship Essentials

Interactive video
•
6th - 10th Grade