Over the past six months, the development cost per story has risen by more than 250% due to a faulty platform which is NO longer supported. The product vision highlights unique features of the platform as a pre-requisite for the product. What should the project manager do to determine next steps?

Đề 4

Quiz
•
English
•
1st - 5th Grade
•
Hard
Thắng Nguyễn
FREE Resource
12 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Cancel the project due to exceeding the budget constraint
Ask the product owner to select an alternative platform
Cancel the project as the product vision CANNOT be fulfilled
Run what-if cost impact scenarios with the product owner
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Senior management asked you to consider the types of organizational structure and working
styles that might be followed at your development company that builds homes for low-income
families, and the possible impact on the projects you will be managing. Your organization has
departments for donations, construction, marketing, volunteers, and finance. But before you
start working on it, you need to verify your knowledge on the organizational structures and
functions.
Choose the organizational structure where the authority of the project manager is the
highest
Functional
Projectized
Matrix
Composite
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Senior management asked you to consider the types of organizational structure and working
styles that might be followed at your development company that builds homes for low-income
families, and the possible impact on the projects you will be managing. Your organization has
departments for donations, construction, marketing, volunteers, and finance. But before you
start working on it, you need to verify your knowledge on the organizational structures and
functions.
In addition to the departments listed in the scenario, your company also has a manager
of project management to oversee all of the ongoing projects. As one of the project
managers, you report directly to the project management department but share staff
with other departments. What type of organizational structure does this describe?
Functional
Projectized
Matrix
Composite
4.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
The company you work for builds and operates large shopping centers throughout the United
States, and its culture is committed to continuous improvement. You are about to embark on
managing your first shopping center project, and your sponsor is testing your knowledge about
continuous process improvements.
Which of the following are key attributes of continuous improvement? (Choose three.)
Better design of products to improve service
Exceeding customer expectations
Striving to always lower costs
Higher level of uniform product quality
Increasing sales through global markets
5.
MULTIPLE SELECT QUESTION
45 sec • 1 pt
As part of an organizational change program, an experienced project manager with agile experience and certification is hired by a company with a strong predictive culture. Which two actions can the project manager take to start helping the company adopt agile methodologies? (Choose TWO.)
Ensure that the MoSCoW method is used to write all project requirements.
Analyze all planned projects to pick the appropriate agile model.
Show stakeholders how agile can increase quality and decrease risk.
Train project teams to be more self-reliant and cross-functional.
Identify opportunities for incremental business value delivery.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
An agile team needs to decide who should represent them in the Scrum of Scrums. Which option should be used to select the best-suited team member?
Scrum
DevOps
extreme Programming
CI/CD
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A Canadian start-up company announces to the press its imminent launch in the European Union (EU) and Latin America. Soon afterward, the compliance team recommends delaying the launch by six (6) months to avoid substantial penalties related to a new set of EU regulations.
Which approach could the project manager take to advance the launch project while preparing the compliance measures?
Run a SWOT analysis to weigh priorities between compliance and consumer needs, and resume project if the result favors consumers
Estimate impact of penalties on the project, increase the contingency reserve accordingly and resume project as planned.
Re-plan the predictive project as a Large-Scale Scrum life cycle, and use story points to estimate approval milestones.
Split out work affected by the regulations into a agile track, and re-plan unaffected work in the predictive schedule.
Create a free account and access millions of resources
Similar Resources on Quizizz
16 questions
Sequence Process

Quiz
•
4th Grade
16 questions
Sequence of Order

Quiz
•
4th Grade
16 questions
Chronological Order Worksheets

Quiz
•
4th Grade
10 questions
Workshop Expert's Secrets

Quiz
•
1st Grade
10 questions
English Project Work

Quiz
•
1st - 5th Grade
17 questions
Text Structure Practice

Quiz
•
4th - 8th Grade
15 questions
Tracking Monsters Vocabulary

Quiz
•
5th Grade - University
16 questions
Put the Story in Sequence Order

Quiz
•
4th Grade
Popular Resources on Quizizz
15 questions
Multiplication Facts

Quiz
•
4th Grade
25 questions
SS Combined Advisory Quiz

Quiz
•
6th - 8th Grade
40 questions
Week 4 Student In Class Practice Set

Quiz
•
9th - 12th Grade
40 questions
SOL: ILE DNA Tech, Gen, Evol 2025

Quiz
•
9th - 12th Grade
20 questions
NC Universities (R2H)

Quiz
•
9th - 12th Grade
15 questions
June Review Quiz

Quiz
•
Professional Development
20 questions
Congruent and Similar Triangles

Quiz
•
8th Grade
25 questions
Triangle Inequalities

Quiz
•
10th - 12th Grade