PMP_Exc_14

PMP_Exc_14

3rd Grade

105 Qs

quiz-placeholder

Similar activities

skład chemiczny organizmów

skład chemiczny organizmów

1st - 6th Grade

105 Qs

OLIMPIADE IPA SD

OLIMPIADE IPA SD

1st - 5th Grade

110 Qs

Final 2016

Final 2016

KG - University

100 Qs

Implantació de jardins i zones verdes

Implantació de jardins i zones verdes

1st - 12th Grade

100 Qs

Parásitos nematodos

Parásitos nematodos

KG - 5th Grade

109 Qs

STAAR Review

STAAR Review

KG - University

108 Qs

100 point. Revision Quiz

100 point. Revision Quiz

3rd - 5th Grade

100 Qs

201-300

201-300

1st - 5th Grade

100 Qs

PMP_Exc_14

PMP_Exc_14

Assessment

Quiz

Biology

3rd Grade

Hard

Created by

Quyen Nguyen

FREE Resource

105 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Two start-up companies have merged, and now more than 100 developers on eight agile teams are working on a common portfolio. Which agile practice or method can best ensure release coordination between the teams?
Scrum of Scrums
Mobbing
Scrumban
Feature-Driven Development

Answer explanation

Your answer is incorrect. FDD provides the most complete set of methods specifically for the needs of large software development projects. The correct answer is: Feature-Driven Development

2.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

Six months into a strategic agile project, company executives are closely monitoring its progress. The COO expresses frustration that the last weekly burn-down charts show the projected completion date significantly moving back and forward several times. How can the project manager forecast the completion date with more accuracy and certainty?
Ensure upcoming backlog items are elaborated in more detail with the team.
Educate the executive committee on the flexible nature of agile planning.
Plan for variable-size iterations according to story complexity and load.
Reduce frequency of the progress reports sent to senior stakeholders.

Answer explanation

Your answer is correct. Erratic progress curve variations are typical of inconsistent or uninformed story point estimates. Backlog refinement can ensure that overly complex stories are broken down and that past progress informs new story estimates. The correct answer is: Ensure upcoming backlog items are elaborated in more detail with the team.

3.

MULTIPLE SELECT QUESTION

2 mins • 1 pt

An ongoing agile project is measured as follows: According to the table, which two of the following are the project's metrics? (Choose TWO).
SPI = 0.98
CPI = 1.05
CPI = 1.30
SPI = 1.01
CPI = 0.95

Answer explanation

Your answer is correct. SPI is calculated as stories completed/stories planned (78/77 = 1.01) and CPI as planned value /completed value (3090K/2950K = 1.05). The correct answers are: CPI = 1.05, SPI = 1.01

4.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

A project team has been efficiently delivering results. The product upgrade they are working on must be released in three months or else a competitor’s new product will make theirs obsolete. Citing this reason, the product owner makes a sudden request for a feature revision. However, no one on the project team is capable of doing the work. The project sponsor is willing to extend the budget but CANNOT extend the schedule. What should the project manager do?
Meet the new demand by adding new resources with the required skills.
Recommend suspending the project until a firm decision can be made.
Discuss options with the project sponsor and choose the best one.
Challenge the request and initiate customer research to determine whether the new feature is desirable.

Answer explanation

Your answer is correct. In situations with time constraints, the most efficient option is expanding the team to include skilled resources. Training is also an option if resources have the capability to learn within the timeframe. The project sponsor has already made their request, so it is up to the project manager to realize it. Agile projects are designed to function in highly complex and unpredictable environments, so suspending or cancelling the project hardly ever is an option. The correct answer is: Meet the new demand by adding new resources with the required skills.

5.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

A start-up has grown quickly, and there are now four (4) agile teams working on interrelated products. All teams have begun to experience impediments and gaps related to work in other teams. How should the project manager address this problem?
Eliminate dependencies between teams.
Favor collaboration tools over meetings.
Implement a Scrum of Scrums layer.
Merge into two large teams to reduce issues.

Answer explanation

Your answer is incorrect. Scrum of Scrums is the most effective way to coordinate work between teams working on interrelated products. The correct answer is: Implement a Scrum of Scrums layer.

6.

MULTIPLE CHOICE QUESTION

2 mins • 1 pt

The IT integration team has a major setback in a hybrid project. Testing has confirmed that the hardware does NOT support the target operating system. The agile team's software releases must now run on a later operating system version. What should the project manager do next?
Meet with the scrum master to determine if the product vision is still valid.
Meet with the product owner and team to update the product backlog during the sprint.
Work with the agile team to run root cause analysis on why the problem did not surface earlier.
Inform the team at the daily meeting and update the Definition of Done and Definition of Ready.

Answer explanation

Your answer is incorrect. "Changes of frame assumptions during execution requires impact analysis as quickly as possible. Product owner input is required for major scope changes (including rework) which would be reflected as updates to the product backlog. Reviewing the product vision would give you insight to use cases rather than specific OS versions. Root cause analysis is already performed by the IT team—the agile team must work with the new requirement—and changing the Definition of Done and Definition of Ready would NOT address the impact analysis on work already done." The correct answer is: Meet with the product owner and team to update the product backlog during the sprint.

7.

MULTIPLE SELECT QUESTION

2 mins • 1 pt

A hybrid virtual reality project is running an agile software track and a predictive electronics track. Halfway into the project, delays are accumulating due to misaligned deliverable releases between the two tracks. Which two elements should the project manager combine to produce a common network diagram? (Choose TWO).
Definition of Ready with dependency milestones
Epic breakdown with work breakdown structure
Product backlog with critical path task sequence
Definition of Done with exit criteria
Definition of Ready with work breakdown structure

Answer explanation

Your answer is correct. Misalignment is caused by missing dependencies between the tracks. The purpose of the network diagram is to sequence activities based on dependency. The Scrum equivalent of a task start dependency is the Definition of Ready, and the equivalent of the task exit criteria are the Definition of Done. The correct answers are: Definition of Ready with dependency milestones, Definition of Done with exit criteria

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?