1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
____ refer(s) to all the work involved in creating the products of the project and the processes used to create them.
Deliverables
Milestones
Scope
Product development
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which tool or technique for collecting requirements is often the most expensive and time consuming?
Interviews
Focus groups
Surveys
Observation
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A is a deliverable-oriented grouping of the work involved in a project that defines its total scope.
scope statement
WBS
WBS dictionary
work package
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What approach to developing a WBS involves writing down or drawing ideas in a nonlinear format?
Top-down
Bottom-up
Analogy
Mind mapping
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Assume that you have a project with major categories called planning, analysis, design, and testing. What level of the WBS would these items fall under?
0
1
2
3
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is not a best practice that can help in avoiding scope problems on IT projects?
Keep the scope realistic.
Use off-the-shelf hardware and software whenever possible.
Follow good project management processes.
Don’t involve too many users in scope management.
7.
MULTIPLE SELECT QUESTION
30 sec • 1 pt
What constitutes requirements for agile projects?
The Scrum
The backlog
The sprints
The requirements list
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?