CAPM Cost & Quality

CAPM Cost & Quality

1st Grade

15 Qs

quiz-placeholder

Similar activities

rodzaje opraw

rodzaje opraw

1st Grade

18 Qs

SAK_ Kuis 1 : Pendahuluan dan Pemutakhiran

SAK_ Kuis 1 : Pendahuluan dan Pemutakhiran

1st Grade

11 Qs

Ranking 1 Cofee Morning Informa Malang

Ranking 1 Cofee Morning Informa Malang

KG - 3rd Grade

20 Qs

Piłka Nożna

Piłka Nożna

1st Grade - Professional Development

17 Qs

Microsoft Excel

Microsoft Excel

KG - Professional Development

20 Qs

17 Days of SDGs Quiz - Day 10 (English)

17 Days of SDGs Quiz - Day 10 (English)

KG - Professional Development

15 Qs

Praca

Praca

1st - 6th Grade

20 Qs

Modulo 1

Modulo 1

1st Grade

20 Qs

CAPM Cost & Quality

CAPM Cost & Quality

Assessment

Passage

Professional Development

1st Grade

Practice Problem

Hard

Created by

sudiyuwono wowo

Used 3+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The plan for the first iteration was to complete 80 story points. However, the team was only able to complete 60. Each story point earns $1,000 for the project. The actual cost of the iteration was $70,000. As the iteration retrospective approaches, the scrum master requests that the team prepares all the data required to calculate the various earned value metrics.

At the retrospective, the team determines that the project is..............budget.

on

under

over

can not be determined

Answer explanation

To answer whether the project is on, under, or over budget, the CPI should be calculated and its value interpreted. Based on the information provided in the scenario, the CPI/ =

$60,000 / $70,000 = 0.857, which is less than 1.0, meaning that the project is over budget, making this choice the best answer to the question asked.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

You are managing a project to relocate a historic building to a new property that is a safe distance from the rising river basin. You have just finished developing your cost estimate, and are preparing the supporting documentation to accompany it.

What should be included in this documentation?

Cost register

Cost forecast

Range of possible estimates

Cost baseline

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In preparation for an upcoming project status meeting, you have determined the value of the work completed thus far is $100,000 with a budget at completion (BAC) of $1,000,000. At this point in the project, you have spent 12% of the project budget. The value of work planned to be completed at this point is $115,000.

What will you report at the project status meeting?

The project is performing well in terms of cost but not in terms of schedule

The project is not performing well both in terms of cost and schedule

The project is currently behind schedule

The project is currently over budget

Answer explanation

To determine the status of the project, the schedule variance and cost variance (or, alternatively, the cost performance index (CPI) and schedule performance index (SPI)) must be calculated.

The earned value (EV), which is the actual work completed in the scenario described, is stated as $100,000. The planned value (PV), which is the value of work planned to be completed at this point in the scenario, is stated as $115,000. The actual cost (AC), which is the portion of the project budget you have spent so far in the scenario described, is 12% of the budget of $1,000,000 which is $120,000. The calculations of the cost variance (CV) and the schedule variance (SV) are shown below:

CV = EV - AC = $100,000 - $120,000 = -$20,000

SV = EV - PV = $100,000 - $115,000 = -$15,000

Both the schedule variance and the cost variance are negative at this point in the project. Therefore, at the project status meeting, you should report that the project is not performing well both in terms of cost and schedule.

Alternatively, you can calculate the CPI and the SPI:

CP| = EV / AC = $100,000 / $120,000 = 0.83

SPI = EV / PV = $100,000 / $115,000 = 0.87

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager has recently been given a promotion and became the sponsor of a new initiative within her company. Given her past success in managing similar projects, the organization's project steering committee asks her to submit a high-level project estimate that will be reviewed next week to decide on whether or not to initiate the project.

What is the best course of action for the new sponsor?

Get a professional estimate from external subject matter experts

Use her own expert judgment and some historical information

Use the WBS to create an accurate bottom-up estimate

Work with the project team to create the requested estimate

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

You are managing a project to develop a new instrument. During planning, the number of design reviews was reduced. This reduction in design reviews allowed a lower project budget and a shorter timeline. The instrument has been transitioned to operations, and unfortunately, the support costs are significantly higher than expected as several field modifications on the instrument are being performed.

What could you have done differently to help avoid this situation?

Nothing. Limiting the number of design reviews will always increase the product's operating costs.

Consider the impact of fewer project design reviews before deciding to reduce them

Planned a better transition to operations

Nothing, you are only responsible for the outcome of your project.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During a sprint review, the product owner acknowledges that the deliverable meets the technical requirements and acceptance criteria but is not ready for customer use because not all required approvals have been obtained. The product owner asks why this critical step was missed.

What was the most likely reason for this issue?

A definition of done (DoD) was not established or was established but not used.

The acceptance criteria were not defined during requirements gathering.

The deliverable was not verified as part of the Control Quality process.

The team used eXtreme Programming (XP) instead of Scrum methods.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager is about to start the process of identifying quality requirements and standards for an infrastructure project. The project manager examines the project charter to gain a high-level understanding of project objectives and reviews relevant information from the available components of the project management plan.

What else should the project manager do to gather inputs to the process?

Review the requirements documentation to gain an understanding of the project and product quality requirements

Conduct a brainstorming session with the project team and subject matter experts to develop the quality management plan

Perform a cost-benefit analysis to determine if the planned quality activities are cost-effective

Update the lessons learned register with information on challenges encountered in the quality planning process

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

By signing up, you agree to our Terms of Service & Privacy Policy

Already have an account?