CAPM Cost & Quality

Passage
•
Professional Development
•
1st Grade
•
Hard
sudiyuwono wowo
Used 3+ times
FREE Resource
15 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The plan for the first iteration was to complete 80 story points. However, the team was only able to complete 60. Each story point earns $1,000 for the project. The actual cost of the iteration was $70,000. As the iteration retrospective approaches, the scrum master requests that the team prepares all the data required to calculate the various earned value metrics.
At the retrospective, the team determines that the project is..............budget.
on
under
over
can not be determined
Answer explanation
To answer whether the project is on, under, or over budget, the CPI should be calculated and its value interpreted. Based on the information provided in the scenario, the CPI/ =
$60,000 / $70,000 = 0.857, which is less than 1.0, meaning that the project is over budget, making this choice the best answer to the question asked.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
You are managing a project to relocate a historic building to a new property that is a safe distance from the rising river basin. You have just finished developing your cost estimate, and are preparing the supporting documentation to accompany it.
What should be included in this documentation?
Cost register
Cost forecast
Range of possible estimates
Cost baseline
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In preparation for an upcoming project status meeting, you have determined the value of the work completed thus far is $100,000 with a budget at completion (BAC) of $1,000,000. At this point in the project, you have spent 12% of the project budget. The value of work planned to be completed at this point is $115,000.
What will you report at the project status meeting?
The project is performing well in terms of cost but not in terms of schedule
The project is not performing well both in terms of cost and schedule
The project is currently behind schedule
The project is currently over budget
Answer explanation
To determine the status of the project, the schedule variance and cost variance (or, alternatively, the cost performance index (CPI) and schedule performance index (SPI)) must be calculated.
The earned value (EV), which is the actual work completed in the scenario described, is stated as $100,000. The planned value (PV), which is the value of work planned to be completed at this point in the scenario, is stated as $115,000. The actual cost (AC), which is the portion of the project budget you have spent so far in the scenario described, is 12% of the budget of $1,000,000 which is $120,000. The calculations of the cost variance (CV) and the schedule variance (SV) are shown below:
CV = EV - AC = $100,000 - $120,000 = -$20,000
SV = EV - PV = $100,000 - $115,000 = -$15,000
Both the schedule variance and the cost variance are negative at this point in the project. Therefore, at the project status meeting, you should report that the project is not performing well both in terms of cost and schedule.
Alternatively, you can calculate the CPI and the SPI:
CP| = EV / AC = $100,000 / $120,000 = 0.83
SPI = EV / PV = $100,000 / $115,000 = 0.87
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager has recently been given a promotion and became the sponsor of a new initiative within her company. Given her past success in managing similar projects, the organization's project steering committee asks her to submit a high-level project estimate that will be reviewed next week to decide on whether or not to initiate the project.
What is the best course of action for the new sponsor?
Get a professional estimate from external subject matter experts
Use her own expert judgment and some historical information
Use the WBS to create an accurate bottom-up estimate
Work with the project team to create the requested estimate
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
You are managing a project to develop a new instrument. During planning, the number of design reviews was reduced. This reduction in design reviews allowed a lower project budget and a shorter timeline. The instrument has been transitioned to operations, and unfortunately, the support costs are significantly higher than expected as several field modifications on the instrument are being performed.
What could you have done differently to help avoid this situation?
Nothing. Limiting the number of design reviews will always increase the product's operating costs.
Consider the impact of fewer project design reviews before deciding to reduce them
Planned a better transition to operations
Nothing, you are only responsible for the outcome of your project.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During a sprint review, the product owner acknowledges that the deliverable meets the technical requirements and acceptance criteria but is not ready for customer use because not all required approvals have been obtained. The product owner asks why this critical step was missed.
What was the most likely reason for this issue?
A definition of done (DoD) was not established or was established but not used.
The acceptance criteria were not defined during requirements gathering.
The deliverable was not verified as part of the Control Quality process.
The team used eXtreme Programming (XP) instead of Scrum methods.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager is about to start the process of identifying quality requirements and standards for an infrastructure project. The project manager examines the project charter to gain a high-level understanding of project objectives and reviews relevant information from the available components of the project management plan.
What else should the project manager do to gather inputs to the process?
Review the requirements documentation to gain an understanding of the project and product quality requirements
Conduct a brainstorming session with the project team and subject matter experts to develop the quality management plan
Perform a cost-benefit analysis to determine if the planned quality activities are cost-effective
Update the lessons learned register with information on challenges encountered in the quality planning process
Create a free account and access millions of resources
Similar Resources on Wayground
20 questions
ACP dari Bit.ly

Quiz
•
1st Grade
18 questions
PMI SH - Plan and Manage Procurement

Quiz
•
1st Grade
18 questions
PMI SH - Integrate Project Planning Activities

Quiz
•
1st Grade
20 questions
Agile PM#1 Quiz

Quiz
•
1st Grade - University
12 questions
PMI SH Manage Project Issues

Quiz
•
1st Grade
21 questions
PMI SH - Determine Appropriate Project Methodology/methods and P

Quiz
•
1st - 3rd Grade
12 questions
001. Pre & Post Test PMP Des 2024

Quiz
•
1st Grade
15 questions
PMI SH - Support Organizational Change

Quiz
•
1st - 3rd Grade
Popular Resources on Wayground
18 questions
Writing Launch Day 1

Lesson
•
3rd Grade
11 questions
Hallway & Bathroom Expectations

Quiz
•
6th - 8th Grade
11 questions
Standard Response Protocol

Quiz
•
6th - 8th Grade
40 questions
Algebra Review Topics

Quiz
•
9th - 12th Grade
4 questions
Exit Ticket 7/29

Quiz
•
8th Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
19 questions
Handbook Overview

Lesson
•
9th - 12th Grade
20 questions
Subject-Verb Agreement

Quiz
•
9th Grade