CAPM Cost & Quality
Passage
•
Professional Development
•
1st Grade
•
Practice Problem
•
Hard
sudiyuwono wowo
Used 3+ times
FREE Resource
Enhance your content in a minute
15 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The plan for the first iteration was to complete 80 story points. However, the team was only able to complete 60. Each story point earns $1,000 for the project. The actual cost of the iteration was $70,000. As the iteration retrospective approaches, the scrum master requests that the team prepares all the data required to calculate the various earned value metrics.
At the retrospective, the team determines that the project is..............budget.
on
under
over
can not be determined
Answer explanation
To answer whether the project is on, under, or over budget, the CPI should be calculated and its value interpreted. Based on the information provided in the scenario, the CPI/ =
$60,000 / $70,000 = 0.857, which is less than 1.0, meaning that the project is over budget, making this choice the best answer to the question asked.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
You are managing a project to relocate a historic building to a new property that is a safe distance from the rising river basin. You have just finished developing your cost estimate, and are preparing the supporting documentation to accompany it.
What should be included in this documentation?
Cost register
Cost forecast
Range of possible estimates
Cost baseline
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In preparation for an upcoming project status meeting, you have determined the value of the work completed thus far is $100,000 with a budget at completion (BAC) of $1,000,000. At this point in the project, you have spent 12% of the project budget. The value of work planned to be completed at this point is $115,000.
What will you report at the project status meeting?
The project is performing well in terms of cost but not in terms of schedule
The project is not performing well both in terms of cost and schedule
The project is currently behind schedule
The project is currently over budget
Answer explanation
To determine the status of the project, the schedule variance and cost variance (or, alternatively, the cost performance index (CPI) and schedule performance index (SPI)) must be calculated.
The earned value (EV), which is the actual work completed in the scenario described, is stated as $100,000. The planned value (PV), which is the value of work planned to be completed at this point in the scenario, is stated as $115,000. The actual cost (AC), which is the portion of the project budget you have spent so far in the scenario described, is 12% of the budget of $1,000,000 which is $120,000. The calculations of the cost variance (CV) and the schedule variance (SV) are shown below:
CV = EV - AC = $100,000 - $120,000 = -$20,000
SV = EV - PV = $100,000 - $115,000 = -$15,000
Both the schedule variance and the cost variance are negative at this point in the project. Therefore, at the project status meeting, you should report that the project is not performing well both in terms of cost and schedule.
Alternatively, you can calculate the CPI and the SPI:
CP| = EV / AC = $100,000 / $120,000 = 0.83
SPI = EV / PV = $100,000 / $115,000 = 0.87
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager has recently been given a promotion and became the sponsor of a new initiative within her company. Given her past success in managing similar projects, the organization's project steering committee asks her to submit a high-level project estimate that will be reviewed next week to decide on whether or not to initiate the project.
What is the best course of action for the new sponsor?
Get a professional estimate from external subject matter experts
Use her own expert judgment and some historical information
Use the WBS to create an accurate bottom-up estimate
Work with the project team to create the requested estimate
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
You are managing a project to develop a new instrument. During planning, the number of design reviews was reduced. This reduction in design reviews allowed a lower project budget and a shorter timeline. The instrument has been transitioned to operations, and unfortunately, the support costs are significantly higher than expected as several field modifications on the instrument are being performed.
What could you have done differently to help avoid this situation?
Nothing. Limiting the number of design reviews will always increase the product's operating costs.
Consider the impact of fewer project design reviews before deciding to reduce them
Planned a better transition to operations
Nothing, you are only responsible for the outcome of your project.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During a sprint review, the product owner acknowledges that the deliverable meets the technical requirements and acceptance criteria but is not ready for customer use because not all required approvals have been obtained. The product owner asks why this critical step was missed.
What was the most likely reason for this issue?
A definition of done (DoD) was not established or was established but not used.
The acceptance criteria were not defined during requirements gathering.
The deliverable was not verified as part of the Control Quality process.
The team used eXtreme Programming (XP) instead of Scrum methods.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager is about to start the process of identifying quality requirements and standards for an infrastructure project. The project manager examines the project charter to gain a high-level understanding of project objectives and reviews relevant information from the available components of the project management plan.
What else should the project manager do to gather inputs to the process?
Review the requirements documentation to gain an understanding of the project and product quality requirements
Conduct a brainstorming session with the project team and subject matter experts to develop the quality management plan
Perform a cost-benefit analysis to determine if the planned quality activities are cost-effective
Update the lessons learned register with information on challenges encountered in the quality planning process
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
17 questions
Computing part 1 U 6-10
Quiz
•
1st Grade
11 questions
Environmental Hygiene
Quiz
•
1st - 3rd Grade
12 questions
Icebreaker Activity
Quiz
•
1st Grade - Professio...
16 questions
L2 Above Ground Drainage Systems Pt1
Quiz
•
1st - 3rd Grade
15 questions
Classroom Expectations
Quiz
•
1st Grade
15 questions
BHP
Quiz
•
1st - 12th Grade
20 questions
QUIZ 4 : TOPIC 8 [PROCESS COSTING]
Quiz
•
1st Grade - University
20 questions
How much idea I have?
Quiz
•
1st Grade - Professio...
Popular Resources on Wayground
5 questions
This is not a...winter edition (Drawing game)
Quiz
•
1st - 5th Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
10 questions
Identify Iconic Christmas Movie Scenes
Interactive video
•
6th - 10th Grade
20 questions
Christmas Trivia
Quiz
•
6th - 8th Grade
18 questions
Kids Christmas Trivia
Quiz
•
KG - 5th Grade
11 questions
How well do you know your Christmas Characters?
Lesson
•
3rd Grade
14 questions
Christmas Trivia
Quiz
•
5th Grade
20 questions
How the Grinch Stole Christmas
Quiz
•
5th Grade
Discover more resources for Professional Development
5 questions
This is not a...winter edition (Drawing game)
Quiz
•
1st - 5th Grade
18 questions
Kids Christmas Trivia
Quiz
•
KG - 5th Grade
10 questions
Christmas/Winter
Quiz
•
KG - 2nd Grade
20 questions
Christmas Movies
Quiz
•
1st - 12th Grade
20 questions
How the Grinch Stole Christmas
Quiz
•
1st - 3rd Grade
10 questions
Christmas Characters
Quiz
•
KG - 3rd Grade
10 questions
Exploring Christmas Math Word Problems
Interactive video
•
1st - 5th Grade
16 questions
Christmas 1st grade
Quiz
•
1st Grade
