10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 6 pts
What are the three roles in Scrum?
Project Manager, Business Analyst, Developer
Product Manager, QA Tester, Developer
Scrum Master, Product Owner, Developer, and Tester
None
Answer explanation
Scrum Master, Product Owner, and Developers
2.
MULTIPLE CHOICE QUESTION
30 sec • 6 pts
Which of the following is NOT an official Scrum event?
Daily Scrum
Sprint Review
Retrospective
Sprint Refinement
3.
MULTIPLE CHOICE QUESTION
30 sec • 6 pts
What is the purpose of the Sprint Retrospective?
To review the product backlog
To inspect how the last sprint went with regards to people, relationships, processes, and tools
To present the completed work to stakeholders
All of them
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Why is having a Definition of Done (DoD) important for a Scrum Team?
It ensures the team knows when to stop working on a task
It defines the criteria for what constitutes complete work and aligns the team on quality standards.
It helps the Product Owner prioritize the Product Backlog.
t sets the scope for the next sprint's work.
Answer explanation
DoD creates clarity around when work is truly "done" and ensure that everyone on the team adheres to the same quality standards
5.
MULTIPLE CHOICE QUESTION
30 sec • 6 pts
Which of the following is a responsibility of the Development Team?
Deciding how much work to commit to during the sprint
Managing the product backlog
Reviewing the product with stakeholders
6.
MULTIPLE CHOICE QUESTION
30 sec • 6 pts
Which artifact in Scrum represents work to be done in the sprint?
Product Backlog
Sprint Backlog
Definition of Done
7.
MULTIPLE CHOICE QUESTION
30 sec • 6 pts
What does the Definition of Done (DoD) ensure?
That the product is ready to be released
That a Product Backlog item is complete according to agreed-upon criteria
That the sprint has been successfully completed
That the Development Team is ready to start the next sprint
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
10 questions
Train Lighting Systems Quiz
Quiz
•
University
10 questions
Mastering Java Arithmetic Operators
Quiz
•
10th Grade - University
10 questions
DERN1322 - Ergonomics
Quiz
•
University
11 questions
SOS#13 - DAY 3 pop quiz
Quiz
•
University
13 questions
CE423: CE LAW QUIZ No. 1
Quiz
•
University
15 questions
TOPIC 1-Materials and Prestressing Applications
Quiz
•
University
12 questions
Methods of Estimating Quiz
Quiz
•
University
10 questions
CNN Layer
Quiz
•
University
Popular Resources on Wayground
15 questions
Fractions on a Number Line
Quiz
•
3rd Grade
20 questions
Equivalent Fractions
Quiz
•
3rd Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
22 questions
fractions
Quiz
•
3rd Grade
20 questions
Main Idea and Details
Quiz
•
5th Grade
20 questions
Context Clues
Quiz
•
6th Grade
15 questions
Equivalent Fractions
Quiz
•
4th Grade
20 questions
Figurative Language Review
Quiz
•
6th Grade
Discover more resources for Engineering
12 questions
IREAD Week 4 - Review
Quiz
•
3rd Grade - University
23 questions
Subject Verb Agreement
Quiz
•
9th Grade - University
7 questions
Force and Motion
Interactive video
•
4th Grade - University
7 questions
Renewable and Nonrenewable Resources
Interactive video
•
4th Grade - University
5 questions
Poetry Interpretation
Interactive video
•
4th Grade - University
19 questions
Black History Month Trivia
Quiz
•
6th Grade - Professio...
15 questions
Review1
Quiz
•
University
15 questions
Pre1
Quiz
•
University