1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What are the leadership style that can be practised in managing an engineering team? 

 

  1. I. Bureaucratic 

  1. II. Systematic 

  1. III. Laissez-Faire 

I and II

II and III

I and III

I, II and III

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Refer to the statement below. 

 

A bar graph that ranks data classification in descending order from left to right, which categorised the vital few and useful many data. 

 

Determine the type of quality control tool referred to in this statement. 

Bar chart

Histogram

Pareto Diagram

Check Sheet

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

Figure shows a shape symbol that is frequently used in a typical flowchart. Determine the conventional meaning of this symbol. 

Starting or ending point of a flowchart. 

Printout, such as document or report. 

Decision or branching point. 

Information entering or leaving the system. 

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Just in Time (JIT) is a Total Quality Management (TQM) method to reduce waste and improve workflow. Determine the advantages of JIT in improving the work process. 

 

  1. I. Reduce required storage space. 

  1. II. Less likelihood of stock perishing. 

  1. III. More working capital. 

I and II

II and III

I and III

I, II and III

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The functions of project planning in any engineering project include 

 

  1. I. Ensure all tasks are carefully considered and anticipated. 

  1. II. Provide a basis for monitoring performance of the project. 

  1. III. Encourage better communication with stakeholders. 

I and II

II and III

I and III

I, II and III

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

Figure above shows a method for planning a project. Determine the name of this method. 

  1. Critical Path Method 

PERT

Gantt Chart

5W + 1H

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Safety and health are very important in any engineering project. Identify the responsible organization for the administration and enforcement of legislation related to occupational safety and health in Malaysia. 

National Institute of Occupational Safety and Health.

Department of Occupational Safety and Health

Ministry of Health. 

Fire and Rescue Department Malaysia. 

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?