Pre-Test - Fast track

Pre-Test - Fast track

Professional Development

14 Qs

quiz-placeholder

Similar activities

Microsoft 365

Microsoft 365

Professional Development

11 Qs

SLS PS 2.0 Types of Learning Experiences (LE)

SLS PS 2.0 Types of Learning Experiences (LE)

Professional Development

10 Qs

Experiencia del cliente ágil

Experiencia del cliente ágil

Professional Development

10 Qs

Pre Test Financial Planning for Mental Health

Pre Test Financial Planning for Mental Health

Professional Development

10 Qs

Soal PPPK Pedagogik 4

Soal PPPK Pedagogik 4

Professional Development

15 Qs

Trg@home 1

Trg@home 1

Professional Development

10 Qs

Pre and Post Test

Pre and Post Test

Professional Development

10 Qs

Anatomia capilar

Anatomia capilar

Professional Development

15 Qs

Pre-Test - Fast track

Pre-Test - Fast track

Assessment

Quiz

Professional Development

Professional Development

Practice Problem

Medium

Created by

Afghanistan Center

Used 31+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

14 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager is leading a construction project and the initial requirements have been fully defined. Midway through the project, a stakeholder requests a significant change. What should the project manager do first?

Implement the change immediately to meet stakeholder needs.

Perform a feasibility study to determine the impact of the change.

Reject the change as it is outside the scope defined in the planning phase.

Submit the change request to the change control board (CCB) for review.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During the execution phase of a Waterfall project, the project manager realizes that one of the deliverables is taking longer to complete than initially planned. What is the most appropriate action?

Skip some quality checks to catch up on the schedule.

Reassign tasks to team members without consulting them.

Continue with the current plan as deviations are expected.

Update the project schedule and inform the stakeholders.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a Waterfall project, the design phase is complete, and the team is moving into the development phase. A team member suggests a minor change to improve the design. What should the project manager do?

Approve the change to improve the project outcome.

Reject the change as the design phase is already completed.

Implement the change and document it later.

Submit a change request and assess the impact.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager is overseeing a software development project using the Waterfall methodology. The project is currently in the testing phase, and a critical bug is discovered. What should the project manager do?

Halt the testing phase and return to the development phase.

Log the bug and proceed with testing until the end of the phase.

Immediately implement a fix and continue testing.

Escalate the issue to the change control board.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A stakeholder wants to add a new feature to the product during the execution phase of a Waterfall project. How should the project manager respond?

Implement the feature to ensure stakeholder satisfaction.

Explain that changes are not allowed after the planning phase.

Submit a change request for impact analysis and review.

Integrate the feature into the project plan without formal approval.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During a review meeting, a stakeholder expresses dissatisfaction with the current progress of the project. The project manager realizes that the issue stems from unclear requirements. What should the project manager do next?

Adjust the project deliverables to meet the stakeholder's expectations.

Review the original requirements document and initiate a change request if necessary.

Proceed with the project as planned to avoid delays.

Request additional funding to accommodate the changes.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In a Waterfall project, the project manager notices that the team is consistently behind schedule. What is the most effective course of action?

Reduce the scope of the project to meet the deadlines.

Increase the working hours for the team members.

Conduct a detailed review of the project plan and adjust the timeline.

Move resources from other projects to speed up completion.

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?