PMI-CP_M4 Scope or Change

Quiz
•
Professional Development
•
Professional Development
•
Medium
Benigno Cruz
Used 1+ times
FREE Resource
51 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which one of these statements is incorrect?
Business goals and business objectives drive
early scope discussions and definition.
A scope statement starts with a problem to be
solved, also called business opportunity.
Business objectives and project performance
are the foundation blocks of all projects.
Every project has one single business objective which leads to different performance outcomes.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Good outcomes are:
Specific, Measurable, and Realistic
Multiple, Measurable, and Predictable
Specific, Reproducible, and Predictable
Expansible, Reproducible, and Realistic
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
There are a var iety of methods and
tools that help to define robust
business objectives and performance
outcomes. Which of the below has a
strong focus on collaboration across
the project team?
SMART approach
Basic logic model tool
CLEAR goals method
Modern business approach
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
By validating the scope change, you
Take the project out of its course
Increase unwarranted changes
Lower the owner's expectations
Reduce unwanted changes
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following statements about scope is correct?
In the built environment, project scope refers to a holistic view of all activities to be executed during the front-end phase.
The scope baseline identifies what's not included
and what is not to be delivered in the project.
The scope definition occurs before the vision and
project goals have been defined.
The lack of clear scope and goals are the number one consequence of claims and disputes.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is not part of front-end planning?
Determination of the business need
The general design outline
Identification of project risks
The cost of changes represented by the MacLeamy curve
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In this stage of the front-end planning, if the study does not generate positive outcomes, the idea is not progressed. Which stage is this?
Feasibility
Concept
Definition
Selection
Create a free account and access millions of resources
Similar Resources on Wayground
50 questions
Post Test PMLI

Quiz
•
Professional Development
46 questions
AZ400 quiz prelim prep 2

Quiz
•
Professional Development
48 questions
Sharepoint Administration Revision

Quiz
•
Professional Development
50 questions
Self-Leadership and Management Quiz

Quiz
•
Professional Development
50 questions
PMI-CP_M3_Contract and Risk

Quiz
•
Professional Development
50 questions
National Builder Farmwork 4

Quiz
•
Professional Development
50 questions
Cuestionario Resumen PMI-CP

Quiz
•
Professional Development
50 questions
PMP 380 mock questions - Chapter 2 (Process)

Quiz
•
Professional Development
Popular Resources on Wayground
18 questions
Writing Launch Day 1

Lesson
•
3rd Grade
11 questions
Hallway & Bathroom Expectations

Quiz
•
6th - 8th Grade
11 questions
Standard Response Protocol

Quiz
•
6th - 8th Grade
40 questions
Algebra Review Topics

Quiz
•
9th - 12th Grade
4 questions
Exit Ticket 7/29

Quiz
•
8th Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
19 questions
Handbook Overview

Lesson
•
9th - 12th Grade
20 questions
Subject-Verb Agreement

Quiz
•
9th Grade