1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which one of these statements is incorrect?

Business goals and business objectives drive

early scope discussions and definition.

A scope statement starts with a problem to be

solved, also called business opportunity.

Business objectives and project performance

are the foundation blocks of all projects.

Every project has one single business objective which leads to different performance outcomes.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Good outcomes are:

Specific, Measurable, and Realistic

Multiple, Measurable, and Predictable

Specific, Reproducible, and Predictable

Expansible, Reproducible, and Realistic

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

There are a var iety of methods and

tools that help to define robust

business objectives and performance

outcomes. Which of the below has a

strong focus on collaboration across

the project team?

SMART approach

Basic logic model tool

CLEAR goals method

Modern business approach

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

By validating the scope change, you

Take the project out of its course

Increase unwarranted changes

Lower the owner's expectations

Reduce unwanted changes

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following statements about scope is correct?

In the built environment, project scope refers to a holistic view of all activities to be executed during the front-end phase.

The scope baseline identifies what's not included

and what is not to be delivered in the project.

The scope definition occurs before the vision and

project goals have been defined.

The lack of clear scope and goals are the number one consequence of claims and disputes.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is not part of front-end planning?

Determination of the business need

The general design outline

Identification of project risks

The cost of changes represented by the MacLeamy curve

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In this stage of the front-end planning, if the study does not generate positive outcomes, the idea is not progressed. Which stage is this?

Feasibility

Concept

Definition

Selection

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?

Discover more resources for Professional Development