Contractor's Possession of Site

Authored by Muhammad Nasrol Jamal

Other

University

Contractor's Possession of Site
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

40 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the value of the performance bond as a percentage of the total Contract Sum?

5%

10%

15%

20%

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What types of insurance are required before entering the site?

Third party liability insurance

Workmen compensation

Insurance of Work

All of the above

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the duration given to the Contractor to prepare after receiving the Letter of Acceptance?

1 week

2 weeks

3 weeks

4 weeks

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In the event that the giving of the possession of the whole Site is delayed beyond ninety (90) days of the 'Date for Possession' stated in the Letter of Acceptance, what must the S.O. do?

Give written notice to the Contractor of the causes of such delay.

Allow the Contractor to claim for loss and damage.

Terminate the contract immediately.

Proceed with the works regardless of the delay.

5.

MULTIPLE SELECT QUESTION

30 sec • 1 pt

What options does the Contractor have upon receiving the written notice of delay?

Agree to proceed with the Works.

Terminate the contract.

Request for an extension of time.

Claim for loss and damage.

6.

MULTIPLE SELECT QUESTION

30 sec • 1 pt

What happens if the giving of possession of any section or part of the Site is delayed beyond ninety (90) days?

The Contractor must inform the S.O. in writing.

The Contractor can claim for any loss and/or expenses.

The S.O. must send a written notice to the Contractor.

The contract is automatically terminated.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What must the notice from the S.O. include when the possession is delayed?

Reasons for the delay.

A new date for possession.

Compensation details.

A request for the Contractor's decision.

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?