Project Management Quiz Module 2B

Project Management Quiz Module 2B

12th Grade

15 Qs

quiz-placeholder

Similar activities

Time management

Time management

12th Grade

10 Qs

Year 12 Business Studies - Operations Quiz

Year 12 Business Studies - Operations Quiz

12th Grade

20 Qs

Fundamentals of Management

Fundamentals of Management

12th Grade

10 Qs

1.7 Organisational Planning Tools

1.7 Organisational Planning Tools

10th - 12th Grade

15 Qs

GPOn.1

GPOn.1

12th Grade

20 Qs

Project Mgmt. I Final Review 1 21-22

Project Mgmt. I Final Review 1 21-22

9th - 12th Grade

20 Qs

Gantt Charts and MS Project

Gantt Charts and MS Project

12th Grade

20 Qs

Management Theories

Management Theories

7th Grade - University

10 Qs

Project Management Quiz Module 2B

Project Management Quiz Module 2B

Assessment

Quiz

Business

12th Grade

Hard

Created by

Craig Sheely

FREE Resource

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is a Work Breakdown Structure (WBS)?

A method to prioritize tasks based on importance

A flow-chart diagram used to decompose a project into manageable parts

A tool to visualize a project's schedule with bars

A list of completed tasks and deliverables

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the purpose of categorization in project management?

To decompose tasks into smaller units

To organize items into related groups

To visualize a project's schedule

To list completed tasks

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the main function of a GANTT Chart?

To estimate the cost of a project

To visualize a project's schedule with a timeline

To list completed tasks

To decompose a project into smaller tasks

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the main difference between a GANTT Chart and a PERT Chart?

GANTT Chart uses bars; PERT Chart uses nodes and arrows

GANTT Chart lists tasks; PERT Chart prioritizes tasks

GANTT Chart decomposes tasks; PERT Chart visualizes schedule

GANTT Chart is for prioritization; PERT Chart is for categorization

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is Lead Time?

The delay between the end of one task and the beginning of the next

The amount of time a task is paused without affecting the schedule

The amount of time saved by starting a task early

The dependency of one task on another

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is Dependency in project management?

The amount of time saved by starting a task early

A delay between the end of one task and the beginning of the next

The amount of time a task is paused without affecting the schedule

When a task depends on another activity to be completed in a certain order

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the role of a Stakeholder Register in communication?

To list all tasks

To outline communication methods

To provide stakeholder contact information

To delay tasks

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?