工程时间的延长
Authored by Muhammad Nasrol Jamal
Other
University

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
35 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
According to PWD 203A (2007), what should the contractor do regarding the completion date?
Complete the work on time
Delay the work
Ignore the completion date
Complete the work after the deadline
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What must the contractor do if the project is not completed on time?
Continue construction until completion
Stop all work immediately
Request additional funds
Notify the employer
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What happens if the completion date is not clearly defined?
The project must be completed within a reasonable time
The employer can charge LAD for delays
The contractor can demand an extension
The project can be abandoned
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the meaning of the extended time granted to the contractor?
Additional time to complete the project beyond the original completion date
A penalty for delays
A bonus for early completion
A requirement to finish faster
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What are the main categories of reasons for delayed completion?
Contractor's breach, Employer's breach, Any party's breach
Weather conditions, Material shortages, Labor strikes
Design changes, Client requests, Financial issues
Site conditions, Regulatory approvals, Equipment failure
6.
MULTIPLE SELECT QUESTION
30 sec • 1 pt
What are the main categories of delays in completion?
Contractor's breach - Contractor has no right to claim EOT
Employer or S.O. breach - Contractor has the right to claim EOT and can claim damages and costs
Any party's breach: - Situations beyond the control of the employer and contractor - Contractor has the right to EOT - No claims for damages and costs, such losses are shared by both parties
7.
MULTIPLE SELECT QUESTION
30 sec • 1 pt
Under what circumstances can the contractor's EOT claim be based?
Force majeure factors as per Clause 43.1(a)
Abnormal weather conditions as per Clause 43.1(b)
Suspension of works as per Clause 43.1(c)
Instructions from S.O. as per Clause 43.1(d)
Instructions from S.O. as per Clause 43.1(e)
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?