工程时间的延长

工程时间的延长

University

35 Qs

quiz-placeholder

Similar activities

APPLIED LINGUISTICS REVIEW 02

APPLIED LINGUISTICS REVIEW 02

University

35 Qs

Occ85 Establish work area protection and safety

Occ85 Establish work area protection and safety

KG - University

37 Qs

The Project Manager

The Project Manager

University

36 Qs

L3 Core 07 Analysing technical information, quantities and c

L3 Core 07 Analysing technical information, quantities and c

KG - University

40 Qs

ESL 3 Final Exam Practice 2

ESL 3 Final Exam Practice 2

University

40 Qs

BUILDING ECONOMICS II_ONLINE EXAM_150221

BUILDING ECONOMICS II_ONLINE EXAM_150221

University

40 Qs

CSM80003_P2

CSM80003_P2

University

30 Qs

Repaso Prueba Final MIBC

Repaso Prueba Final MIBC

University

30 Qs

工程时间的延长

工程时间的延长

Assessment

Quiz

Other

University

Hard

Created by

Muhammad Nasrol Jamal

FREE Resource

35 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

According to PWD 203A (2007), what should the contractor do regarding the completion date?

Complete the work on time

Delay the work

Ignore the completion date

Complete the work after the deadline

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What must the contractor do if the project is not completed on time?

Continue construction until completion

Stop all work immediately

Request additional funds

Notify the employer

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What happens if the completion date is not clearly defined?

The project must be completed within a reasonable time

The employer can charge LAD for delays

The contractor can demand an extension

The project can be abandoned

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the meaning of the extended time granted to the contractor?

Additional time to complete the project beyond the original completion date

A penalty for delays

A bonus for early completion

A requirement to finish faster

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What are the main categories of reasons for delayed completion?

Contractor's breach, Employer's breach, Any party's breach

Weather conditions, Material shortages, Labor strikes

Design changes, Client requests, Financial issues

Site conditions, Regulatory approvals, Equipment failure

6.

MULTIPLE SELECT QUESTION

30 sec • 1 pt

What are the main categories of delays in completion?

Contractor's breach - Contractor has no right to claim EOT

Employer or S.O. breach - Contractor has the right to claim EOT and can claim damages and costs

Any party's breach: - Situations beyond the control of the employer and contractor - Contractor has the right to EOT - No claims for damages and costs, such losses are shared by both parties

7.

MULTIPLE SELECT QUESTION

30 sec • 1 pt

Under what circumstances can the contractor's EOT claim be based?

Force majeure factors as per Clause 43.1(a)

Abnormal weather conditions as per Clause 43.1(b)

Suspension of works as per Clause 43.1(c)

Instructions from S.O. as per Clause 43.1(d)

Instructions from S.O. as per Clause 43.1(e)

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?