According to PWD 203A (2007), what should the contractor do regarding the completion date?

工程时间的延长

Quiz
•
Other
•
University
•
Hard
Muhammad Nasrol Jamal
FREE Resource
35 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Complete the work on time
Delay the work
Ignore the completion date
Complete the work after the deadline
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What must the contractor do if the project is not completed on time?
Continue construction until completion
Stop all work immediately
Request additional funds
Notify the employer
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What happens if the completion date is not clearly defined?
The project must be completed within a reasonable time
The employer can charge LAD for delays
The contractor can demand an extension
The project can be abandoned
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the meaning of the extended time granted to the contractor?
Additional time to complete the project beyond the original completion date
A penalty for delays
A bonus for early completion
A requirement to finish faster
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What are the main categories of reasons for delayed completion?
Contractor's breach, Employer's breach, Any party's breach
Weather conditions, Material shortages, Labor strikes
Design changes, Client requests, Financial issues
Site conditions, Regulatory approvals, Equipment failure
6.
MULTIPLE SELECT QUESTION
30 sec • 1 pt
What are the main categories of delays in completion?
Contractor's breach - Contractor has no right to claim EOT
Employer or S.O. breach - Contractor has the right to claim EOT and can claim damages and costs
Any party's breach: - Situations beyond the control of the employer and contractor - Contractor has the right to EOT - No claims for damages and costs, such losses are shared by both parties
7.
MULTIPLE SELECT QUESTION
30 sec • 1 pt
Under what circumstances can the contractor's EOT claim be based?
Force majeure factors as per Clause 43.1(a)
Abnormal weather conditions as per Clause 43.1(b)
Suspension of works as per Clause 43.1(c)
Instructions from S.O. as per Clause 43.1(d)
Instructions from S.O. as per Clause 43.1(e)
Create a free account and access millions of resources
Similar Resources on Quizizz
35 questions
CMT 210 Midterm Study Guide

Quiz
•
University
37 questions
Project Management Module 4

Quiz
•
University
31 questions
Analyze Phase

Quiz
•
University
32 questions
Mod 2 Unit 2

Quiz
•
University
36 questions
evaluating sources

Quiz
•
5th Grade - University
32 questions
They're a 10, but...

Quiz
•
University
40 questions
week13 wrap up

Quiz
•
University
32 questions
Mod 7 Unit 2

Quiz
•
University
Popular Resources on Quizizz
15 questions
Multiplication Facts

Quiz
•
4th Grade
25 questions
SS Combined Advisory Quiz

Quiz
•
6th - 8th Grade
40 questions
Week 4 Student In Class Practice Set

Quiz
•
9th - 12th Grade
40 questions
SOL: ILE DNA Tech, Gen, Evol 2025

Quiz
•
9th - 12th Grade
20 questions
NC Universities (R2H)

Quiz
•
9th - 12th Grade
15 questions
June Review Quiz

Quiz
•
Professional Development
20 questions
Congruent and Similar Triangles

Quiz
•
8th Grade
25 questions
Triangle Inequalities

Quiz
•
10th - 12th Grade