SELF TEST: Scope Management
Quiz
•
Construction
•
University
•
Medium
NURSHUHADA ZAINON
Used 2+ times
FREE Resource
Enhance your content in a minute
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Of the following, which is not part of project scope management?
Scope planning
Scope verification
Quality assurance
Create WBS
Answer explanation
Quality assurance is not part of project scope management. It is the quality assurance program of the entire organisation.
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
You are the project manager for the new Tenby School Project and will need as many inputs to the scope planning as possible. Of the following, which one is not an organisational process asset?
WBS
Organisational procedures
Organisational policies
Historical information
Answer explanation
The WBS is not an organisational process asset. Other answers are example of organisational process assets.
3.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
You are the Project Manager for a technical project. The project is about completing installation of a new operating system on 4500 workstations. You have, in your project cost and time estimates, told the customer that the estimates provided will be accurate if the workstations meet the hardware requirements of the new operating system. This is an example of which of the following?
Risk
Constraint
Order of magnitude
Assumption
Answer explanation
This is an example of an assumption since the workstations must meet the hardware requirements. The scenario did not describe risk or constraint. Order of magnitude refers to the level of confidence in an estimate.
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
You are the Project Manager for the NBG Project. This project must be completed within six months. This is an example of which of the following?
Schedule
Assumption
Constraint
Planning process
Answer explanation
A project must be completed by a deadline is dealing with time constraint.
5.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
Which of the following best describes the project scope statement?
The description of the project deliverables.
The authorizing document that allows the project manager to move forward with the project and to assign resources to tasks.
The process of managing all of the required work - and only the required work - to create the project deliverables.
The process of planning and executing all of the required work in order to deliver the project to the customer.
Answer explanation
Choice A is a product description, not a scope. Choice B describes the charter. Choice D does not define the project scope as completely as choice C.
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Salman, a Project Manager you are mentoring, does not know which plan he should reference for guarding the project scope. Which of the following plans does Salman need?
The scope management plan
The scope change control system
The scope verification
The scope charter
Answer explanation
The scope management plan provides details about how the project scope may be changed. B is not a valid choice because it refers to the scope change control system, not the plan to guard the scope from changes. C is the process of formally accepting the product. D does not define how changes to the project may happen.
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
You need to ensure the customer formally accepts the deliverables of each project phase. This process is known as?
Earned value management
Scope verification
Quality control
Quality assurance
Answer explanation
A is incorrect because EVM measures project performance. C is concerned with the correctness of the work, not the acceptance of the work. D describe the quality program for the organisation as a whole.
Create a free account and access millions of resources
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?
Similar Resources on Wayground
10 questions
Principles of Management W4
Quiz
•
University
13 questions
QHSE---Qualité en BTP
Quiz
•
University
10 questions
Construção
Quiz
•
University
10 questions
307 Central Heating Systems 3 Quiz
Quiz
•
2nd Grade - University
10 questions
CIVL372_Quiz 1
Quiz
•
University
15 questions
Construction Industry Trivia Challenge
Quiz
•
12th Grade - University
5 questions
Week 21 - Quiz 4 - Bracing Systems
Quiz
•
University
10 questions
Division 06 Review
Quiz
•
University
Popular Resources on Wayground
20 questions
Halloween Trivia
Quiz
•
6th - 8th Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
15 questions
Order of Operations
Quiz
•
5th Grade
20 questions
Halloween
Quiz
•
5th Grade
16 questions
Halloween
Quiz
•
3rd Grade
12 questions
It's The Great Pumpkin Charlie Brown
Quiz
•
1st - 5th Grade
20 questions
Possessive Nouns
Quiz
•
5th Grade
10 questions
Halloween Traditions and Origins
Interactive video
•
5th - 10th Grade
Discover more resources for Construction
10 questions
Halloween Movies Trivia
Quiz
•
5th Grade - University
12 questions
Halloween
Quiz
•
3rd Grade - University
5 questions
Using Context Clues
Interactive video
•
4th Grade - University
20 questions
Definite and Indefinite Articles in Spanish (Avancemos)
Quiz
•
8th Grade - University
7 questions
Force and Motion
Interactive video
•
4th Grade - University
14 questions
Eat Healthy,Be Healty
Quiz
•
4th Grade - University
7 questions
History of Halloween: Pagan or Christian?
Interactive video
•
11th Grade - University
7 questions
Renewable and Nonrenewable Resources
Interactive video
•
4th Grade - University