
SELF TEST: Scope Management

Quiz
•
Construction
•
University
•
Medium
NURSHUHADA ZAINON
Used 2+ times
FREE Resource
10 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Of the following, which is not part of project scope management?
Scope planning
Scope verification
Quality assurance
Create WBS
Answer explanation
Quality assurance is not part of project scope management. It is the quality assurance program of the entire organisation.
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
You are the project manager for the new Tenby School Project and will need as many inputs to the scope planning as possible. Of the following, which one is not an organisational process asset?
WBS
Organisational procedures
Organisational policies
Historical information
Answer explanation
The WBS is not an organisational process asset. Other answers are example of organisational process assets.
3.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
You are the Project Manager for a technical project. The project is about completing installation of a new operating system on 4500 workstations. You have, in your project cost and time estimates, told the customer that the estimates provided will be accurate if the workstations meet the hardware requirements of the new operating system. This is an example of which of the following?
Risk
Constraint
Order of magnitude
Assumption
Answer explanation
This is an example of an assumption since the workstations must meet the hardware requirements. The scenario did not describe risk or constraint. Order of magnitude refers to the level of confidence in an estimate.
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
You are the Project Manager for the NBG Project. This project must be completed within six months. This is an example of which of the following?
Schedule
Assumption
Constraint
Planning process
Answer explanation
A project must be completed by a deadline is dealing with time constraint.
5.
MULTIPLE CHOICE QUESTION
2 mins • 1 pt
Which of the following best describes the project scope statement?
The description of the project deliverables.
The authorizing document that allows the project manager to move forward with the project and to assign resources to tasks.
The process of managing all of the required work - and only the required work - to create the project deliverables.
The process of planning and executing all of the required work in order to deliver the project to the customer.
Answer explanation
Choice A is a product description, not a scope. Choice B describes the charter. Choice D does not define the project scope as completely as choice C.
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Salman, a Project Manager you are mentoring, does not know which plan he should reference for guarding the project scope. Which of the following plans does Salman need?
The scope management plan
The scope change control system
The scope verification
The scope charter
Answer explanation
The scope management plan provides details about how the project scope may be changed. B is not a valid choice because it refers to the scope change control system, not the plan to guard the scope from changes. C is the process of formally accepting the product. D does not define how changes to the project may happen.
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
You need to ensure the customer formally accepts the deliverables of each project phase. This process is known as?
Earned value management
Scope verification
Quality control
Quality assurance
Answer explanation
A is incorrect because EVM measures project performance. C is concerned with the correctness of the work, not the acceptance of the work. D describe the quality program for the organisation as a whole.
Create a free account and access millions of resources
Similar Resources on Wayground
8 questions
Sustainability and Pre planning Documents

Quiz
•
University
15 questions
Construction Industry Trivia Challenge

Quiz
•
12th Grade - University
8 questions
Blockchain Innovations in Construction

Quiz
•
University
15 questions
Health and Safety Executive (HSE) Quiz

Quiz
•
12th Grade - University
10 questions
Kuis Dasar K2 2025

Quiz
•
University
10 questions
Project Scheduling

Quiz
•
University
10 questions
Bidding

Quiz
•
University
10 questions
Roles of QS at Pre and Post Contract Stage

Quiz
•
University
Popular Resources on Wayground
18 questions
Writing Launch Day 1

Lesson
•
3rd Grade
11 questions
Hallway & Bathroom Expectations

Quiz
•
6th - 8th Grade
11 questions
Standard Response Protocol

Quiz
•
6th - 8th Grade
40 questions
Algebra Review Topics

Quiz
•
9th - 12th Grade
4 questions
Exit Ticket 7/29

Quiz
•
8th Grade
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
19 questions
Handbook Overview

Lesson
•
9th - 12th Grade
20 questions
Subject-Verb Agreement

Quiz
•
9th Grade