A project manager has two projects that are being executed at the same time The duration of the critical project must be reduced, but the project manager does not have enough resources to achieve this goal In addition, the schedule does not have activities that can be overlapped.What should the project manager do?

200/1700

Quiz
•
Professional Development
•
4th Grade
•
Hard
Afghanistan Center
FREE Resource
16 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Analyze both projects to determine the most effective use of common resources
Use resource optimization to justify requesting more resources for the critical project
Provide schedule optimization training to the project teams to improve their skills.
Apply fast-tracking techniques to compress the schedule of the critical project
2.
MULTIPLE SELECT QUESTION
30 sec • 1 pt
Which two actions should a project manager consider while launching a new virtual team? (Choose two)
Recruit the best resources within the organization to be part of the virtual team
Evaluate the project manager’s own strengths and weaknesses as a virtual team leader to identify avoidable pitfalls
Identify the types and quantities of resources required for each work package or activity
Establish in the beginning, how progress will be monitored and the best means for communicating progress
Verify if team members are on more than one team and cannot devote enough time to this team
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
After reviewing the project management plan with key stakeholders, the project manager was told that an 18-month release plan was unacceptable and the product should launch in six months. Based on the new timeline, what should the project manager do?
Plan for overtime apply crashing and fast tracking and share the risk of failure with project stakeholders
Review the project backlog looking for high-priority items and come up with a minimum viable product (MVP) that fits the expected timeline
Seek approval with the sponsor to triple the project budget, hiring more people to compensate for the compressed schedule
Go over the critical path with stakeholders, explaining why it is not possible to deliver all the scope in the expected timeline
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A Scrum team has committed to delivering a specific capability in their first release Multiple operational issues have prevented the developer from delivering key capabilities. The technical lead has also given notice that they are resigning from the company.What should the project manager have the Scrum team do to recover from these issues?
Review constraints in the ongoing sprint planning and evaluate options for the release plan
Stop the sprint and replan and prioritize the backlog to reduce resource levels
Consult the resource management plan for an appropriate response
Continue with existing sprint plans to ensure some of the scope will be delivered
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The project team follows a hybrid framework for its delivery. During the execution of a project, the team learns of a new compliance requirement that has to be delivered before any other requirements.How should the project manager address this situation?
Ask the team to include the compliance requirement in the current sprint and deliver it.
Add the new compliance requirement to the backlog as the technical team does not have any capacity.
Include the compliance lead in the stakeholders list and wait for the next status meeting
Collaborate with the compliance team member to review and prioritize the requirement’s delivery
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
A project manager is assigned to a project in a company that is transitioning to agile Not all stakeholders believe in the project, and some stakeholders would like the entire project defined and planned out early in the project However the project sponsor needs a quick win to ensure the continuation of the project.What approach should the project manager use?
An agile approach as this would provide working functionality earlier
A predictive approach as this would please the senior stakeholders
A hybrid project as this will mitigate stakeholders' concerns.
A predictive approach as this will show benefits for all stakeholders
7.
MULTIPLE SELECT QUESTION
30 sec • 1 pt
A large project is affecting the neighborhood in which it is located The neighbors are not satisfied with the project and their resistance to the project may affect the project deadline.What two actions should the project manager take'? (Choose two)
Send letters to the neighbors and ask them kindly not to disturb the project.
Set up a meeting with neighborhood representatives to win their cooperation
Analyze the situation and find out what is causing the neighborhood's negative attitude.
Ask the customer to extend the project deadline to allow time for conflict resolution
Ask the mayor of the city to use their authority to stop neighborhood resistance
Create a free account and access millions of resources
Similar Resources on Quizizz
12 questions
W.6 TA3 Workplace Meeting

Quiz
•
3rd Grade - University
14 questions
Blank Quiz 101

Quiz
•
4th Grade
12 questions
AM Game

Quiz
•
1st - 12th Grade
20 questions
PMP MOCK Phase 1

Quiz
•
1st - 10th Grade
14 questions
Project Ceo

Quiz
•
1st - 12th Grade
18 questions
Leader in Me: Habit #2 (Begin With the End in Mind)

Quiz
•
4th - 5th Grade
14 questions
Kaun Banega S&RC King

Quiz
•
4th - 6th Grade
11 questions
PPR Practice

Quiz
•
KG - University
Popular Resources on Quizizz
15 questions
Multiplication Facts

Quiz
•
4th Grade
20 questions
Math Review - Grade 6

Quiz
•
6th Grade
20 questions
math review

Quiz
•
4th Grade
5 questions
capitalization in sentences

Quiz
•
5th - 8th Grade
10 questions
Juneteenth History and Significance

Interactive video
•
5th - 8th Grade
15 questions
Adding and Subtracting Fractions

Quiz
•
5th Grade
10 questions
R2H Day One Internship Expectation Review Guidelines

Quiz
•
Professional Development
12 questions
Dividing Fractions

Quiz
•
6th Grade
Discover more resources for Professional Development
15 questions
Multiplication Facts

Quiz
•
4th Grade
20 questions
math review

Quiz
•
4th Grade
20 questions
Parts of Speech

Quiz
•
3rd - 6th Grade
20 questions
Fun Trivia

Quiz
•
2nd - 4th Grade
20 questions
Basic multiplication facts

Quiz
•
4th Grade
26 questions
June 19th

Quiz
•
4th - 9th Grade
20 questions
Math Review

Quiz
•
4th Grade
12 questions
Story Elements

Quiz
•
4th Grade