30 sec • 1 pt
How many Solution Delivery tickets took 154 days to process
153
89
312
2.
FILL IN THE BLANKS QUESTION
30 sec • 1 pt
Name one of the 4 initiative that COAT implemented
(a)
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
How many SOAR-developed solutions suffered from delay?
14 solutions had an average delay of 78 days
48 solutions had an average delay of 23 days
17 solutions had an average delay of 41 days
4.
FILL IN THE BLANKS QUESTION
30 sec • 1 pt
What automation tool was used to produce ISMSDO age report
(a)
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
How much did the cycle time improve?
26%
49%
13%
Answer explanation
Cycle time reduction was from 154 days to 35 days
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the meaning of ISCS?
Intelligent Solution Computing Standard
Internet Server Controls Standard
Intelligent Solution Controls Standard
7.
FILL IN THE BLANKS QUESTION
30 sec • 1 pt
What is the C in COAT Project?
(a)
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?