1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Top-down estimates are most likely to occur during the ______ phase

Conceptual

Planning

Execution

Delivery

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following describes the "six-tenths" rule?

Project Evaluation based on price inflation over time

Cost estimation method based on size or capacity

Project Evaluation based on probability pricing

Cost estimation method based on price index of an item

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How many activity duration estimates are used for Program Evaluation & Review Technique?

One

Two

Three

Four

4.

LABELLING QUESTION

30 sec • 1 pt

Label the work breakdown structure (WBS) according to its hierarchy level.

a
b
c
d
Milestone
Work package
Task
Project

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the most effective communication channel?

Email

Face-to-face

Social Media

Written letter

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

For the PERT Analysis, the calculation of the duration of each activity follows:

te=(2a+4m+2b)/6


te=(a+4m+b)/6


te=(a+4m+b)/3


te=(a+4m+b)/2

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following key characteristics of a task is false?


Be unambiguous


Be continuous in time

Be longer than a standard reporting period

Be performed at a single site

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?