1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Top-down estimates are most likely to occur during the ______ phase
Conceptual
Planning
Execution
Delivery
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following describes the "six-tenths" rule?
Project Evaluation based on price inflation over time
Cost estimation method based on size or capacity
Project Evaluation based on probability pricing
Cost estimation method based on price index of an item
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
How many activity duration estimates are used for Program Evaluation & Review Technique?
One
Two
Three
Four
4.
LABELING QUESTION
30 sec • 1 pt
Label the work breakdown structure (WBS) according to its hierarchy level.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the most effective communication channel?
Face-to-face
Social Media
Written letter
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
For the PERT Analysis, the calculation of the duration of each activity follows:
te=(2a+4m+2b)/6
te=(a+4m+b)/6
te=(a+4m+b)/3
te=(a+4m+b)/2
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following key characteristics of a task is false?
Be unambiguous
Be continuous in time
Be longer than a standard reporting period
Be performed at a single site
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Microsoft
or continue with
%20(1).png)
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?