PC12 - Week 1 - Variance, CPI, SPI Final Quiz
Authored by Tom Robinson
Construction
11th Grade
Used 1+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
24 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
What is Schedule Variance (SV)?
Difference between BCWP and ACWP
Difference between BCWS and ACWP
Difference between BCWP and BCWS
Difference between ACWP and PV
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Which of the following indicates a project is behind schedule?
Positive SV
Negative SV
Positive CV
Negative CV
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
What does a positive Cost Variance (CV) indicate?
Project is over budget
Project is on budget
Project is ahead of schedule
Project is under budget
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
What does the Cost Performance Index (CPI) measure?
Schedule efficiency
Cost efficiency
Labour efficiency
Equipment efficiency
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
What is the purpose of an S-Curve in project management?
To track individual tasks
To monitor cumulative project progress
To manage team communication
To allocate resources
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Which software is commonly used to generate S-Curves?
Excel
Primavera P6
AutoCAD
Photoshop
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
What does a steep rise in ACWP without a corresponding increase in BCWP suggest?
Cost underrun
Efficient use of resources
Cost overrun
Schedule adherence
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?