PC12 - Week 1 - Variance, CPI, SPI Final Quiz

Authored by Tom Robinson

Construction

11th Grade

Used 1+ times

PC12 - Week 1 - Variance, CPI, SPI Final Quiz
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

24 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is Schedule Variance (SV)?

Difference between BCWP and ACWP
Difference between BCWS and ACWP
Difference between BCWP and BCWS
Difference between ACWP and PV

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of the following indicates a project is behind schedule?

Positive SV
Negative SV
Positive CV
Negative CV

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What does a positive Cost Variance (CV) indicate?

Project is over budget
Project is on budget
Project is ahead of schedule
Project is under budget

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What does the Cost Performance Index (CPI) measure?

Schedule efficiency
Cost efficiency
Labour efficiency
Equipment efficiency

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is the purpose of an S-Curve in project management?

To track individual tasks
To monitor cumulative project progress
To manage team communication
To allocate resources

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which software is commonly used to generate S-Curves?

Excel
Primavera P6
AutoCAD
Photoshop

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What does a steep rise in ACWP without a corresponding increase in BCWP suggest?

Cost underrun
Efficient use of resources
Cost overrun
Schedule adherence

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?