PC12 - Week 1 - Variance, CPI, SPI Final Quiz

PC12 - Week 1 - Variance, CPI, SPI Final Quiz

11th Grade

24 Qs

quiz-placeholder

Similar activities

4 External Render

4 External Render

11th Grade

22 Qs

PC12 - Week 1 - Variance, CPI, SPI Final Quiz

PC12 - Week 1 - Variance, CPI, SPI Final Quiz

Assessment

Quiz

Construction

11th Grade

Medium

Created by

Tom Robinson

Used 1+ times

FREE Resource

24 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is Schedule Variance (SV)?
Difference between BCWP and ACWP
Difference between BCWS and ACWP
Difference between BCWP and BCWS
Difference between ACWP and PV

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of the following indicates a project is behind schedule?
Positive SV
Negative SV
Positive CV
Negative CV

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What does a positive Cost Variance (CV) indicate?
Project is over budget
Project is on budget
Project is ahead of schedule
Project is under budget

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What does the Cost Performance Index (CPI) measure?
Schedule efficiency
Cost efficiency
Labour efficiency
Equipment efficiency

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is the purpose of an S-Curve in project management?
To track individual tasks
To monitor cumulative project progress
To manage team communication
To allocate resources

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which software is commonly used to generate S-Curves?
Excel
Primavera P6
AutoCAD
Photoshop

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What does a steep rise in ACWP without a corresponding increase in BCWP suggest?
Cost underrun
Efficient use of resources
Cost overrun
Schedule adherence

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?