20 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

An agile project is in its third sprint. The participation from sales and the sponsor is infrequent. The sponsor states that they will participate when an important portion of the functionality becomes available. What should the agile leader do?

Escalate the issue to their manager.

Adjust the backlog priorities so that each sprint contains at least one important portion of functionality.

Accept the sponsor's response.

Explain the importance of early feedback in reducing the need for future rework and waste.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Agile enterprise framework consists of four layers: portfolio governance, project management, iteration management, and technical practices. What layers are the most suitable for the implementation of Scrum and eXtreme Programming (XP) methods?

Portfolio governance and project management

All layers are equally suitable

Iteration management and technical practices

None of the layers are suitable

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During a sprint planning meeting, the scrum team is arguing over 115 story points' worth of user stories that the product owner is pushing to be completed in the upcoming sprint. However, the development team's average velocity is only 100 story points. Who makes the final decision on how many story points will be targeted for completion during a sprint?

The project manager

The development team

The scrum master

The product owner

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A new team member has recently joined an experienced high performing team. The new team member approaches the agile coach and recommends using a new testing methodology that if successful would save the team time in each iteration. If the new testing method is unsuccessful, it could threaten the iteration goals. What should the agile coach do?

Allow the new testing approach for next iteration

Let the team decide whether to use the new testing methodology in the next iteration

Don't do anything that would jeopardize the iteration goals

Check with the product owner

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

An agile project will be using new technology. At the release planning meeting, the project manager insisted on getting a forecast for the release's completion date despite team members protesting that they need to run a few iterations first to provide an estimate. What should an agile practitioner do in this situation?

Recommend using historical values of velocity from previous projects to make a forecast

Support the project manager's demand and force the team to provide a forecast

Recommend using the cone of uncertainty to calculate a velocity and make a forecast based on this

Support the team's response to run a few iterations first before providing a forecast

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In order to enable osmotic communication, a project manager ensured that all team members who needed to communicate often with each other were co-located. This worked well for the team until the technical lead complained about the noise around him, preventing him from focusing on some difficult programming tasks. The project manager suggested an idea where the technical lead should not be disturbed by the discussions of his teammates. What was the project manager referring to?

Caves and common

Tacit knowledge

Adaptive communication

Bus-length communication

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A team has found a defect in the product they have been developing. The team members remembered that they have already fixed the defect in the last iteration, but it repeated itself in the current one. What should the team do to find the reason for this reoccurrence?

Carry out an architectural spike

Create a fishbone diagram

Discuss the issue in the next review

Consult the team's senior developer

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?