1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
You are the project manager of the GUY Project for your organization. This project has recently been chartered and you're starting the process of stakeholder identification. In this process, you're working with your project team, some of the known stakeholders, and your project sponsor.
Which one of the following inputs will you NOT need for the stakeholder identification process?
Organizational process assets
Risk management plan
Agreements
Project charter
Answer explanation
B. The risk management plan is not an input to the stakeholder identification process.
A, C, and D are incorrect because these answers are inputs to the stakeholder identification process.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Beth is the project manager for a large healthcare project. She is working with the project sponsor to define the steps she'll use to perform stakeholder analysis.
Which of the following correctly defines the steps for stakeholder analysis?
Identify and document the stakeholder information, create a communications management plan, plan for stakeholder management.
Identify and document the stakeholder information, prioritize and classify the stakeholders, create the communications management plan for stakeholder management
Identify and document the stakeholder information, prioritize and classify the stakeholders, plan for stakeholder management
Create a focus group for known stakeholders, identify and document the stakeholder information, prioritize and classify the stakeholders, plan for stakeholder management
Answer explanation
C. Of all the choices presented, C is the best answer. Stakeholder identification starts with the project manager identifying and documenting the stakeholders contact information, knowledge, expectations of the project, and their level of influence over project decisions. Then the project manager must prioritize and classify stakeholders based on their power, influence, expectations, and concerns for the project. Finally, Beth should plan for managing the stakeholders based on possible negative or positive scenarios in the project that may affect the stakeholders.
A, B, and D are incorrect because these answers do not reflect the correct ordering of steps for stakeholder analysis.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
You are the project manager for your organization. Management has asked you to create a stakeholder classification model to show the amount of authority stakeholders have over project decisions in relation to how much their political capital and position in the company could affect the project.
What type of stakeholder classification model should you create?
A power/influence grid
A RAM matrix
An influence/impact grid
A RACI chart
Answer explanation
A. Management is asking you to create a power/influence grid. Evaluating the amount of power and influence a stakeholder has over the project will determine where the stakeholder is placed on the grid. Stakeholders with high power and high influence are top priority. Stakeholders with little power and influence are still considered, but they have less priority than other stakeholders in the project.
B is incorrect because a RAM is a responsibility assignment matrix.
C is incorrect because this classification model focuses on the influence of the stakeholders and their impact, not their power.
D is incorrect because RACI is a responsibility matrix that tracks a pe
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Henry has been tasked to create a salience model for his project. This model defines three characteristics for project stakeholders.
Which one of the following is not one of the three characteristics of the stakeholders mapped in the salience model?
Power
Urgency
Legitimacy
Influence
Answer explanation
D. A salience model plots out a person's power, urgency, and legitimacy in the project. It does not include their influence.
A, B, and C are incorrect because these answers are part of the salience model.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
You are the project manager of a large technology project for your company. This project will span the United States and parts of Europe. There are key stakeholders in all countries represented. As part of your stakeholder analysis, you'd like to create a document that captures all of the stakeholders' contact information, assessment information, and classification in the project.
What type of document are you creating?
Stakeholder director
Stakeholder engagement plan
Stakeholder register
Stakeholder communications matrix
Answer explanation
C You are creating a stakeholder register. The stakeholder register is the only output of stakeholder identification. It's a log of all the stakeholder information you've gathered in the project. It will help you communicate with project stakeholders; ensure that you understand the stakeholders needs, wants, and expectations; and help you classify stakeholder objectives and priorities.
A and D are incorrect because there are no project management documents called the stakeholder directory or the stakeholder communications matrix.
B is incorrect because the stakeholder engagement plan defines how the stakeholders will be identified and engaged, and how stakeholder engagement will be controlled.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Terry is the project manager of the ARB project for his company. Terry approaches Scott for his insight about the schedule for releasing the product the project will create. Scott doesn't know anything about the project Terry is working on and is surprised to learn about the product.
What type of stakeholder is Scott?
Unaware
Uninformed
Neutral
Sensitive
Answer explanation
A. Scott is an unaware stakeholder. Scott doesn't know about the project and the effect the project may have on him.
B and D are incorrect choices because there is no stakeholder classification known as uninformed or sensitive.
C is also incorrect because neutral describes a stakeholder who is neither opposed nor in favor of the project.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
You are a project management consultant for your company and you're meeting the stakeholders for the first time. Mary, a stakeholder, tells you that she hates the project and she hopes that it fails miserably.
What type of stakeholder is Mary?
Resistant
Unhappy
Honest
Defiant
Answer explanation
A. Mary is a resistant stakeholder. Mary knows about the project and doesn't want the change the project will bring. Although Mary may be unhappy, honest, and defiant, these answers are not stakeholder classification types, so choices
B, C, and D are incorrect.
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?