
Quick Drill
Authored by Dedy Hartanto
Construction
Professional Development
Used 2+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
31 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A project manager presented the project schedule to the main stakeholders. They requested that the project be completed two months earlier. What should the project manager do?
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A project manager is assigned to a project in a company that is transitioning to agile. Not all stakeholders believe in the project, and some stakeholders would like the entire project defined and planned out early in the project. However, the project sponsor needs a quick win to ensure the continuation of the project. What approach should the project manager use?
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Two weeks after the approval of the project management plan for a global project, the project manager noticed that it was approved based on a different level of understanding by international stakeholders and is not what the project manager presented for approval. What should the project manager have done to prevent this from happening?
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Due to delays on some activities, one of the project team members has increased the scope without any approval. What should the project manager do next?
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
After 1 year into the lifecycle of an ongoing residential project, an announcement was received from the municipality regarding a new regulation that will greatly impact the project's schedule and budget. What should the project manager do next?
6.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A stakeholder is requesting that the project manager share project status updates on a regular basis. This stakeholder is not included in the regular distribution list. What should the project manager do?
7.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
A project manager accepts a delivery at the project site but the items are of poor quality. The project manager gets the local vendor to fix the items but more deliveries from this vendor are expected. What should the project manager do going forward?
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
30 questions
Quiz on Environmental Protection Measures
Quiz
•
Professional Development
29 questions
Understand Construction Information (2)
Quiz
•
Professional Development
26 questions
garys 05
Quiz
•
Professional Development
29 questions
Gas Fire Safety Quiz
Quiz
•
Professional Development
29 questions
Gas Consumption and Measurement Quiz
Quiz
•
Professional Development
Popular Resources on Wayground
15 questions
Fractions on a Number Line
Quiz
•
3rd Grade
20 questions
Equivalent Fractions
Quiz
•
3rd Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
22 questions
fractions
Quiz
•
3rd Grade
20 questions
Main Idea and Details
Quiz
•
5th Grade
20 questions
Context Clues
Quiz
•
6th Grade
15 questions
Equivalent Fractions
Quiz
•
4th Grade
20 questions
Figurative Language Review
Quiz
•
6th Grade
Discover more resources for Construction
10 questions
How to Email your Teacher
Quiz
•
Professional Development
6 questions
3RD GRADE DECLARATION OF INDEPENDENCE EXIT TICKET
Quiz
•
Professional Development
19 questions
Black History Month Trivia
Quiz
•
6th Grade - Professio...
22 questions
Multiplying Exponents with the Same Base
Quiz
•
9th Grade - Professio...
40 questions
Flags of the World
Quiz
•
KG - Professional Dev...