1.
MULTIPLE CHOICE QUESTION
20 sec • 1 pt
1. You are in the Plan Resource Management process of identifying and documenting project roles, responsibilities, required skills, competencies, reporting structure, and other items. The structure that you are using is arranged according to an organization’s existing departments, units, or teams with their respective work packages. Which of the following are you using?
Answer explanation
1. Question about Plan Resource Management tools :Explanation: A RAM, such as a RACI chart, is a key tool used in Plan Resource Management to document roles, responsibilities, and relationships in projects. It clearly shows who is Responsible, Accountable, Consulted, and Informed for project activities.
2.
MULTIPLE CHOICE QUESTION
20 sec • 1 pt
2. Project success is heavily dependent on the leadership and management style of the project manager. Even though we do not usually distinguish between leading and managing, it is generally believed that there is a difference between these two. Which of the following is typically considered to be a responsibility associated with managing?
Answer explanation
2. Question about project manager's leadership :Explanation: While all options are important leadership aspects, consistently producing expected results is the fundamental measure of project success. This directly impacts stakeholder satisfaction and project outcomes.
3.
MULTIPLE CHOICE QUESTION
20 sec • 1 pt
3. You made sure that one of the junior team members in your team received the required training to perform his activities. While assessing the team member, you were concerned to find out that the team member was still lacking the competency and required further improvement. What will be the BEST course of action?
Answer explanation
3. Question about handling team member training :Explanation: This is the most constructive approach. Rather than replacing the resource or taking punitive actions, providing additional focused training addresses the competency gap and helps develop the team member.
4.
MULTIPLE CHOICE QUESTION
20 sec • 1 pt
4. A project manager is overseeing a complex custom CSM solution that has rigorous quality standards and tight schedule constraints. The project manager just found out that one of the key deliverables in the project was not completed because the team member responsible for it was assigned to another higher-priority project by her functional manager. Who will be the person for the project manager to address the issue within this kind of situation?
Answer explanation
4. Question about project manager's power in a complex CSM solution :Explanation: In complex projects with tight schedules and quality requirements, the project manager's primary responsibility is to lead and empower the team to meet these challenges.
5.
MULTIPLE CHOICE QUESTION
20 sec • 1 pt
5. A project manager recently got her PMP certification and joined a professional project management group. The group members meet on a regular basis to discuss new opportunities, trends, and issues in project management. The satisfaction that the project manager gains from the association with this group is MOST closely aligned with:
Answer explanation
5. Question about motivation theory in professional groups :Explanation: The third level of Maslow's hierarchy relates to social needs/belonging, which aligns with joining professional groups for networking and community.
6.
MULTIPLE CHOICE QUESTION
20 sec • 1 pt
6. You are currently managing the team through observing, using issue logs, keeping in touch, providing feedback, completing performance appraisals, resolving issues and conflicts, and through other methods. You are in which of the following human resource management processes?
Answer explanation
6. Question about current management activities :Explanation: The activities described (observing, using issue logs, providing feedback) are part of the Manage Team process, which involves tracking team performance and providing feedback.
7.
MULTIPLE CHOICE QUESTION
20 sec • 1 pt
7. You are the project manager overseeing a project to build a navigation system for an auto company. You are in the Develop Team process, and your key focus is to enhance the project performance by building a sense of team and improving the competencies, team interaction, and overall team environment. You will be using all of the following tools & techniques in the process EXCEPT:
Answer explanation
7. Question about team development :Explanation: In the Develop Team process, establishing ground rules is crucial for setting team expectations and behavior standards.
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?