Contract Law Quiz

Contract Law Quiz

12th Grade

26 Qs

quiz-placeholder

Similar activities

Cosmetology Ch 31: On the Job

Cosmetology Ch 31: On the Job

11th - 12th Grade

26 Qs

Ch 8 Business Law: Consideration

Ch 8 Business Law: Consideration

10th - 12th Grade

30 Qs

Marketing Chapter 4

Marketing Chapter 4

9th - 12th Grade

21 Qs

Muscle Functionality

Muscle Functionality

9th - 12th Grade

27 Qs

Personal Law FINAL 2025

Personal Law FINAL 2025

9th - 12th Grade

30 Qs

Contracts Overview

Contracts Overview

12th Grade

25 Qs

Business Law - Contract Basics

Business Law - Contract Basics

10th - 12th Grade

22 Qs

Law of Contract

Law of Contract

12th Grade

25 Qs

Contract Law Quiz

Contract Law Quiz

Assessment

Quiz

Other

12th Grade

Easy

Created by

Helena Taylor

Used 3+ times

FREE Resource

26 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Which of the following is NOT a way to discharge a contract?

Performance

Breach

Frustration

Agreement

Answer explanation

The correct answer is 'Agreement' because it refers to a mutual decision to modify or end a contract, rather than a method of discharging it. Performance, Breach, and Frustration are all valid ways to discharge a contract.

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

In the case of Cutter v Powell (1795), why was the contract discharged?

Cutter completed his work

Cutter died before completing his work, making performance incomplete

Cutter breached the contract by not finishing his work

Cutter was fired before completing his work

Answer explanation

The contract was discharged because Cutter died before completing his work, which rendered the performance incomplete. This means he could not fulfill the terms of the contract.

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is the strict rule of performance in contract law?

Performance must be substantial

Performance must be complete and exact

Performance must be reasonable

Performance must be partial

Answer explanation

The strict rule of performance in contract law requires that performance must be complete and exact. This means that parties must fulfill their contractual obligations precisely as agreed, without deviations.

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

In Dakin & Co. v Lee (1916), what was the court's decision regarding substantial performance?

The builders were not entitled to any payment

The builders were entitled to full payment

The builders were entitled to payment minus the cost of poor work

The builders were entitled to double payment

Answer explanation

In Dakin & Co. v Lee, the court ruled that the builders were entitled to payment, but it would be reduced by the cost of the poor work, reflecting the principle of substantial performance.

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is an actual breach of contract?

A party anticipates they will not perform

A party fails to perform their obligations according to the terms

A party performs their obligations exactly

A party performs their obligations substantially

Answer explanation

An actual breach of contract occurs when a party fails to perform their obligations according to the terms of the agreement. This distinguishes it from merely anticipating non-performance or performing obligations partially.

6.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

What are the two options of the innocent party in the context of anticipatory breach?

Repudiate the contract immediately

Claim restitition so that any benefits already received are returned

Wait for the time of agreed performance

Rescind the contract so parties are restored to their original positions

Answer explanation

In the context of anticipatory breach, the innocent party can choose to repudiate the contract immediately. This allows them to terminate the contract due to the other party's indication of non-performance. Or the innocent party can wait until the time agreed for performance to see the extent of the breach. They can then repudiate the contract if it is a breach of condition and sue for

damages, or sue for damages if it is a breach of warranty.

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

In Hochester v de la Tour (1853), what was the court's decision regarding anticipatory breach?

Hochester had to wait until June to repudiate the contract

Hochester could repudiate the contract immediately

Hochester could not repudiate the contract

Hochester had to perform his obligations

Answer explanation

In Hochester v de la Tour, the court ruled that Hochester could repudiate the contract immediately due to the anticipatory breach by the other party, allowing him to seek damages without waiting for the performance date.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?