1.

MATCH QUESTION

1 min • 5 pts

Match each contract or document with its correct description.

Con Mgmt For Services

CCDC 5A

Cost Plus Contract

CCDC 5B

Stipulated Price Contract

CCDC 2

Unit Price Contract

CCDC 3

Con Mgmt For Services & Construction

CCDC 4

2.

MATCH QUESTION

1 min • 5 pts

Match each contract or document with its correct description.

Civil Works Contract

CCDC 30

Design-Build Stipulated Price Contract

CCDC 14

Stip Price b/t Owner & Trade Contractor

CCDC 18

Design Services Contract b/t DB & Consul

CCDC 17

Integrated Project Delivery (IPD)

CCDC 15

3.

MATCH QUESTION

1 min • 5 pts

Match each contract or document with its correct description.

Stipulated Price Subcontract

P3

Stipulated Price Sub-Subcontract

CCA 19

Contract for Architectural Services

RAIC 6 (2017)

Public-Private Partnership Guidelines

CCDC 31

Service Contract b/t Owner & Consult.

CCA 1

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

An owner is managing a project where they want to directly hire multiple trade contractors for specific portions of the work. They want a firm price from a trade contractor for their scope of work. Identify the contract the owner would use to hire the trade contractors.

CCDC 17

CCDC 5A

CCDC 4

CCA 1

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

An owner is restoring a heritage building with significant unknowns in the scope of work. They want the flexibility to pay for actual costs plus a fixed or percentage fee.

CCDC 2

CCDC 3

CCDC 14

CCDC 5B

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A government is commissioning a large transportation project and wants to collaborate with private companies to finance, design, build, and operate the project over a long-term agreement.

CCDC 18

P3

CCDC 30

CCDC 14

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

An owner needs a warehouse and prefers a single point of responsibility for design and construction. They want to know the project cost upfront.

CCDC 3

CCDC 4

CCDC 14

CCDC 15

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?