Search Header Logo

PMP MCQ SERIES-Risk

Authored by Shamsil ARFEEN

Other

University

Used 1+ times

PMP MCQ SERIES-Risk
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

43 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

1. If a project has a 60 % chance of a $100,000 profit and a 40 % chance of a $100,000 loss, the EMV for the Project will be;

A. $100,000 profit
B. $60,000 loss
C. $20,000 profit
D. $40,000 loss

Answer explanation

Explanation: Expected monetary value (EMV) is calculated by multiplying the probability by the impact. We need to calculate both positive and negative values and then add them: * 0.6 x $100,000 = $60,000 * 0.4 x ($100,000) = ($40,000) * Expected monetary value = $60,000 - $40,000 = $20,000 profit

2.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

2. Assuming the ends of a range of estimates are +/-3 sigma from the mean, which of the following range estimates involves the Least RISK?

A. 30 days, plus or minus 5 days
B. 22 to 30 days
C. Optimistic- 26 days, most likely 30 days, pessimistic-33 days
D. Mean of 28 days

Answer explanation

Explanation: The question asks which range estimate involves the least risk, given that the ends of the range are from the mean. Here’s the explanation of why the correct answer is C: Optimistic - 26 days, most likely 30 days, pessimistic - 33 days:

1. Understanding range and risk:

Risk is associated with the width of the range. A narrower range indicates less uncertainty and, therefore, less risk.

The width of the range is calculated as the difference between the pessimistic and optimistic estimates.

2. Analyzing each option:

Option A: 30 days ± 5 days

Range = .

Total range = 10 days.

Option B: 22 to 30 days

Range = .

Total range = 8 days.

Option C: Optimistic - 26 days, most likely - 30 days, pessimistic - 33 days

Range = .

Total range = 7 days.

This is the narrowest range, indicating the least risk.

Option D: Mean of 28 days

This is not a valid range estimate as it provides no variability or boundaries for the estimate.

3. Conclusion:

Option C has the narrowest range (7 days), representing the least uncertainty and therefore the least risk.

3.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

3. Your new project is tasked with designing a robotic device. A successful outcome for this high-profile project would

create a technological breakthrough and a significant market opportunity, but there is a lot of uncertainty about the

technology and requirements. The CFO has asked you to determine as quickly as possible whether the project is

viable. What would be the best approach for doing this?

A. Ask the team to perform thorough proof of concept tests before starting development.
B. Do a risk-based spike to determine if the Kansas testing facility is tornado-proof.
C. Have the team begin planning and development, and see if they reach an impasse.
D. Do an exploratory spike to research potential quality control issues and ways to mitigate them.

Answer explanation

Explanation: This scenario deals with the agile concept of fast failure, where we want to determine if a project is viable as quickly as possible. To determine project viability, agile teams typically use architectural spikes to do proof-of-concept testing. Performing proof-of-concept tests before starting development is the correct answer.

4.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

4. If a risk has a 20 % chance of happening in a given month, and the Project is expected to last 5 months,

What is the probability that this Risk event will occur during the 4-month of the project?

A. Less than 1 percent
B. 20 percent
C. 60 percent
D. 80 percent

Answer explanation

Explanation: No calculation is needed. If there is a 20 percent chance in any one month, the chance in the fourth month is 20 percent.

5.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

5. If a risk event has a 90 % chance of occurring, and the consequences will be $10,000, what does $9,000 represent?

A. Risk value
B. Present value
C. Expected monetary value
D. Contingency budget

Answer explanation

Explanation: Expected monetary value is calculated by multiplying the probability times the impact. In this case, EMV = 0.9 x $10,000 = $9,000.

6.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

6. Most of the project risks will be identified during which risk management processes?

A. Perform Quantitative Risk Analysis and Identify Risks
B. Identify Risks and Monitor Risks
C. Perform Qualitative Risk Analysis and Monitor Risks
D. Identify Risks and Perform Qualitative Risk Analysis

Answer explanation

Explanation: Although risks can be identified at any time throughout the project, most risks are identified during the Identify Risks process. Newly emerging risks are identified in the Monitor Risks process.

7.

MULTIPLE CHOICE QUESTION

20 sec • 1 pt

7. What kind of change-driven project would gain the most benefit from conducting a project pre-mortem exercise?

A. A high-value project with dear specifications for technology and requirements
B. An urgent, risky project with a hard deadline
C. A project that will require process tailoring
D. A long-term, high-visibility project

Answer explanation

Explanation: This question asks when a dedicated workshop for identifying potential risks would be most worthwhile. A long-term, high-visibility project is the correct answer.

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?