
PMP MCQ SERIES-Risk
Authored by Shamsil ARFEEN
Other
University
Used 1+ times

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
43 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
20 sec • 1 pt
1. If a project has a 60 % chance of a $100,000 profit and a 40 % chance of a $100,000 loss, the EMV for the Project will be;
Answer explanation
Explanation: Expected monetary value (EMV) is calculated by multiplying the probability by the impact. We need to calculate both positive and negative values and then add them: * 0.6 x $100,000 = $60,000 * 0.4 x ($100,000) = ($40,000) * Expected monetary value = $60,000 - $40,000 = $20,000 profit
2.
MULTIPLE CHOICE QUESTION
20 sec • 1 pt
2. Assuming the ends of a range of estimates are +/-3 sigma from the mean, which of the following range estimates involves the Least RISK?
Answer explanation
Explanation: The question asks which range estimate involves the least risk, given that the ends of the range are from the mean. Here’s the explanation of why the correct answer is C: Optimistic - 26 days, most likely 30 days, pessimistic - 33 days:
1. Understanding range and risk:
Risk is associated with the width of the range. A narrower range indicates less uncertainty and, therefore, less risk.
The width of the range is calculated as the difference between the pessimistic and optimistic estimates.
2. Analyzing each option:
Option A: 30 days ± 5 days
Range = .
Total range = 10 days.
Option B: 22 to 30 days
Range = .
Total range = 8 days.
Option C: Optimistic - 26 days, most likely - 30 days, pessimistic - 33 days
Range = .
Total range = 7 days.
This is the narrowest range, indicating the least risk.
Option D: Mean of 28 days
This is not a valid range estimate as it provides no variability or boundaries for the estimate.
3. Conclusion:
Option C has the narrowest range (7 days), representing the least uncertainty and therefore the least risk.
3.
MULTIPLE CHOICE QUESTION
20 sec • 1 pt
3. Your new project is tasked with designing a robotic device. A successful outcome for this high-profile project would
create a technological breakthrough and a significant market opportunity, but there is a lot of uncertainty about the
technology and requirements. The CFO has asked you to determine as quickly as possible whether the project is
viable. What would be the best approach for doing this?
Answer explanation
Explanation: This scenario deals with the agile concept of fast failure, where we want to determine if a project is viable as quickly as possible. To determine project viability, agile teams typically use architectural spikes to do proof-of-concept testing. Performing proof-of-concept tests before starting development is the correct answer.
4.
MULTIPLE CHOICE QUESTION
20 sec • 1 pt
4. If a risk has a 20 % chance of happening in a given month, and the Project is expected to last 5 months,
What is the probability that this Risk event will occur during the 4-month of the project?
Answer explanation
Explanation: No calculation is needed. If there is a 20 percent chance in any one month, the chance in the fourth month is 20 percent.
5.
MULTIPLE CHOICE QUESTION
20 sec • 1 pt
5. If a risk event has a 90 % chance of occurring, and the consequences will be $10,000, what does $9,000 represent?
Answer explanation
Explanation: Expected monetary value is calculated by multiplying the probability times the impact. In this case, EMV = 0.9 x $10,000 = $9,000.
6.
MULTIPLE CHOICE QUESTION
20 sec • 1 pt
6. Most of the project risks will be identified during which risk management processes?
Answer explanation
Explanation: Although risks can be identified at any time throughout the project, most risks are identified during the Identify Risks process. Newly emerging risks are identified in the Monitor Risks process.
7.
MULTIPLE CHOICE QUESTION
20 sec • 1 pt
7. What kind of change-driven project would gain the most benefit from conducting a project pre-mortem exercise?
Answer explanation
Explanation: This question asks when a dedicated workshop for identifying potential risks would be most worthwhile. A long-term, high-visibility project is the correct answer.
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?