Project Cost Management Principles Quiz

Project Cost Management Principles Quiz

University

15 Qs

quiz-placeholder

Similar activities

Decimal Multiplication: Estimation & Models Challenge

Decimal Multiplication: Estimation & Models Challenge

5th Grade - University

10 Qs

Project management

Project management

KG - University

15 Qs

Estimating Decimal Differences and Comparisons for 4th Graders

Estimating Decimal Differences and Comparisons for 4th Graders

4th Grade - University

10 Qs

PM - Lesson 7 + 8

PM - Lesson 7 + 8

University

17 Qs

Estimating Decimal Costs and Differences in Daily Life

Estimating Decimal Costs and Differences in Daily Life

4th Grade - University

10 Qs

CEN 102 Technical Terms #2

CEN 102 Technical Terms #2

University

16 Qs

Decimal Multiplication: Estimation & Models Challenge

Decimal Multiplication: Estimation & Models Challenge

5th Grade - University

10 Qs

Real-Life Decimal Challenges: Estimating & Multiplying

Real-Life Decimal Challenges: Estimating & Multiplying

5th Grade - University

10 Qs

Project Cost Management Principles Quiz

Project Cost Management Principles Quiz

Assessment

Quiz

English

University

Medium

Created by

Wiwied Virgiyanti

Used 12+ times

FREE Resource

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the total of direct and indirect costs incurred in accomplishing work on an activity during a given period known as?

Earned value (EV)

Actual Cost (AC)

Budget at Completion (BAC)

Schedule Variance (SV)

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The original project plan plus approved changes is called ______________.

Baseline

Cost Baseline

Cost Control

Cost Management Plan

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

__________________ is the ratio of actual work completed to the percentage of work planned to have been completed at any given time during the life of the project or activity.

Schedule Variance (SV)

Learning Curve Theory

Parametric Modeling

Rate of Performance (RP)

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

__________________ is the ratio of earned value to planned value; can be used to estimate the projected time to complete a project.

Indirect Costs

Life Cycle Costing

Schedule Variance (SV)

Schedule Performance Index (SPI)

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the cost estimate that provides an accurate estimate of project costs called?

Contingency Reserves

Baseline

Direct Costs

Definitive Estimate

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the term for a time-phased budget that project managers use to measure and monitor cost performance?

Cost Variance

Cost Baseline

Cost Budgeting

Cost Estimating

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the cost estimating technique based on estimating individual work items and summing them to get a project total called?

Analogous Estimates

Bottom-Up Estimates

Definitive Estimate

Parametric Estimate

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?