Pre Test - Akuntansi Pengantar ISC UAS Ganjil

Pre Test - Akuntansi Pengantar ISC UAS Ganjil

University

5 Qs

quiz-placeholder

Similar activities

FINE AGGREGATES

FINE AGGREGATES

University

10 Qs

Review Tabungan

Review Tabungan

12th Grade - University

10 Qs

QUIZ INFLASI

QUIZ INFLASI

KG - Professional Development

10 Qs

BASIC ELECTRONICS

BASIC ELECTRONICS

University

10 Qs

QUIZ KEL 6 EKO INTER

QUIZ KEL 6 EKO INTER

University

10 Qs

UGC and Games Social Networking

UGC and Games Social Networking

University

10 Qs

CHILD CARE

CHILD CARE

University

10 Qs

Civil Engineering Material Chapter 1 & 2

Civil Engineering Material Chapter 1 & 2

University

10 Qs

Pre Test - Akuntansi Pengantar ISC UAS Ganjil

Pre Test - Akuntansi Pengantar ISC UAS Ganjil

Assessment

Quiz

Education

University

Practice Problem

Hard

Created by

IMAGAMA IDE

Used 1+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

5 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 20 pts

1. PT Economics - Sistem Kos Proses (Metode MPKP) 

Data: 

• Sediaan Awal (200 unit): 

• Material: Rp378.000 (40%) 

• Konversi: Rp208.000 (60%) 

• Ditambahkan Tahun 2020 (1.200 unit): 

• Material: Rp10.080.000 

• Konversi: Rp4.160.000 

• Sediaan Akhir (300 unit): 

• Tingkat Penyelesaian: 

• Material: 80% 

• Konversi: 20%


Jika semua sumber daya yang tersedia (termasuk sediaan awal) digunakan untuk menyelesaikan produk, berapa unit produk jadi yang dapat diselesaikan?

A. 1.260 unit

B. 1.040 unit

C. 1.200 unit

D. 1.400 unit

2.

MULTIPLE CHOICE QUESTION

30 sec • 20 pts

 PT Imagama - Sistem Kos Proses (Metode MPKP) 

Data: 

• Sediaan Barang Dalam Proses Awal (100 unit): 

• Material: Rp900.000 (20%) 

• Konversi: Rp400.000 (80%) 

• Ditambahkan Tahun 2020 (900 unit): 

• Material: Rp9.000.000 

• Konversi: Rp4.000.000 

• Produksi Selesai: 800 unit 

• Sediaan Barang Dalam Proses Akhir: 

• Tingkat Penyelesaian: 

• Material: 60% 

• Konversi: 40% 

Pertanyaan: 

Mendekati berapakah biaya per unit produksi (Production Unit Cost) untuk konversi?


A. Rp4.650 

B. Rp5.500 

C. Rp5.000

D. Rp4.760

3.

MULTIPLE CHOICE QUESTION

30 sec • 20 pts

PT IDE - Sistem Kos Proses (Metode MPKP) Data: 

• Sediaan Barang Dalam Proses Awal (100 unit): • Material: Rp900.000 (20%) 

• Konversi: Rp400.000 (80%) 

• Ditambahkan Tahun 2020 (900 unit): 

• Material: Rp7.200.000 

• Konversi: Rp3.200.000 

• Sediaan Akhir (200 unit): 

• Tingkat Penyelesaian: 

• Material: 60% 

• Konversi: 40% 

Pertanyaan: 

Berapakah biaya sediaan barang dalam proses akhir?


A. Rp1.440.000 

B. Rp2.340.000 

C. Rp2.400.000 

D. Rp1.280.000

4.

MULTIPLE CHOICE QUESTION

30 sec • 20 pts

PT ISC - Sistem Kos Proses (Metode Rata-rata) Data: 

• Sediaan Barang Dalam Proses Awal (200 unit): • Material: Rp900.000 (100%) 

• Tenaga Kerja Langsung (TK): Rp600.000 (80%) • Overhead: Rp720.000 (40%) 

• Ditambahkan Tahun 2020 (1.800 unit): 

• Material: Rp14.100.000 

• TK Langsung: Rp4.920.000 

• Overhead: Rp4.320.000 

• Produksi Selesai: 1.600 unit 

• Sediaan Barang Dalam Proses Akhir: 

• Tingkat Penyelesaian: 

• Material: 100% 

• TK Langsung: 60% 

• Overhead: 20%

Pertanyaan: 

Jika seluruh sumber daya yang tersedia dicurahkan untuk produk selesai, berapakah unit selesai yang dapat dihasilkan? 

A. 1.680 unit

B. 1.840 unit 

C. 2.000 unit 

D. 1.800 unit

5.

MULTIPLE CHOICE QUESTION

30 sec • 20 pts

PT FEB - Sistem Kos Proses (Metode Rata-rata) 

Data: 

• Sediaan Barang Dalam Proses Awal (200 unit): 

• Material: Rp900.000 (100%) 

• Tenaga Kerja Langsung (TK): Rp600.000 (80%) 

• Overhead: Rp720.000 (40%) 

• Ditambahkan Tahun 2020 (1.800 unit): 

• Material: Rp14.100.000 

• TK Langsung: Rp4.920.000 

• Overhead: Rp4.320.000 

• Produksi Selesai: 1.600 unit 

• Sediaan Barang Dalam Proses Akhir: 

• Tingkat Penyelesaian: 

• Material: 100% 

• TK Langsung: 60% 

• Overhead: 20% 

Pertanyaan: 

Berapakah biaya sediaan barang dalam proses akhir tahun? 


A. Rp3.667.450 

B. Rp3.960.000

C. Rp5.112.000 

D. Rp3.280.00