PMG201c Mooc 3

PMG201c Mooc 3

1st - 5th Grade

30 Qs

quiz-placeholder

Similar activities

Morphology

Morphology

5th Grade

30 Qs

Untitled Quiz

Untitled Quiz

1st - 5th Grade

28 Qs

One Hen

One Hen

5th Grade

30 Qs

04. PASSIVE VOICE

04. PASSIVE VOICE

5th Grade

25 Qs

JOB APPLICATION LETTER

JOB APPLICATION LETTER

3rd Grade

30 Qs

word form anh

word form anh

2nd Grade

30 Qs

WWW list 3- ALL

WWW list 3- ALL

5th - 9th Grade

25 Qs

Luz Sees the Light

Luz Sees the Light

4th Grade

25 Qs

PMG201c Mooc 3

PMG201c Mooc 3

Assessment

Quiz

English

1st - 5th Grade

Medium

Created by

Le CT)

Used 2+ times

FREE Resource

30 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

True or False: A project manager spends 75% of his or her time communicating.

False

True

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which item would most likely NOT be part of a basic communication plan

The best medium for the communication.

The amount of their annual bonus.

With whom to communicate.

What they need to know.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Upward communication is communication to/from:

Your direct reports.

Your peers.

Your senior management.

Your social groups.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

When you report project status you compare actual performance to:

The performance of other similar projects.

The planned performance or baseline.

The performance of previous projects.

The performance of your competitors.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

True or False: Earned value integrates scope, schedule and budget and uses monetary values to assess project status

False

True

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

You are beginning to staff your project. Which of the following will not be used in developing and/or communicating roles and responsibilities?

Organization chart

Responsibility Assignment Matrix

Pareto chart

WBS

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is not likely to be documented in a communications management plan?

Person responsible for tracking risk events

What information will be communicated

Time frame and frequency of communication

How information will be communicated

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?