Project Management Practice Questions Day 7

Authored by Brian Nanns

Other

12th Grade

Used 7+ times

Project Management Practice Questions Day 7
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is scope creep?

Adding features outside the original scope without approval

Completing tasks ahead of schedule

Revising project objectives mid-project

Reducing the scope to save resources

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is gold plating in project management?

Adjusting the budget to reflect new resources

Adding extra features without stakeholder approval

Completing a project within the budget constraints

Increasing the scope through change management

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How can scope creep be prevented?

Allowing team members to add features independently

Implementing a strict change control process

Avoiding stakeholder involvement in planning

Reducing the project timeline

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the purpose of tracking performance metrics?

To ensure all team members follow the same work schedule

To monitor planned vs. actual project performance

To reduce the overall project scope

To document stakeholder communication

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the first step in resolving a variance in a project?

Communicating the variance to stakeholders

Identifying the root cause of the variance

Revising the project budget

Increasing resource allocation

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which scenario is an example of gold plating?

Adding an extra feature without approval

Removing a deliverable to save costs

Completing a task ahead of schedule

Reassigning tasks among team members

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the impact of unresolved variances on a project?

Improved project quality

Delays and increased costs

Reduced team productivity

Enhanced stakeholder satisfaction

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?