GMJ 6035 & 9189 phase 2 cold water pressure testing and flushing

Authored by Glen Johnson

Construction

Vocational training

Used 61+ times

GMJ 6035 & 9189 phase 2 cold water pressure testing and flushing
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the required internal water pressure for water fittings as per the Water Supply (Water Fittings) Regulations 1999?

A. 1.1 times the maximum operating pressure

B. 1.5 times the maximum operating pressure

C. 2 times the maximum operating pressure

D. 1.3 times the maximum operating pressure

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

According to WRAS guidance, what is the testing duration for rigid pipe systems without further pumping?

A. 30 minutes

B. 1 hour

C. 2 hours

D. 90 minutes

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In BS EN 806, what is the formula for calculating the maximum design pressure (MDP)?

A. 1.5 × maximum operating pressure

B. 2 × maximum working pressure

C. 1.65 × maximum operating pressure

D. 1.1 × maximum operating pressure

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

For a system with a maximum working pressure of 5 bar, what is the test pressure recommended by BS EN 806?

A. 7.5 bar

B. 6.5 bar

C. 8.25 bar

D. 10 bar

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During pre-commissioning checks, which of the following is NOT required?

A. Checking that all joints are made correctly

B. Ensuring adequate pipe supports

C. Testing with maximum allowable pressure

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What material requires pressure testing as per BS EN 806?

Copper tubes

Plastic pipes

Steel pipes

PVC pipes

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In WRAS Test A for plastic pipes, what is the final step?

Reducing pressure to one-third of the test pressure for 90 minutes

Pumping for 1 hour

No pressure drop for 120 minutes

Checking for leaks at full pressure

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?