GMJ 9189 phase 2 cold water pressure testing and flushing

GMJ 9189 phase 2 cold water pressure testing and flushing

Vocational training

15 Qs

quiz-placeholder

Similar activities

108 Basic Employment Skills #1

108 Basic Employment Skills #1

9th Grade

15 Qs

Job Application and Interview Concepts

Job Application and Interview Concepts

9th Grade

15 Qs

JRCTC 2025 POC  FINAL EXAMS

JRCTC 2025 POC FINAL EXAMS

12th Grade

20 Qs

307 Central Heating System 2 Quiz

307 Central Heating System 2 Quiz

2nd Grade - University

20 Qs

305 Cold water systems 3 Quiz

305 Cold water systems 3 Quiz

2nd Grade - University

18 Qs

Level 2 Cold Water Plumbing Exam - Version 2

Level 2 Cold Water Plumbing Exam - Version 2

12th Grade - University

18 Qs

305 Cold Water systems  2 Quiz

305 Cold Water systems 2 Quiz

2nd Grade

20 Qs

306 hot water systems 2 Quiz

306 hot water systems 2 Quiz

2nd Grade - University

20 Qs

GMJ 9189 phase 2 cold water pressure testing and flushing

GMJ 9189 phase 2 cold water pressure testing and flushing

Assessment

Quiz

Construction

Vocational training

Hard

Created by

Glen Johnson

Used 17+ times

FREE Resource

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the required internal water pressure for water fittings as per the Water Supply (Water Fittings) Regulations 1999?

A. 1.1 times the maximum operating pressure

B. 1.5 times the maximum operating pressure

C. 2 times the maximum operating pressure

D. 1.3 times the maximum operating pressure

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

According to WRAS guidance, what is the testing duration for rigid pipe systems without further pumping?

A. 30 minutes

B. 1 hour

C. 2 hours

D. 90 minutes

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In BS EN 806, what is the formula for calculating the maximum design pressure (MDP)?

A. 1.5 × maximum operating pressure

B. 2 × maximum working pressure

C. 1.65 × maximum operating pressure

D. 1.1 × maximum operating pressure

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

For a system with a maximum working pressure of 5 bar, what is the test pressure recommended by BS EN 806?

A. 7.5 bar

B. 6.5 bar

C. 8.25 bar

D. 10 bar

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During pre-commissioning checks, which of the following is NOT required?

A. Checking that all joints are made correctly

B. Ensuring adequate pipe supports

C. Testing with maximum allowable pressure

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What material requires pressure testing as per BS EN 806?

Copper tubes

Plastic pipes

Steel pipes

PVC pipes

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In WRAS Test A for plastic pipes, what is the final step?

Reducing pressure to one-third of the test pressure for 90 minutes

Pumping for 1 hour

No pressure drop for 120 minutes

Checking for leaks at full pressure

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?