Search Header Logo

Bai Tap PMP 12

Authored by Bui Hoang

Information Technology (IT)

University

Bai Tap PMP 12
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

70 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager and project team developing a new product are discussing which work methods and tools to use to build the deliverable. What should the result of this discussion be?

A. A detailed mitigation plan on the risks for each work method and the tools used
B. A technology roadmap for creating similar deliverables in the future with the same tools
C. An agreed-upon work method and tools that should fit the business need and project constraints
D. A consensus that everything will run as anticipated once the tools and work methods are identified

Answer explanation

Alignment with goals: Choosing work methods and tools should prioritize achieving the project's objectives and meeting the business's needs. This ensures resources are used effectively and deliverables align with expectations.Feasibility within constraints: Considering project constraints like time, budget, and available expertise is crucial. The chosen methods and tools should be realistic and achievable within these limitations.Team buy-in: Reaching agreement through discussion fosters ownership and commitment from the team. By understanding the rationale behind the chosen methods and tools, the team is more likely to be engaged and motivated to use them effectively.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager is instructed by the project sponsor to draft the project charter. The project sponsor asks the project manager to involve a particular stakeholder in order to provide necessary resources. However, the stakeholder is refusing to get involved because the stakeholder thinks that there is no benefit in using the project deliverable.What should the project manager do to resolve this?

A. Consider the stakeholder as a risk and evaluate possible solutions with the project team.
B. Escalate to the project sponsor due to the political nature of the issue.
C. Improve communication with the stakeholder to obtain their assistance in the future.
D. Meet with the stakeholder to discuss the impact of the deliverable.

Answer explanation

Open communication: A direct conversation allows the project manager to understand the stakeholder's reasoning for refusing involvement. Addressing concerns directly through respectful and open communication is often more effective than assumptions or escalation.Clarifying potential benefits: By engaging with the stakeholder, the project manager can explain the broader impact of the project deliverable and its potential benefits beyond the stakeholder's immediate purview. This could involve demonstrating how the deliverable aligns with the organization's strategic goals or could benefit other departments and initiatives.Collaborative solutions: The conversation might reveal alternative solutions or modifications to the deliverable that could address the stakeholder's concerns and encourage their participation. This collaborative approach fosters ownership and increases the chances of securing the necessary resources.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

While working on a proposal for a national-level solution, a new project manager finds that the proposal is asking for compliance from various organizations and policies. The project manager understands that while several compliances are in place, some of the specific regulatory needs for this project are not in place. Senior management advised the project manager to overlook these compliance problems, because they will be ready when that stage of the project is reached, and to continue building the proposal.What should the project manager do first?

A. Verify the regulatory requirements and establish a strategy for compliance.
B. Document the interactions with senior management in the risk register.
C. Advise senior management that itis ethically unprofessional to continue.
D. Build the proposal with an alternative set of regulatory requirements.

Answer explanation

No doubt is A

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A company's project management office (PMO) is incorporating more adaptive technologies and has hired a new project manager with hybrid project management experience. The team is slow in adopting the new methodology and has not been updating project artifacts in a timely manner.Which action should the project manager take to improve the team's performance?

A. Send an email asking all project team members to complete updates at the end of the day.
B. Speak individually with each project team member about making the needed updates.
C. Set up a training session for all project team members.
D. Reach out to the functional managers for support.

Answer explanation

C. Set up a training session for all project team members

5.

MULTIPLE SELECT QUESTION

30 sec • 1 pt

A company is launching a new product and decides to transition from a predictive to an agile approach. During the third sprint, the project manager notices that the team is not working as a cohesive unit.Which two rules are appropriate for the project manager to instill in the team? (Choose two.)

A. Work together daily as a team.
B. Strive toward continuous improvement.
C. Send communications to the entire team.
D. Follow the sprint planning.
E. Only share suggestions at the end of the sprint.

Answer explanation

A. Daily team collaboration: Frequent interaction strengthens communication, fosters trust, and allows for real-time problem-solving. This is crucial for building cohesion and overcoming the observed lack of unity. Daily stand-up meetings, pair programming sessions, or other collaborative activities can facilitate this interaction.B. Continuous improvement: An agile mindset embraces constant learning and adapting. Encouraging the team to identify and address areas for improvement, both individually and collectively, can spark innovation and boost team dynamics. This ongoing feedback loop promotes growth and helps the team learn and adapt together.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager is working on a large project with a very difficult client. During the course of the project, the project manager realizes that if the project team had a little more time and funding to make some minor changes, the client could realize the benefits of 25% of the project outcomes early.How should the project manager approach this?

A. Concentrate on the current project milestones.
B. Make all the changes and then show the client the results.
C. Develop a business case and submit it to the client.
D. Update the project management plan for this new work.

Answer explanation

C. Develop a business case and submit it to the client

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

A project manager identified a risk on a deliverable completed by a contractor and added it to the risk register. During the last inspection meeting for the deliverable, the project manager notices that the suggested mitigation did not produce the expected results.How should the project manager proceed?

A. Review the procurement performance to identify the root cause
B. Reevaluate the probability of the risk occurrence and mitigation strategy.
C. Issue a change request to apply the risk response plan for this risk.
D. Audit the procurement process to identify why the mitigation did not work.

Answer explanation

What should B help when it already happen? A audit is to identify all nonconformity. So D is my answer.

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?