Search Header Logo

PMP - Quality

Authored by Nguyễn Đạt

Education

University

Used 1+ times

PMP - Quality
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

35 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

When a product or service completely meets a customers requirements:

Quality is achieved.
The cost of quality is high.
The cost of quality is low.
The customer pays the minimum price.

Answer explanation

As a general rule, one cannot say that quality (as defined in the question) is either of high or low cost. It provides what the customer wanted, which may not be the lowest or highest cost. When a product or service completely meets a customer's needs, quality is achieved.

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

To what does the following definition refer? "The point where the benefits or revenue to be received from improving quality equals the incremental cost to achieve that quality."

Quality control analysis
Marginal analysis
Standard quality analysis
Conformance analysis

Answer explanation

This is the definition of marginal analysis. Know the term so you will be able to answer questions that deal with this concept. The other choices may sound good, but they are made-up terms.

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Who is ultimately responsible for quality management on the project?

The project engineer
The project manager
The quality manager
The team member

Answer explanation

Although each person working on the project should check their own work, the project manager ultimately has the responsibility for quality on the project as a whole.

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A project has faced major difficulties in the quality of its deliverables. Management now states that quality is the most important project constraint. If another problem with quality were to occur, what would be the BEST thing for the project manager to do?

Fix the problem as soon as possible.
Allow the schedule to slip by cutting cost.
Allow cost to increase by fixing the root cause of the problem.
Allow risk to increase by cutting cost.

Answer explanation

Allowing the cost to increase by fixing the root cause of the problem addresses both finding the cause and the probable impact of dealing with the problem.

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

A manager notices that a project manager is holding a meeting with some of the team and some stakeholders to discuss the quality of the project. The project schedule has been compressed, and the CPI is 1.1. They have worked hard on the project, the team has been rewarded according to the reward system the project manager put in place, and there is a strong sense of team. The manager suggests that the project manager does not have enough time to hold meetings about quality when the schedule is so compressed. Which of the following BEST describes why the manager is wrong?

Improved quality leads to increased productivity, increased cost effectiveness, and decreased cost risk
Improved quality leads to increased productivity, decreased cost effectiveness, and increased cost risk.
Improved quality leads to increased productivity, increased cost effectiveness, and increased cost risk.
Improved quality leads to increased productivity, decreased cost effectiveness, and decreased cost risk.

Answer explanation

Quality efforts should produce a decrease rather than an increase in cost risk as a result of less rework. Quality efforts should also provide increased cost effectiveness due to less rework.

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

From the project perspective, quality attributes:

Determine how effectively the performing organization supports the project.
Provide the basis for judging the project's success or failure.
Are specific characteristics for which a product is designed and tested.
Are objective criteria that must be met.

Answer explanation

Quality attributes are the measurements that determine if the product is acceptable. They are based on the characteristics of the product for which they were designed.

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

Quality is:

Meeting and exceeding the customers expectations.
Adding extras to make the customer happy.
The degree to which the project meets requirements.
Conformance to management's objectives.

Answer explanation

There can be a cost impact (or time, risk, etc.) of exceeding expectations or adding extras. Quality is the degree to which the project meets requirements.

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?