1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
The project has been going well, except for the number of changes being made. The product of the project is being installed into seven different departments within the company and will greatly improve departmental performance when operational. The team has selected the appropriate processes for use on the project. The project manager is a technical expert and has been trained in communications and managing people. Which of the following is the most likely cause of the project changes?
The project manager was not trained in understanding the company environment.
The project should have more management oversight since it will result in such great benefits to the company.
The project should have used more of the project management processes.
Some stakeholders were not identified.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
You have been tentatively assigned to a project that has not yet received final approval. Several stakeholders who will likely be involved or impacted by the project have already been identified. Stakeholders can be identified during which project management process groups?
Initiating, planning, executing, and monitoring and controlling
Initiating and planning
Planning and monitoring and controlling
Monitoring and controlling and closing
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following statements best describes how stakeholders are involved on a project?
They help to determine the project schedule, deliverables, and requirements.
They help to determine the project constraints and product deliverables.
They help to determine the resource needs and resource constraints on the project.
They approve the project charter, help provide assumptions, and create the management plans.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
You know that some groups within your organization are going to provide input to requirements that may impact your ability to develop a realistic schedule. Managing stakeholder expectations is always important, but achieving stakeholder satisfaction will be more critical with some groups than with others. All the following are parts of the team's stakeholder management effort except:
Determining stakeholders' needs
Identifying stakeholders
Giving stakeholders added value
Managing stakeholders' expectations
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
You are working on a project that requires the use of a stakeholder engagement assessment matrix. This tool can be used to identify:
Additional stakeholders
Variances from anticipated stakeholder involvement
Key relationships between stakeholders
Skill levels of stakeholders
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
You are managing a project to develop an organization's new website. The site will be highly complex and interactive, and neither your project team nor the client has much experience with this type of website development. The timeline is extremely aggressive. Any delay will be costly for both your firm and the client. You and the project sponsor have achieved agreement and sign-off on both the project charter and the project management plan. Client personnel have been kept fully informed of the project's progress through status reports and regular meetings. The project is on schedule and within budget, and a final perfunctory review has been scheduled. Suddenly you hear that the entire effort may be canceled because the product being developed is totally unacceptable. What is the most likely cause of this situation?
A key stakeholder was not adequately engaged in the project.
The project charter and project management plan were not thoroughly explained to or adequately reviewed by the client.
Communications arrangements were inadequate and did not provide the required information to interested parties.
The project sponsor failed to provide adequate support for the project.
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In managing a change-driven project, which aspect of stakeholder management is most important?
Making sure the team members are fully occupied at all times
Planning the team members' interactions with other stakeholders
Leaving the team alone to solve their own problems
Ensuring a shared understanding of the project goals
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?