L4M3 Commercial Contracting Recap Week 4

Authored by Helen Stone

Other

Professional Development

Used 1+ times

L4M3 Commercial Contracting Recap Week 4
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following should be applied when tracking how often deliveries are on time during the contract?

Binary measure

Numerical measure

Subjective measure

Qualitative assessment

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the name of the clause that frees the parties from their contractual duties when unexpected events like natural disasters or terrorist attacks happen?

Indemnity clause

Liquidated damage clause

Exclusion clause

Insurance clause

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following shall help the purchaser control the selection of tier 2 suppliers?

Insurance clause

Guarantee clause

Warranty clause

Subcontracting clause

4.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

Which of the following are likely to be express terms in a contract?...Choose TWO that apply

Legislation

Custom and Practice

Contract particulars

Terms and conditions

5.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

What methods do buyers use to pick suppliers from a framework agreement? Select TWO that apply:

 

Call off contract

Mini competition

Contract for lease

Rescission of contract

Direct call-off

6.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

Which of the following would be useful tools to encourage the supplier to innovate throughout the contract?

Gainshare arrangement

Liquidated Damages

Service Credits

Fixed Bonus Payments

7.

MULTIPLE SELECT QUESTION

45 sec • 1 pt

Which of the following are reasons why a purchaser wants to embed a subcontracting clause into the main contract? Select TWO that apply:

To reduce the main contract complexity

To improve supply chain transparency

To induce the conflicts between the main contractor and subcontractors

To keep main contractor liable

To condemn whole liabilities to subcontractors

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?